19-1043B_RFI_Response.pdf
PDF 121 KB Posted
- Attached to
- 19-1043B, Replace Door with Automatic Door, Bldg. 6670 Federal contract opportunity
- Solicitation number
- FA4610-19-R-A041
About this file
Response to RFI Questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch_1_SOW_20190812.pdf | ||
| Solicitation_Amendment_FA461019RA0410001_SF_30.pdf | ||
| 19-1043B_Site_Visit_Minutes.pdf | ||
| 19-1043B_SV_Sign_In.pdf | ||
| Atch_5_QC_Plan_01_45_00.pdf | ||
| FA461019RA041_19-1043B_Solicitation.pdf | ||
| Atch_2_Door_Photos.pdf | ||
| Atch_3_General_Requirements_01_00_00.pdf | ||
| Atch_6_Environmental_01_57_20.pdf | ||
| Atch_4_Submittal_Procedures_01_33_00.pdf | ||
| Atch_1_SOW_20190620.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
30TH SPACE WING (AFSPC)
GUARDIANS OF THE HIGH FRONTIER
27 August 2019
MEMORANDUM FOR 30CONS/PKA
ATTN: Ms. Alyson Kolding, CS
FROM: 30 CES/ CENMP
SUBJECT: Response to Request for Information (RFI# 01); Project XUMU19-1043B, Replace Door with Automatic Controlled Door Bldg. # 6670.
1. The following is provided in response to your e-mail request, dated 23 August 2019 and the Contractor’s RFI (Request for Information) #01 list.
a. Specifications Section 01 45 00 indicates the CQC System Manager may have other duties such as Project Superintend. May he also be the Site Safety Health Officer? One person wearing all three hats?
Yes, the Government authorized contractor to use one person wearing multiple hats.
b. Do the walls contain any lead base paint or asbestos containing materials? Can the Government provide a hazardous material survey report?
Government identified that the walls does not contain lead based paint and no asbestos containing material, Contractor to confirm.
c. Must all new electrical conduit runs be concealed either above the t-bar ceiling or inside existing walls?
The contractor shall concealed all new electrical conduits above the T-bar ceiling.
d . Please confirm the scope of work includes installation of an automatic interior and exterior wall push plates.
Yes, the door will open automatic from both directions but with sensor controlled instead of wall push plates.
3. Should you have any further questions or details concerning the above subject project, please contact the undersigned at (805) 605-4759.
ROLANDO D QUIZON, GS-11, DAF
Project Manager, SABER/PAVING IDIQ
| 2019-08-27T09:32:01-0700 | |
| QUIZON.ROLANDO.1184362038 |