Attachment 3 - Statement of Work v3.pdf

PDF 687 KB Posted

Attached to
Building Lettering For 2 AMXS Federal contract opportunity
Solicitation number
FA460824QC133
Issued by
Department of the Air Force Global Strike Command

About this file

This document is a Statement of Work (SOW) for building lettering services on two hangars at Barksdale Air Force Base (AFB) in Louisiana. The work includes removing old lettering, patching holes, painting, and installing new injection molded plastic lettering in dark brown Helvetica font, 12 inches high. The work must be completed within 60 days of award. The contract is a small business set-aside with a NAICS code of 236220 and a $45 million size standard. The solicitation number is FA460824QC133, with a due date of 1 PM CDT on July 19, 2024. The contracting office is the Department of the Air Force, Air Force Global Strike Command. Key points of contact are provided. The SOW includes security, safety, and housekeeping requirements for the contractor.

View the file

Other files for this federal contract opportunity

Other files attached to Building Lettering For 2 AMXS, newest first.
File Type Posted
Amendment 01 - 24QC133.pdf PDF
Attachment 1 - Provisions and Clauses.pdf PDF
Attachment 3 - Statement of Work (SOW).pdf PDF
Combined Synopsis Solicitation - 24QC133.pdf PDF
Attachment 2 - Salient Characteristics.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3 – Statement Of Work

FA406824QC133

Statement of Work

Building lettering v3, dated 12 July 2024

20th Bomber Generation Squadron

96th Bomber Generation Squadron Non-Flightline side

1. SCOPE / DESCRIPTION OF SERVICES: The work covered by these requirements consists of furnishing all plans, materials, labor, equipment, appliances, and performing all operations to remove/install building lettering on both hangars to include paint touch-ups if necessary.

2. DELIVERY AND INSTALLATION: Sixty (60) Days ARO.

3. BACKGROUND: 2 AMXS is dissolving and standing up as the 96th BGS and 20th BGS. Each squadron is operating under their respective buildings. Squadron identifying lettering is required on 2 buildings, totaling four hangars.

4. LOCATION: 315 Lindbergh Rd East Bldg 6415, Hangars 6 &5 Non- Flightline Side

339 Lindbergh Rd East Bldg 6238, Hangars 11 & 10 Non- Flightline Side Barksdale AFB (BAFB), LA

• 2.1. HOURS OF OPERATIONS. Normal hours of operation for this contract are between hours of 0800 and 1600 hours. The contractor shall perform the services required under this contract during this time excluding Saturdays, Sundays, and Federal Holidays.

5. REQUIRMENTS (OVERVIEW): The work covered under this Statement of Work shall consist of furnishing all material, labor, and equipment in performing all operations necessary to remove/install Building Lettering on both hangars to include paint touch ups if required. All lettering will be injection molded plastic and 12 inches in Helvetica font in dark brown.

Building 6415 Hangars 6 & 5 Non-Flight line side

a) Hangar 6

a. Remove original lettering “20th Bomb Squadron” (Do not Dispose)

b. Patch holes in building, clean surrounding area as best as possible and Paint over patches to best match paint of existing building and taper in edges.

c. Install original “20th Bomb Squadron”

d. Install new “20th Bomber Generation Squadron” below “20th Bomb Squadron”

Final Look Below

20th Bomb Squadron

20th Bomber Generation Squadron

b) Hangar 5

a. Remove original lettering “20th Aircraft Maintenance Unit” (Dispose of)

b. Patch holes in building, clean surrounding area as best as possible and Paint over patches to best match paint of existing building and taper in edges.

c. Install New “20th Bomber Generation Squadron” and “Sortie Support Flight” in its place

20th Bomber Generation Squadron

Sortie Support Flight

Building 6238 Hangars 11 & 10 Non-Flight line side

c) Hangar 11

a. Removal of old lettering if any exist (Dispose of).

b. Patch holes in building, clean surrounding area as best as possible and Paint over patches

c. Install New “96th Bomber Generation Squadron” and “Sortie Support Flight”

Sortie Support Flight

d) Hangar 10

a. Remove old lettering “2d Aircraft Maintenance Squadron” and “96th Aircraft

Maintenance Unit” (Dispose of)

b. Patch holes in building, clean surrounding area as best as possible and Paint over patches

c. Install new “96th Bomber Generation Squadron” below “96th Bomb Squadron”

96th Bomb Squadron

6. SECURITY REQUIREMENTS: Visitor Passes: To receive a visitor pass the contractor must complete an (S5 Pass) AF Form 75 Visitors/ Vehicle Pass. The contractor should contact TSgt Lafosse/SSgt Miller at (318) 456-3687 or (318) 456-2356, once the driver is 30 min from the East Gate (industrial gate), so an escort can be provided to meet the driver, and/or installation crew, to get their visitor pass (S5 Pass). Once the form is filled out, send the form back to S5 (email is on the form). S5 will conduct a background check, after 7-10 days the sponsor will meet the contractor at the East Gate Visitor Center and escort the contractors to S5 to receive a temporary I.D. for the duration of the project. The contractor vehicle must be inspected for any contraband upon arrival to East Gate anytime they need to gain access to the installation. This information will be reviewed and forwarded to 2 SFS/S5 Pass & Registration Office. If a pass is approved, the 2 SFS/S5 Pass & Registration Office will issue an AF Form 75 (Visitor Pass) to the contractor and his/her employees upon completion of screening process for the duration of the contract. The screening process takes time, and the contractor shall visit the Commercial Visitor Control Center prior to expecting base entry to receive required forms and instruction on the application process, to include estimated time of receiving the visitor pass. Other option is for the contractor to contact TSgt Lafosse/SSgt Miller at (318) 456-3687 or (318) 456-2356, once the driver is 30 min from the east gate (industrial gate), so an escort can be provided to meet the driver, and/or installation crew, to get their visitor pass. Although contractors will not be issued vehicles passes, vehicles are subject to search while on the installation. Employee privately owned vehicles will not be allowed access to restricted/controlled areas without a free zone being established. All Contractor vehicles should have markings with the company name for quick identification of ownership and notification if they are involved in an incident. Conduct Requirements: The contractor shall ensure that his/her employees comply with all base traffic regulations and properly conduct themselves while on the base.

• 5.1. Retrieving Identification Media. The Contractor shall be responsible for retrieving all identification media including vehicle passes from employees who depart for any reason before the contract expires (e.g., terminate for cause, retirement, etc.)

• 5.2. The Contractor and contractor employees shall comply with base traffic regulations.

• 5.3. Weapons, Firearms, Ammunition. Contractor employees are prohibited from possessing weapons, firearms, and ammunition on themselves or within their contractor or privately owned vehicles while on base.

• 5.4. The Contractor shall be responsible for safeguarding all government property, and controlled forms provided for contractor use. At the end of each work period, Contractor shall secure all Government facilities, equipment, and materials.

• 5.5. The contractor shall be responsible for the quality of all completed look. The contractor shall also ensure that furniture has been inspected for durability, material defects, and physical operational checks of office furniture completed. The contractor will be responsible for safeguarding government property.

7. SAFETY: The Contractor shall have a safety plan for their employees. The Contractor shall instruct each employee in the recognition and avoidance of unsafe conditions and regulations to his or her work environment to control or eliminate any hazards or other exposure to illness or injury. The Contractor shall provide their employees appropriate Personal Protective Equipment (PPE) and mandate proper wear.

• 6.1 Accident/Incident Reporting and Investigation. Contractor shall record and report to the 2d Security Forces Squadron Law Enforcement Desk at (318) 456-2551 all available facts relating to each instance of accidental damage to Government property or injury to either Contractor or Government personnel. The Contractor shall secure the accident scene and wreckage until released by the accident investigative authority through the 2d Security Forces Squadron POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is complete.

8. HOUSEKEEPING: The Contractor shall keep all facilities and work areas clean and neat

IAW industry, Occupational, Safety and Administration (OSHA), fire and safety standards.

9. PROJECT LIAISONS: TSgt Lafosse (318) 456-3687 & SSgt Miller (318) 456-2356

BLDG 6415 HANGAR 5

BLDG 6415 HANGAR 6

BLDG 6238 HANGAR

File details come from the government source that posted it. Updated .