This document is a Questions and Answers (Q&A) file for the B436 O'Malley Inn Demolition project. The solicitation covers a one-time demolition service with several key specifications: the project involves demolishing a building and associated infrastructure, with no additional funding modifications if hazardous materials are found. Contractors are expected to assume the presence of asbestos and have a plan for abatement as stated in the Statement of Work. The project requires specific demolition parameters, including maintaining the parking lot, demolishing sidewalks to the back of existing curbs, and focusing storm sewer demolition only on roof drains and associated storm piping to the main.

Key technical requirements include using 95% modified backfill with ±3% moisture, and the contractor may utilize small skid loaders for interior building demolition, subject to verification by a licensed structural engineer. No bid bonds are required, and all digitized as-built drawings will be issued to bidders. The government acknowledges potential inaccuracies in hazardous material assessments and advises contractors to calculate risk within their quotations. The existing trash enclosure will also be demolished, and trucks will need to process through the search pit during regular business hours.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B436 O'Malley Inn Demo Questions Questions Answers

If asbestos / hazardous materials are found, will the funding for the abatement be available?

Will there be any delay in funding if needed for the abatement of hazardous materials if they are found?

Will the project manager need a bachelor's degree if they can demonstrate ten years or more of experience in demolition projects of the same size and magnitude?

Are bid bonds required for this project?

No As-Built drawings were included in the solicitation. Will these be made available prior to bid date?

Given the fact that the hazardous material survey is part of the project, does the base intend to allow adjustments to the cost estimate and duration of this project based on the rewsults of the survey post award?

No, USG does not have that technical information available.

As this solicitation is for a one time service, there will not be modifications if asbestos is found. The contractor should assume its presence and plan for abatement as stated in the SOW.

As this is a one time service, there will be no additional funding if hazardous materials are found. Therefore, no delay in funding.

No. That level of demonstratable experience is acceptable with appropriate documentation.

No, bid bonds are not required.

Yes, all digitized as-built drawings in our possession will be issued to bidders

Will the owner supply a topographic map of the area of the project prior to the bid date to allow proper estimating?

As this is a one time service, there will be no additional funding if hazardous materials are found. The contractor should assume its presence and plan for abatement as stated in the SOW.

Since storm sewer line drains turn around, storm shall be maintained and only storm demo shall be roof drains. Roof drains and associated storm piping to be demo'ed to the main.

No. Parking lot shall be maintained. Sidewalks on site shall be demolished to the back of existing curbs.

Will the storm sewer connections be demolished originating at the surface inlet at the NW corner of the building or does the base wish to leave this intact at this time?

Is the intent of this project to remove the associated parking area to the South of the building? Please indicate limits of demolition.

Is existing trash enclosure to be demolished? Yes

Current project documentation does not indicate compaction reqruirements for building void backfill or general grading. Please specify these requirements.

Contractor intends to utilize small skid loader(s) for interior building demo.

This feasibility of this method will be evaluated by a licensed engineer to verify structural integrity of the building. This method will enable contractor to separate non-recyclable building materials from those that can be recycled. Will the base consider this approach to building demolition in principle?

No. Contractor shall assume that all trucks will need to process through the search pit during reglar business hours.

95% modified with +\-3% moisture

Yes, as long as it is vetted by a liscensed structural engineer.

Yes, what is available will be provided. Please note that some of the identified asbestos MAY have already been removed. Contractor to verify. Additional site visit can be facilitated if need be.

unknown. The survey is required for the Government's knowledge of how much asbestos was present within the facility. The Government acknowledges the potential for inaccuracy & advises all prospective offerors to assume & calculate risk within their quotations based on the

Have any previous harazrdous material surveys been performed on this structure? If so, will they be provided prior to bid submission to allow for more accurate pricing?

We're unable to provide accurate pricing on asbestos abatement without first conducting the asbestos survey, which will not be conducted until after award of the contract. How is it suggested that pricing be made for the abatement without survey results?

Will the base make lane 5 at the SAC gate available for trucks for the demo and grading on this project?