Solicitation Amendment 01 FA460025B00010001 SF 30.pdf
PDF 1 MB Posted
- Attached to
- Demolition Bldg. 404, Offutt AFB, NE
- Solicitation number
- FA460025B0001
About this file
This document is a Standard Form 30 (SF 30) Amendment to Solicitation FA460025B0001 for a demolition project at Offutt Air Force Base in Nebraska. The amendment makes three key modifications: (1) changes the unit of measure for Line Item 0001 from "each" to "lot", (2) updates the Contract Drawings and Specifications clause with detailed requirements for handling contract drawings, and (3) replaces the previous Bid Opening and Submission Information attachment with a new version labeled "Amend 01".
The solicitation is a 100% small business set-aside for demolishing Building 404 and associated site elements, with a project magnitude between $1-5 million under NAICS code 238910. Key dates include a mandatory site visit on 15 April 2025 at 2:00 PM CST, with questions due by 23 April 2025 at 10:00 AM CST. Electronic bid submissions are required via email, and bid opening will be conducted via teleconference the business day following the submission deadline. The project is being executed by the Department of the Air Force Air Combat Command.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
Created On:
01 Apr 2025, 10:01 AM Central Daylight Time
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section B - Supplies or Services & Prices or Costs
Line Item 0001
The following Line Item modifications were made:
INFORMATION FROM TO
Unit of Measure Each Lot
Section I - Contract Clauses
Additional Information/Notes
The following Clauses modifications were made:
252.236-7001 Contract Drawings and Specifications. Aug 2000 hereby reads as follows:
As prescribed in 236.570(a), use the following clause:
CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall-
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing No.
Drawings, dated 12 Apr 2022
Specifications, dated12 Apr 2022
OFF-B-6473
21-047
(End of clause)
Section J - List of Attachments
The following Attachments were added:
Amend 01 - Bid Opening and Submission Information
The following Attachments were deleted:
Bid Opening and Submission Information.
FA460025B00010001
| SUMMARY OF CHANGES |
| Supplies or Services & Prices or Costs |
| Contract Clauses |
| List of Attachments |
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0001 |
| EffDate: 01 Apr 2025 |
| ReqNo: |
| ProjNo: SGBP 19-0018 |
| IssCode: FA4600 |
| AdmCode: |
| IssuedBy: FA4600 55 CONS PKP |
BLDG 323C CP 402 232 6459, 106 PEACEKEEPER DR STE 2N3
OFFUTT AFB, NE 68113
UNITED STATES
Elizabeth Dennis, Email: elizabeth.dennis.2@us.af.mil Telephone: 271-4097 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA460025B0001 |
| SolDate: 31 Mar 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: a) Amend attachment 01 to correct bid due date. |
b) Change unit of measure in CLIN 0001 from "each" to "lot".
c) Update fill-in data in DFARS Clause 252.236-7001.
| ContNameTitle: |
| CoNameTitle: |
| ContDate: |
| CODate: |