RFI__2_.pdf
PDF 14 KB Posted
- Attached to
- A-E Services IDIQ Federal contract opportunity
- Solicitation number
- FA4600-18-R-AE01
About this file
Question & Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF330.pdf | ||
| RFI__7.pdf | ||
| RFI__6_.pdf | ||
| RFI__5.pdf | ||
| RFI__4.pdf | ||
| RFI__3.pdf | ||
| RFI__1_Q_&_A_.pdf | ||
| A-E_Synopsis,_26_Jan_18.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
All questions will be answered and posted in this format on a weekly basis to FBO.
RFI # Question Answer 1 Submission Requirements, Section H indicates that responders are to submit copies of project performance evaluations. Each project evaluation typically consists of 3 to 4 pages. Do the project performance evaluations count against the 50 page response limit?
No. The project performance evaluations do not count against the 50 page response limit. All past performance evaluations are to be included at the end of Section H and clearly identified as such to preclude from being included in the 50 page response limit.
2 Can an Engineering firm submit as prime as long as the team consists of all the required disciplines?
Yes. An Engineering firm can submit as prime as long as the team consists of all the required disciplines.