- Construction of RV Lot
- Solicitation number
- FA4600-11-B-0008
About this file
This is the SOW for the RV lot.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determination.pdf | ||
| Atch 7 Bidders Checklist.doc | DOC document | |
| solicitationrvlot16Jun.pdf | ||
| drawings.pdf | ||
| Atch 6 Financial Institution Reference Sheet.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
RV STORAGE LOT – EXPANSION SITE
Location: Work will be conducted to the southeast of the AFWA parking lot, immediately north of the motorcycle safety course.
Period of Performance: All work shall be done between the hours of 7am and 6pm Monday thru Friday. The project must be completed no later than 14 days
Schedule: The contractor will provide the Contracting Officer (CO) or Contracting Officer’s Representative (COR) with a written work schedule for approval before any work is performed.
Work Included: Contractor shall perform the following
1. Contractor shall obtain required digging permit before work proceeds.
2. Contractor shall provide installation of the posts, fence, and gate on the specified concrete parking lot surface.
3. Contractor shall provide electrical connection from the gate to the electrical source provided at approximately 300’ away.
4. Contractor shall provide all excavation, site work, and cleanup.
5. Contractor shall place fencing perimeter at exact specifications approved by the base civil engineers.
6. Contractor shall provide any other installation requirements to make the gate and fencing fully operational at conclusion of project.
7. Contractor work must be in compliance with the Davis Bacon Act.
Workmanship: Contractor shall perform all work in accordance with all local, state, and federal laws, regulations and building codes. Contractor is responsible for all field measurements and digging permits for proper installation. All work shall be done in accordance with all existing commercial standards.
Disposal: Contractor shall clean up and dispose of all related debris off Government property.
Inspections: Government will perform pre-final and final inspection prior to completion of project
Materials and Equipment:
1. Government will provide specified location for the fence and gate.
2. The fence must be 8’ tall, brown steel, shadow box design, overall length 770’ including the 24’ wide chain link cantilever gate. The RV lot is 185 feet by 200 feet.
3. The gate must be 8’ tall, 24’ wide galvanized chain link electric operated cantilever gate.
4. An electric cantilever gate operator with 2 each (outside and inside gate) key pad mounted on gooseneck stands, with 480 code keypad.
5. Contractor will provide the proper tools and equipment to install the fence, gate, and keypad stands.
6. Government will ensure the area is open and available for contractor to perform work between 7am and
6pm Monday thru Friday.
7. Contractor must notify Project Coordinator on days available to work on specified area at least 10 business days in advance.
8. Contractor is encouraged to contact the Project Coordinator for a site survey to ensure all total scope of the project is understood. Site survey will be at no expense to the government.
Warranty: All labor will be under warranty for 1 year for workmanship and repairs
Project Coordinator:
Ms. LeAnn Clausen: Outdoor Recreation (402) 294-2108