This file contains a Questions and Answers document for a cranes and hoist maintenance contract opportunity. The government has provided responses to 14 questions from prospective contractors regarding the requirements and contract details.
The incumbent contractor is Keystone Maintenance Services Corporation with contract number FA449721C0001 valued at $679,084.50. The scope and frequency of services remain unchanged from the previous contract, and there were no performance issues with the incumbent. All cranes and hoists are located inside facilities with a few mobile units belonging to the CE HVAC section, and no equipment is scheduled for upgrades or decommissioning. The contractor must provide all testing and NDI equipment, and while no emergency calls have occurred historically, an emergency repair CLIN is included for contingency purposes. All repairs are identified during quarterly inspections and approved by the Contracting Officer's Representative (COR). Crane and hoist locations are detailed in Appendix C of the Performance Work Statement (PWS), certification requirements are specified in paragraph 1.2.2.1, and emergency response requirements are outlined in paragraph 1.3.4. Contractors will receive base access badges upon award, all questions must be directed to the Contracting Officer via email, and no budget magnitude or Independent Government Cost Estimate (IGCE) was provided for this requirement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0005.pdf | ||
| Attachment 2 - Quote Schedule.xlsx | XLSX spreadsheet | |
| Attachment 2 - Quote Schedule.xlsx | XLSX spreadsheet | |
| Attachment 3 - Provisions and Clauses.pdf | ||
| Attachment 1 - Performance Work Statement.pdf | ||
| Attachment 2 - Quote Schedule.xlsx | XLSX spreadsheet | |
| Attachment 5 52.212-1 Instructions to Quoters.pdf | ||
| Attachment 4 - Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cranes and Hoist Maintenance Questions
1. Is there an incumbent currently doing this work? If yes, could you share their name, contract number, and award amount?
Answer: Yes. Keystone Maintenance Services Corporation, FA449721C0001, $679,084.50.
2. Has the scope or frequency of services changed from the previous contract?
Answer: No.
3. Were there any issues or challenges with the previous contractor’s performance?
Answer: No
4. Is there a list of crane and hoist locations available for review?
Answer: Yes, it located in Appendix C of the PWS.
5. Do we need to supply all testing and NDI equipment, or does the government provide any of it?
Answer: Yes, the Contractor is required to supply all testing and NDI equipment
6. About how many emergency repair calls come in each month on average?
Answer: We have not gotten any emergency calls, but we need this CLIN just in case. All repairs are identified during the Quarterly Inspection, reviewed and approved by the COR for execution.
7. Are all units inside, or do some require outdoor work or extra safety/weather prep? All
Answer: All units are located inside the facilities. There are a few mobile units that belong to the CE HVAC section.
8. Are any of the cranes scheduled for upgrades or decommissioning during this period?
Answer: No.
9. What are the expected response times for emergency repairs?
Answer: Paragraph 1.3.4 In the PWS states the requirement for Emergency response.
10. Will we need escorts or base access paperwork for our subcontractor techs?
Answer: Yes, the contractor will be given a contractor badge for access to the base once the contract is awarded.
11. Is there a government maintenance rep (GTR) we can speak with before or after award for technical clarification?
Answer: All questions must be submitted to the Contracting Officer via email.
12. Are there any surge requirements we should be aware of during deployments or exercises?
Answer: No
13. Are OSHA, ANSI, and NCCCO the only acceptable certifications, or could you consider equivalent military or manufacturer certs?
Answer: Paragraph 1.2.2.1 in the PWS states the requirements.
14. Lastly, is there a ballpark budget or IGCE for this work, to make sure we are within range?
Answer: There is no magnitude required for this requirement.