This document is a set of Questions and Answers related to Solicitation FA449724R0005, which is for a construction service to clean and re-coat high-voltage insulators and replace circuit breakers and protective relays at the Dover AFB North Substations.
The key details are: The government will provide existing CAD as-built/record drawings upon award. The maximum allowable downtime for the substation is 60 days between October 1 and April 30. Metering is not required, but touch screen/visual displays are required for the relays. The government's preferred relay and switch manufacturer is Schweitzer Engineering Laboratories (SEL), but other brands meeting the salient characteristics in the Statement of Work are acceptable. The entire relay enclosure can be replaced. The solicitation is being issued by the Department of the Air Force Air Mobility Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 01 Atch 01 - B614 SOW 16Apr24.pdf | ||
| Amendment FA449724R00050001 SF 30.pdf | ||
| Solicitation - FA449724R0005.pdf | ||
| Atch 3 - Wage Determination_DE2024007_dated 05 Jan 2024.pdf | ||
| B614 Solicitation - FA449724R0005.pdf | ||
| Atch 2 - B614 Bid Schedule.xlsx | XLSX spreadsheet | |
| Atch 1 - B614 SOW 22 Jun 23.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
436th Contracting Squadron (AMC)
639 Atlantic Street Dover AFB, Delaware 19902-5016
18 April 2024
MEMORANDUM FOR ALL OFFERORS
FROM: 436 CONS/PKAA
639 Atlantic St Dover AFB, DE 19902
SUBJECT: FA449724R0005, B614 Maintain Substation Insulators and Replace Relays, Solicitation Questions and Answers
1. Are existing CAD as built/record drawings available for this substation?
GOVERNMENT RESPONSE: Yes, what we have will be provided upon award.
2. What is the allowable maximum downtime for the substation to be taken offline?
GOVERNMENT RESPONSE: 60 days between October 1 and April 30.
3. Is metering going to be required?
GOVERNMENT RESPONSE: No
4. Are touch screen/visual displays a requirement for the relays?
GOVERNMENT RESPONSE: Yes
5. What is the government’s preferred manufacturer for relays and switches?
GOVERNMENT RESPONSE: Schweitzer Engineering Laboratories (SEL) but it is not required. Offerors providing SEL brand will not be found more favorable than those proposing another brand meeting the salient characteristics listed in the Statement of Work (SOW).
6. Is it acceptable to the government for the entire relay enclosure to be replaced?
GOVERNMENT RESPONSE: Yes