SOLICITATION NUMBER FA4497-11-R-0010
CONTRACT NUMBER
-1-
MATERIAL SUBMITTAL SCHEDULE
EXTERIOR PAINT REQUIREMENTS CONTRACT
PROJECT NUMBER: 111102
NOTE: Submittals shall be made on AF Form 3000 within 10 days from the issuance of the Notice to Proceed, unless otherwise approved. Each submittal item shall be listed separately on the form with the "Item No." on the form corresponding to the item number on this schedule. Submittals required by specification and/or drawing shall be made regardless whether or not they are listed below. The type of submittal required for each item shall be identified by the following letter code:
A - Catalog Cuts/Technical Literature F - Color Selection B - Sample G - Control
Diagram C - Certification H - Delivery
Tickets D - Shop Drawings I - Manufacturer's
Instructions/ Manuals
E - Test Results J - Other K -
Material Safety Data Sheets (MSDS)
Item Item Description Submittal
Code Reference Date
Approved by CO
1 MSDS/HazmatChemical Worksheets
K 01 20 00
2 Recycling of Materials K 01 20 00 / Part C 3 Inspector Certificates C,K 01 45 00 / 1.2 4 Waste Management Records J 02 42 00 / 1.3
5 Concrete Rehabilitation A,C,E,I 03 01 30 / 1.3
6 Color Samples B,F 09 06 90 /1.2
7 Thin Film Flooring B,C,E,F,I,J 09 62 51/1.2
8 Epoxy Mortar Flooring B,C,E,F,I,J 09 62 52 /1.2 9 Fluid Applied Flooring A,B,C,D,F,I 09 62 53 /1.2 10 Resilient Flooring A,B,E,F,I 09 65 00 /1.2
--End of Material Submittal Schedule— Attachment 4