Questions and Answers_060326.pdf

PDF 87 KB Posted

Attached to
Repair fiber optic and copper cables at Ft. Dix Bowling Center
Solicitation number
FA448426Q0022
Issued by

About this file

This file is a Questions and Answers document for federal solicitation FA448426Q0022, dated 3 June 2026, addressing clarifications on a repair project involving telecommunications infrastructure.

The solicitation pertains to repair and restoration work for damaged conduit, fiber optic cable, and copper cable infrastructure. Key scope clarifications include: excavation and restoration are limited to grassy areas only, with no asphalt or concrete restoration anticipated; cable lengths (12-strand fiber optic and 25-pair copper) are indicated in illustrations provided in the Performance Work Statement; and the conduit replacement scope is limited to the damaged section near a utility pole with a bypass route, requiring no full conduit replacement to the building unless additional damage is discovered during execution. Contractors should reference the Performance Work Statement and Statement of Work for detailed specifications regarding cable routes and bypass routes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA448426Q0022 Questions and Answers

3 June 2026

Q: Please confirm whether excavation and restoration are limited to dirt/grass areas or if asphalt/concrete restoration should be anticipated.

A: Excavation is limited to the grassy area of the repair.

Q: Please provide the approximate route length of the existing 12-strand fiber optic cable and 25-pair copper cable for estimating purposes.

A: Fiber/Copper length are indicated on the illustrations provided in the Performance Work Statement (PWS).

Q: Please confirm that the conduit scope is limited to repair/bypass of the damaged section near the utility pole and does not require full conduit replacement to the building unless additional damage is discovered.

A: Solicitation is for replacement of the damaged section of conduit(s) only, see the statement of work for bypass route.