STATEMENT OF WORK

FOR

AIRFIELD LINESTRIPING,

RUBBER REMOVAL &

FRICTION TESTING

AT

JOINT BASE MCGUIRE-DIX-LAKEHURST

REV NO. V02

9 February 2023

TABLE OF CONTENTS

SECTION

TITLE PAGES

DIVISION 1

01000

GENERAL REQUIREMENTS

Statement of Work

2 - 6

01012 Special Conditions 7 - 8

01200 Special Provisions 9

01300 Submittal Procedures 10 - 12

DIVISION 2

SITE WORK

02761

Pavement Markings

13 - 16 02951 Runway Rubber Removal and Recovery/Friction

Testing 17 - 20

SECTION 01000

STATEMENT OF WORK

1.1 DESCRIPTION OF WORK: The Contractor shall provide all supervision, management, quality control, labor, tools, equipment, appliances, transportation, supplies and materials and perform all work necessary to apply markings on all airfield pavements located on Joint Base McGuire- Dix-Lakehurst (JB MDL). The scope of work shall also include runway rubber removal, friction testing, and paint removal. The physical work site parameters encompass all airfield pavement areas to include but not limited to: runways, taxiways, parking aprons, streets, and parking lots. This scope of work does not include areas outside the airfield areas.

1.2 LOCATION: The work site is located at various locations on Joint Base McGuire Dix Lakehurst (JB MDL), NJ.

1.3 PRINCIPAL FEATURES: The work to be performed includes the principal features listed below. This general outline of principal features does not in any way limit the responsibility of the Contractor to perform all work and furnish all plant, labor, and material required by the specifications and drawings to perform a complete and permanent job to adequately fulfill the intent of these specifications and to deliver a work product(s) that is fit for its intended purpose. The inspection clause of any resultant contract for this work shall not in any way be interpreted as waiving the Government's requirement that the work product(s) be fit for its intended purpose.

1.3.1 AIRFIELD PAVEMENTS REQUIREMENTS:

Pavement marking, remarking, and marking removal services for airfield runways, taxiways, parking aprons, streets, parking lots & loading zones, etc. within the airfield areas.

Rubber removal from runway surfaces.

Friction testing of runway surfaces.

1.4 ENVIRONMENTAL COMPLIANCE: The Contractor is required to comply with all applicable State and Federal laws, State and Federal regulations, and Air Force instructions in effect at the time of performance of this contract. The laws and regulations include, but are not limited to: environmental protection and occupational safety and health. The Contractor shall be responsible for compliance with construction and operating permits, and also responsible for penalties, fines, or natural resource damage claims that may be required or assessed by the State of New Jersey, Federal or Local Governments resulting from: Contractor performance, or failure to perform, during the course of this contract. The Government will inspect for environmental compliance at their discretion, and will notify the Contracting Officer (CO) of any discrepancies found. In addition, the Contractor may be subject to contractual sanctions including, but not limited to, termination, suspension, debarment, and adverse past performance assessment.

1.4.1 SOLID WASTE, HAZARDOUS WASTE AND HAZARDOUS MATERIALS: The Contractor is responsible for the proper handling and disposal of solid and hazardous wastes and hazardous materials generated by or utilized during the course of its activities. Proper handling may also include recycling and material recovery, where required by law. The terms solid and hazardous wastes, and hazardous materials, include, but are not limited to, those defined in the Federal Water Pollution Control Act, the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, the Solid Waste Disposal Act, the Clean Air Act, and the Toxic Substances Control Act, the New Jersey Solid Waste Management Act, the New Jersey Water Pollution Control Act, the New Jersey Air Pollution Control Act and the regulations promulgated pursuant to those Acts. The Contractor shall also be responsible for any enforcement action that may be taken by the State of New Jersey, other State or the Federal Government related to handling, transportation and the proper disposal of solid and hazardous waste and hazardous materials. If notification, certifications, documentation, manifests, permits or any other written materials are required by law to be obtained, prepared and/or submitted, the Contractor shall prepare same and provide a written copy to the CO, and a copy to the Environmental Section (87 CES/CEAN). Hazardous waste manifests must be signed by the Environmental Flight Hazardous Waste Coordinator, Building 2404.

1.4.2 Source Separation of Solid Waste: Wastes shall be placed in closed metal containers, with liners when necessary, that are emptied on a regular schedule. Solid waste shall be separated and placed in individual containers in a manner that facilitates recycling of the various categories of waste. At a minimum, cardboard and all types of metal shall be source separated.

1.4.3 Disposal of Solid Waste: Unless otherwise directed, the Contractor shall deliver metal and cardboard to the McGuire Recycling Center in Building #2321. All other waste shall be disposed of in accordance with paragraph 1.4A, above.

1.4.4 Hazardous Material Handling: Any chemical to be used or stored by the Contractor must be approved, in writing, by the CO prior to the Contractor bringing it on the Base. The Contractor must utilize an AF Form 3000, “Material Approval Submittal”, provided by the Contracting Officer’s Representative (COR) for each container of hazardous material stored, kept, or utilized. Partially filled containers must be disposed of properly and coordinated with the Civil Engineer Environmental Coordinator, Environmental Section, Building 2404. Radioactive materials/devices will not be allowed on the Base without prior approval of the CO.

1.4.5 WATERS AND WATER SUPPLY: It is not permissible to discharge any materials to the navigable waters of the United States without a permit. Accordingly, discharges to or in areas that may reasonably reach or impact wetland areas and all other watercourses, including ditches, is prohibited without a permit. All discharges to storm drains, including but not limited to, soils and sediments contained in water runoff or dewatering operations, are prohibited. An appropriate soil erosion control plan shall be developed and utilized by the Contractor for construction projects to ensure that discharges do not occur.

1.4.6 NOTIFICATION OF ENVIRONMENTAL SPILLS: In the event that the Contractor spills or releases any unpermitted substance, hazardous substance or hazardous waste into the environment, the Contractor shall immediately report the incident to the Fire Department 609-754-2451, the CO, and the designated Government representative Mr. William Flockhart 609-754-6167. The Contractor shall be liable for the costs of clean-up and remediation of any spills or the release of such substance into the environment.

1.4.7 FUEL STORAGE: Gas or diesel fuels shall not be stored on the construction site, or on Base, without written approval from the CO, and only in compatible containers.

1.5 HEALTH AND SAFETY PLAN: Prior to commencing work, the Contractor shall prepare and submit a site/contract specific health and safety plan in accordance with Occupational Safety and Health Act (OSHA) 1910 standards, that are applicable to construction, for review by the CO. The plan will include worker's safety, confined spaces, OSHA training, handling of hazardous materials (including Safety Data Sheets (SDS)) such as asbestos and fuel discharges, and other site safety considerations. Government approval of plan is required prior to starting work.

1.6 SPECIFICATION DIVISION: These specifications are divided into several trade sections for convenience only and not to establish the units of work required of any trade. The Contractor shall be responsible for the allocation of the work between appropriate trades.

1.7 SUBMITTALS: Items shall be submitted after receipt of Notice to Proceed, within time limits prescribed on the Material Approval Submittals List and in accordance with Section 01300, SUBMITTALS. Materials or equipment shall not be installed until submissions have been approved by the CO. All submittals shall be verified by the Contractor as being in full compliance with requirements of these project specifications and/or drawings. Submittals received without the Contractor's certification will be returned, without action, for the Contractor's certification and re-submittal. Partial submittals for approval of materials and/or equipment will not be accepted for review by the CO. The Contractor shall be responsible for submitting for approval, at one time, all items of material and/or equipment that are part of a given system, i.e., for an air conditioning system.

1.8 PASS AND IDENTIFICATION: The Contractor shall obtain the necessary passes and/or identification for entry into Joint Base McGuire Dix Lakehurst for himself and all employees prior to commencement of work. The Government reserves the right to refuse to issue a pass to any employee of the Contractor for any reason deemed valid by the Government and in doing so shall not be subject to the Equitable Adjustment or Contract Disputes Act. Please see SECURITY

REQUIREMENTS / VEHICLES AND PASSES: After award of contract, the contractor shall request through the COR, CO and Security Forces to be issued base passes and identification badges for their employees and work vehicles in accordance with Security Requirements Air Force Instruction 31-101, AFMAN 31-113.

1.9 SCHEDULE OF WORK: The contractor will adhere to the following guidelines in regrades to scheduling work.

Work shall normally be scheduled a minimum of thirty (30) days in advance and accomplished during the standard eight-hour day, five-day week, 7:30 a.m. to 4:15 p.m., Monday through Friday excluding Federal Holidays. Work outside these hours must be approved by the CO at least three days prior to proposed work.

When work is required on the runways, taxiways, and parking ramps, the Contractor shall work the hours the Government closes the runway, taxiway or ramp areas to include nights and weekends, excluding Federal Holidays.

The Government will close the runway to all traffic while rubber is being removed. In the event of an emergency landing or take-off, the Contractor is required to clear the runway of all equipment and personnel to a minimum distance of 200 feet from the edge of the runway within fifteen minutes of notification. The authority to give the order lies with the Base Operations Officer or designated representative. The Contractor shall notify the CO or representatives two working days prior to moving to the work site to commence work and one working day prior to resumption of work at the site after an interruption of more than two working days.

Contractor shall provide schedule for work thirty (30) days prior to starting work, for CO approval.

The Contractor is not required to provide service on any Federal Holiday.

1.10 INSPECTION: Inspection of work by the Government will normally be accomplished along with the work as it progresses. At the discretion of the CO, inspection of various phases of work may be directed at their completion or prior to initiation of any further work. If phased inspection is directed, the Contractor shall notify the CO at least 24 hours prior to expected completion of the phase to be inspected.

1.11 PRELIMINARY AND FINAL INSPECTIONS: The Contractor shall request scheduling of the final and pre-final inspections in writing a minimum of 24 hours in advance of project completion. The request for scheduling will be in writing to the CO. Deficiencies shall be completed within ten days of the pre-final inspection.

1.12 COORDINATION OF TRADES: The Contractor must have competent personnel on the work site to coordinate all field work. The Contractor shall allot spaces to the various trades prior to the work. The Contractor shall be responsible for the coordination of all the trades involved.

1.13 UTILITIES: All reasonable quantities of utility service will be made available to the Contractor without charge. Any temporary lines and connections that may be required shall be installed, maintained, and removed by the Contractor at his expense and in a manner satisfactory to the COR. Removal shall be accomplished prior to final acceptance.

1.14 ROAD CLOSURE: Contractor will provide two weeks written notification to CO prior to any roadway closures.

1.15 TOILET FACILITIES: Government toilet facilities will not be available for Contractor or sub-Contractor personnel use.

1.16 ACCESS TO CONSTRUCTION SITE: The Government reserves the right to enter all work areas affected by this contract and to do any and all work deemed necessary to correct deficiencies found at any time during the duration of this contract including any and all time extensions thereto.

1.17 EMERGENCIES: In case of an emergency, the CO, Base Fire Chief, and Base Operations Officer, or their representatives, shall have the authority to order the Contractor to stop work and clear the area of personnel and equipment.

The Contractor shall comply to such an order with all possible speed. The COR shall be informed of all stop work orders.

In the case of being informed by the Fire Chief or Base Operations Officer, he shall notify the CO and provide written reasons for the stoppage of work.

1.18 AUTHORITY: Except as noted below, the term "Contracting Officer" (CO) as used in this specification includes the authorized Contracting Officer’s Representative (COR) of the CO acting within the limits of his/her authority. With respect to all paragraphs of the specifications citing "approval by the Contracting Officer" and all paragraphs cited in Material Approval Submittals, of the solicitation, the term "Contracting Officer" means only those individuals properly appointed as CO within the Contracting Squadron; no other Government personnel has the authority to grant such approval.

1.19 DRAWINGS ACCOMPANYING SPECIFICATIONS: Any drawings given to the Contractor during the execution of this project to accompany or clarify the specifications are the property of the Government and shall not be used for purposes other than those contemplated by the specifications.

1.20 BASE REGULATIONS: The Contractor shall conform to all Base regulations and directives, as identified specifically at the pre-construction conference, that pertain to security, safety, traffic, fire, and personnel clearances insofar as they apply to the Contractor's activities as directed by the Contracting Officer. The Contractor shall be responsible for providing and placing barricades, lighting, and safety devices during construction activities.

1.21 COORDINATION OF WORK OPERATIONS: The work to be performed under this contract is on an active military base. The Contractor shall coordinate work operations with the COTR prior to starting work under this contract.

The Contractor shall have a superintendent who speaks, reads, writes, and understands the English language; has authority to act for the Contractor and to be available on the job site throughout each work day. The Contractor shall be responsible for his quality control at all times as well as the amount of work. A specific individual shall be designated as the Contractor's quality control inspector and identified to the COR at the pre-construction conference.

1.22 CONTRACTOR'S PARKING: The Contractor's employees shall park in the areas assigned by the COR.

1.23 CONTRACTOR'S EMPLOYEE RESTRICTIONS: The Contractor's employees shall be restricted to areas within this scope of work plus direct routes to and from the site as may be approved in the preconstruction conference with regard to work scheduling and material handling.

1.24 AIRFIELD PAVEMENT ACCESS: The Contractor shall be shown points of access to the airfield area and work area at the pre-performance conference. Under no circumstances will the Contractor or Sub-Contractor use any other access to the airfield area and work area. The COR will be present at all times while Contractor or Sub-Contractor is working on airfield. The COR will maintain radio contact with the control tower when working on the runways which enables the Government to clear the runways in case of emergencies.

1.25 REFERENCES: Locations of pertinent laws and regulations for this section are as follows:

Section 1.4 Environmental Protection- website (https://www.epa.gov/laws-regulations)

Section 1.4 OSHA- website (https://www.osha.gov/law-regs.html)

Section 1.4A Federal Water Pollution Control Act- website (https://www.fws.gov/laws/lawsdigest/fwatrpo.HTML)

Section 1.4A Comprehensive Environmental Response, Compensation and Liability Act of 1980- website (https://www.epa.gov/laws-regulations/summary-comprehensive-environmental-response-compensationand-liability-act)

Section 1.4A Toxic Substances Control Act- website (https://www.epa.gov/laws-regulations/summary-toxicsubstances-control-act)

Section 1.4A New Jersey Solid Waste Management Act- website (http://www.nj.gov/dep/enforcement/sw.html)

Section 1.4A New Jersey Water Pollution Control Act- website (http://www.nj.gov/dep/dwq/rules.htm)

Section 1.4A New Jersey Air Pollution Control Act- website (http://www.nj.gov/dep/enforcement/air.html)

Section 1.5 Occupational Safety and Health Act 1910 Standards- website (https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_number=191 0)

Section 1.10 Pass and Identification - Security Requirements Air Force Instruction 31-101, AFMAN 31-116- PDF (http://www.e-publishing.af.mil/)

END OF SECTION 01000

SECTION 01012 SPECIAL CONDITIONS

PART I - GENERAL

2.1 CONTRACTOR PERFORMANCE REQUIREMENTS:

2.1.1 Staging Area: The staging area will be assigned by the COR at the pre-construction conference and will be on JB MDL. The staging area may be fenced to identify the limits of the Contractor responsibility. If the Contractor has any dumpsters in the staging area, they shall be clearly marked with a sign "for private use only, not for use of base personnel."

Dumpsters shall be emptied when contents mound to height of sides. Upon completion of all work outlined in the contract drawings and specifications, the Contractor shall remove his construction materials and his equipment from the confines of the Base. Only the office trailer and one storage trailer will be allowed at the work site. All other trailers must be kept at a remote site at JB MDL. Trailers on the work site shall be located as to be shielded from view from base roads as effectively as possible.

2.1.2 Marking of Equipment, Trailers, and Temporary Offices: The Contractor shall ensure that equipment and trucks used on the job are conspicuously marked with both name and telephone number of owner or leaser. All Contractor and sub-contractor temporary offices, trailers, and fencing shall have signs affixed to the exterior, which state the name and telephone number of the company. The letter size of the company name shall be a minimum of eight inches high with all lettering professionally and neatly prepared. All office trailers on the work site shall be a beige color similar to Wheatsheaf by Sherwin-Williams. All trailers, office, and storage shall be kept in good condition.

2.1.3 Cleanliness: The Contractor shall protect Government property and furnishings that may be in, or adjacent to, the work area with appropriate clean drop cloths, barricades, dust- stops, or other provisions as determined by, or approved by, the COR prior to starting work. The Contractor shall remove all debris, tools, materials and equipment, and other items when work is completed in each particular area.

2.1.4 Daily Clean Up: Daily construction site and staging area clean up shall be accomplished by the Contractor. This clean up shall include the placing of construction material and equipment in a neat and orderly arrangement on the site. Equipment and materials must not block access to existing facilities. Rubbish, debris, rubble, and garbage shall be removed at the end of each workday. The Contractor shall inspect the site and area daily to ensure that all paper, cardboard, demolition products, and similar materials are removed to provide a litter-free appearance. On-base access routes utilized by construction equipment and/or delivery vehicles shall be maintained free from clay or mud balls, clods, and mud. During the growing season (April through October), all grass areas around the Contractor's trailer and within ten feet of exterior contract construction areas or within ten feet of buildings shall be mowed and trimmed to maintain neat grassy areas of reasonable length by the Contractor. Grass height shall never be allowed to exceed six inches.

2.1.5 Equipment Storage: Equipment may not be left at worksites if work is stopped for more than 24 hours. Such equipment must be taken back to the remote storage site unless specifically approved to remain by the CO. For utility projects, materials cannot be left on site unless installation will begin within one week. If work does not begin within one week, the material must immediately be delivered to the Contractor storage yard.

2.1.6 Construction Fence: Temporary construction fencing shall be chain link and a minimum of 72 inches high, unless otherwise indicated by the COR.

2.1.7 Vehicle Parking: Contractor personnel must park in approved parking areas. Parking on the grass is not permitted.

Contractor vehicles will not be allowed to drive on grass to gain access to worksites unless specific routes are approved in advance.

2.2 ACCIDENT PREVENTION: Occupational Safety and Health Act (OSHA): Contractors shall comply with OSHA 1926, Construction Standards, and the portions of OSHA 1910 standards that are applicable to construction.

The Army Corps of Engineers Manual EM 385-1-1 will be used in the absence of guidance in OSHA regulations.

2.3 AIRFIELD OPERATIONS: The airfield, taxiways, parking apron, and areas directly adjacent to the airfield are limited to those personnel working on, supervising, or supplying materials, equipment, or services to the contractor. All personnel or activities not requiring airfield access shall be prohibited. All activities capable of being performed in the contractor storage or in other off-airfield areas shall be performed there. All personnel and vehicles requiring airfield access shall be coordinated through Airfield Operations, shall obey all access requirements and limitations imposed by Base requirements to include the following:

2.3.1 Airfield Access: Contractors who are required to access the airfield restricted area must contact Keith Taylor at 609- 754-6466 to obtain the proper instructions and paperwork for entering an airfield restricted area. Contractor personnel, who are authorized to drive on the flight line, must have an AF Form 483 “Certificate of Competency for Airfield Driving” in their possession, and obtain a vehicle identification cone from Base Operations. The cone must be visible during operations of the vehicle when driving on the flight line, and the cone must be secured upon departure from the flight line. Contractors will not have access to the restricted areas unless they are under escort by authorized personnel wearing a restricted area badge.

2.3.2 Personnel Access: Contractor personnel are allowed in the restricted area only if a valid contract is in effect. Entrance to the work site must be by permitted vehicle.

2.4 REFERENCES: Locations of pertinent laws and regulations for this section are as follows:

Section 1.5 OSHA 1926- website (https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_number=1926)

Section 1.5 OSHA 1910- website (https://www.osha.gov/pls/oshaweb/owastand.display_standard_group?p_toc_level=1&p_part_number=1910)

Section 1.5 Army Corp of Engineers Manual EM 385-1-1- website (http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/)

Section 1.8.B AF Form 483 “Certificate of Competency for Airfield Driving”- website (http://www.epublishing.af.mil/) forms will be provided upon completion of required Airfield Drivers Training to be scheduled through COR.

END OF SECTION 01012

DIVISION 1 SPECIAL CONDITIONS

SECTION 01200 SPECIAL PROVISIONS

3.1 ACCESS ON AIRFIELD: During this contract, the airfield will be occupied and in use by Government and other

Contractor personnel and equipment. It will remain in operation during the execution of this contract except in designated work areas. At all times during the performance of the work, the Contractor shall provide maximum cooperation with Government personnel and Contractors on the airfield to ensure minimum interruptions to essential Government operations. Because of these operations, the Contractor shall be required to notify the Contracting Officer or his designated representative to schedule the work in collaboration with and subject to the approval of the Base Operations Officer at least five days in advance of moving onto the work site.

3.2 WORK AREAS: Work areas will be specified per delivery order. All work on this project is subject to the following:

The scheduling of work areas is subject to change. The Contracting Officer will coordinate all such changes with the Contractor: Changes to the work areas by the Government as a result of operations will be made at no additional cost to the Government and will be made prior to completion of work in current work area.

Work areas will be located in restricted areas. Contractor personnel will be required to be escorted in all restricted areas. Contractor personnel shall not enter the airfield zone except while work progresses on the airfield.

3.3 CLEAN UP: The Contractor shall be responsible for clean-up of all areas related to his construction work. These areas include:

At all times, the Contractor shall keep all airfield pavements used as hauling/trucking routes or access to the work area free of foreign objects resulting from his construction or from his traffic and any other operations, performed by the Contractor.

The Contractor shall clean each completed area of work of all debris, equipment, and materials to the satisfaction of the Contracting Officer before moving to the next designated work area.

3.4 PARKING EQUIPMENT: The Contractor will be permitted to park his equipment in his current work area on the airfield apron at the end of each day's work, with prior coordination and approval of the Airfield Manager. All equipment must have sufficient reflectors or be barricaded with blinder lights at all times when parked.

END OF SECTION 01200

DIVISION 1 SPECIAL PROVISIONS

SECTION 01300 SUBMITTAL PROCEDURES

PART 1 - GENERAL

4.1 GENERAL: Submittals will be turned in as required throughout the construction documents to include the Material Approval Submittal list. Failure to include an item on the Material Approval Submittal list will not relieve the Contractor from responsibility to submit the item as specified in the construction documents.

4.2 TYPES OF SUBMITTALS: Submittals are grouped as follows:

Samples: Physical examples of products, materials, equipment, assemblies, or workmanship that are physically identical to portion of work, illustrating portion of work or establishing standards for evaluating appearance of finished work or both.

Certificates/Certifications: Statement signed by responsible officials of a manufacturer of a product, system or material, attesting that the product, system, or material meets specified requirements. The statement must be dated after the award of this contract, must name the project, and must list the specific requirements that are being certified.

Instructions: Preprinted material describing installation of a product, system, or material, including special notices and material safety data which provide calculations, descriptions, or documentation regarding the work.

Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met, but not to ensure directly that work is in accordance.

4.3 CONTRACTOR'S OPTION: For products specified only by reference standard, the Contractor shall select a product meeting that standard which is available from a commercial source. Where names of manufacturer's products or equipment appear in these specifications and drawings, the products of other manufacturers will receive equal consideration. Items to be submitted as "equal" must meet the same noted specifications or acknowledged trade standard for quality, finish, and/or operation. The Contractor is required to provide documentation that the substituted product meets the specification requirements.

PART 2 - PRODUCTS

5.1 GENERAL: A transmittal letter, AF Form 3000, "Material Approval Submittal," shall accompany all submittals.

5.2 MANUFACTURER'S CATALOG CUTS/DATA:

Information should be standard data and/or information published by the manufacturer of the product.

The specific type, size, capacity, and part number will be announced on the manufacturer's information.

Submit three copies of catalog cuts/data to the Contracting Officer.

5.3 SAMPLES: Samples shall be of sufficient size and quantity to clearly illustrate the following:

Functional characteristics of the products, with integrally-related parts and attachment devices.

Color, texture, and patterns.

Method of installation or application.

Submit two samples to the Contracting Officer.

5.4 CERTIFICATES/CERTIFICATIONS:

Certificates/Certification will describe the item to be certified.

The name and address of the Contractor shall be on the document.

Date(s) of certification and date of shipment if appropriate.

5.5 INSTRUCTIONS:

Instructions shall identify the equipment by make and model, the type of the instructions, and reference the specification paragraph or drawing that the instruction covers.

The instruction shall be either a manufacturer's supplied item or, if provided by Contractor, instructions at a minimum shall be neat and clear.

Submit three copies of the instructions to the Contracting Officer.

PART 3 - EXECUTION

6.1 CONTRACTOR'S RESPONSIBILITIES:

Review submittals prior to submission. Transmit submittals to the Contracting Officer for approval.

Coordinate each submittal with requirements of work.

Contractor's responsibility for errors and omissions in submittals shall not be relieved by the Contracting Officer's review of submittals.

Do not begin any work that requires submittal approval without first obtaining Contracting Officer approval.

6.2 TIMING OF SUBMITTALS:

Provide submittals in 30 days from notice to proceed or as specified by the Submittals Legend list.

Allow 14 calendar days for review by Government.

Delays caused by tardiness in delivery of submittals by the Contractor will not be an acceptable basis for extension of the contract completion date.

6.3 RESUBMISSION REQUIREMENTS: Make all revisions required by the Contracting Officer. If the Contractor considers any required revisions to be a change, the Contractor shall so notify the Contracting Officer as provided for under the contract clause entitles "changes."

6.4 SUBSTITUTIONS: The Contractor may submit separate requests for substitution of a product other than that required by the contract documents. Substitutions must be supported by technical and physical evidence that the substitution will provide the same results as the item called out in the contract documents. Failure to provide the supporting data will result in rejection of the substitution. Substitutions must be marked clearly and the product to be substituted shall be indicated clearly on the submittal. Three copies of the substitutions shall be submitted to the Contracting Officer.

6.5 Revision after approval: When a submittal has been reviewed by the Contracting Officer, re-submittal or substitution of material or equipment will not be considered unless accompanied by an explanation to the Contracting Officer for acceptance as to why the revision is necessary.

6.6 References: Locations of pertinent laws and regulations for this section are as follows:

Section 2.1 AF Form 3000, “Material Approval Submittal”- website (http://www.e-publishing.af.mil/)

END OF SECTION 01300

END OF DIVISION I

DIVISION 02 - SITE WORK

SECTION 02761 PAVEMENT MARKINGS

PART 1 GENERAL

7.1 REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only and can be located on the web at the following Uniform Resource Locators (URL):

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM) (https://www.astm.org/) o ASTM D 471 (2016) Rubber Property – Effect of Liquids o ASTM D 522 (2013) Mandrel Bend Test of Attached Organic Coatings o ASTM D 711 (2015) No-Pick-Up Time of Traffic Paint o ASTM D 792 (2013) Density and Specific Gravity (Relative Density) of Plastics by Displacement o ASTM D 823 (2012) Producing Films of Uniform Thickness of Paints, Varnishes, and Related Products on Test Panels o ASTM D 2240 (2015) Rubber Property-Durometer Hardness o ASTM D 2697 (2014) Volume Nonvolatile Matter in clear or Pigmented Coatings o ASTM D 3335 (2014) Lead, Cadmium, and Cobalt in Paint by Atomic Absorption Spectroscopy o ASTM D 3718 (2015) Low Concentrations of Chromium in paint by Atomic Absorption Spectroscopy o ASTM D 3924 (2016) Conditioning and Testing Paint, Varnish, Lacquers, and Related Materials o ASTM D 3960 (2013) Determining Volatile Organic Compound (VOC) Content of Paints and Related Coatings o ASTM D 4280 (2015) Extended Life Type, Non-plowables, Prismatic, Raised, Retroflective Pavement Markers o ASTM D 4541 (2009) Pull-Off Strength of Coatings Using Portable Adhesion Testers o ASTM E 28 (2014) Softening Point by Ring-and-Ball Apparatus o ASTM G 154(2016) Operating Light- and Water-Exposure Apparatus (Fluorescent UV Condensation Type) for Exposure of Nonmetallic Materials

U.S. GENERAL SERVICES ADMINISTRATION (GSA) (www.everyspec.com) o MPI 32 Traffic Marking Paint S.B.

o SAE-AMS-STD-595 Colors Used in Government Procurement o FS TT-B-1325 (2012; Rev. D) Beads (Glass Spheres) Retro-Reflective o FS TT-P-1952 (2015; Rev. E) Paint, Traffic and Airfield Markings, Water Emulsion Base

INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI) (http://www.icri.org/) o ICRI Technical Guideline 03732 Selecting and Specifying Surface Preparation for Sealers, Coatings, and

Membranes

7.2 SUBMITTALS: Submit the following in accordance with Section 01330, "Submittal Procedures"

Product Data:

o Reflective media for airfields o Reflective media for roads and streets o Paints for airfields o Paints for roads and streets o Thermoplastic compounds and primer

Test Reports:

Certificates:

o Paints for roads and streets o Construction equipment list

Manufacturer's Instructions:

o Thermoplastic compounds and primer 4. Submit manufacturer's Material Safety Data Sheets.

7.3 DELIVERY AND STORAGE: Deliver paints, paint materials, and thermoplastic compound materials in original sealed containers that plainly show the designated name, specification number, batch number, color, date of manufacture, manufacturer's directions, and name of manufacturer. Provide storage facilities at the job site for maintaining materials at temperatures recommended by the manufacturer. Make available paint stored at the project site or segregated at the source for sampling not less than 30 calendar days prior to date of required approval for use to allow sufficient time for testing. Notify the Contracting Officer when paint is available for sampling.

7.4 WEATHER LIMITATIONS: Apply paint to clean, dry surfaces, and, unless otherwise approved, only when air and pavement temperatures are above 40 degrees F (5 degrees C) and less than 95 degrees F (35 degrees C) for oil-based materials;

above 50 degrees F (10 degrees C) and less than 110 degrees F (43 degrees C) for water based materials. Maintain paint temperature within these same limits.

7.5 EQUIPMENT: Machines, tools, and equipment used in the performance of the work shall be approved by the Contracting Officer and maintained in satisfactory operating condition. Submit construction equipment list approval by the Contracting Officer.

PART 2 PRODUCTS

8.1 MATERIALS: Provide materials conforming to the requirements specified herein.

Paints for Airfields: FS TT-P-1952, color as selected.

Paints for Roads and Streets: FS TT-P-1952, color as selected.

Reflective Media for Airfields: FS TT-B-1325, Type I, gradation A and Type III.

Reflective Media for Roads and Streets: FS TT-B-1325, Type I, Gradation A.

PART 3 EXECUTION

9.1 SURFACE PREPARATION: Allow new pavement surfaces to cure for a period of not less than 30 days before application of marking materials. Thoroughly clean surfaces to be marked before application of the paint. Remove dust, dirt, and other granular surface deposits by sweeping, blowing with compressed air, rinsing with water, or a combination of these methods as required. Remove rubber deposits, existing paint markings, residual curing compounds, and other coatings adhering to the pavement by water blasting. Remove any potential Foreign Object Debris (FOD) to aircraft. Scrub affected areas, where oil or grease is present on old pavements to be marked, with several applications of approved detergent or degreaser and rinse thoroughly after each application. After cleaning oil-soaked areas, seal with shellac or primer recommended by the manufacturer to prevent bleeding through the new paint. Do not commence painting in any area until pavement surfaces are dry and clean.

9.2 RATE OF APPLICATION:

Reflective Markings:

o Apply paint evenly to the pavement area to be coated at a rate of 105 (plus or minus 5) square feet per gallon (2.5 (plus or minus 0.10) square meter per liter).

o Apply glass spheres uniformly to the wet paint on airfield pavement at a rate of 10 (plus or minus 0.5) pounds of glass spheres per gallon (1198 (plus or minus 60) g of glass spheres per liter).

o Apply glass spheres uniformly to the wet paint on road and street pavement at a rate of 6 (plus or minus 0.5) pounds of glass spheres per gallon (719 (plus or minus 60) g of glass spheres per liter).

o Application of reflective media shall immediately follow the application of paint. Accomplish drop-on application of the glass spheres to ensure even distribution at the specified rate of coverage. Should there be malfunction of either paint applicator or reflective media dispenser, discontinue operations until deficiency is corrected.

Non reflective Markings: Apply paint evenly to the pavement surface to be coated at a rate of l05 (plus or minus 5) square feet per gallon (2.5 (plus or minus 0.10) square meter per liter). Painting: Apply paint pneumatically with approved equipment at rate of coverage specified herein. Provide guidelines and templates as necessary to control paint application.

Take special precautions in marking numbers, letters, and symbols. Manually paint numbers, letters, and symbols. Sharply outline all edges of markings. The maximum drying time requirements of the paint specifications will be strictly enforced, to prevent undue softening of bitumen and pickup, displacement, or discoloration by tires of traffic. Discontinue painting operations if there is a deficiency in drying of the markings until cause of the slow drying is determined and corrected.

9.3 MARKING REMOVAL: Pavement marking, including plastic tape, shall be removed in the areas shown on the drawings. Removal of marking shall be as complete as possible without damage to the surface. Aggregate shall not be exposed by the removal process. After the markings are removed, the cleaned pavement surfaces shall exhibit adequate texture for remarking as specified in paragraph 3.1 “SURFACE PREPARATION”. Contractor shall demonstrate removal of pavement marking in an area designated by the Contracting Officer. The demonstration area will become the standard for the remainder of the work.

Equipment Operation: Equipment shall be operated to remove markings from the pavement surface, prevent dilution or removal of binder from underlying pavement, and prevent emission of blue smoke from asphalt or tar surfaces.

Cleanup and Waste Disposal: The worksite shall be kept clean of debris and waste from the removal operations.

Cleanup shall immediately follow removal operations in areas subject to air traffic. Debris shall be disposed of at approved sites.

9.4 FIELD TESTING AND INSPECTION:

Sampling and Testing: As soon as the paint, reflective, and thermoplastic materials are available for sampling, obtain by random selection from the sealed containers, two-quart samples of each batch in the presence of the Contracting Officer.

Accomplish adequate mixing prior to sampling to ensure a uniform, representative sample. A batch is defined as that quantity of material processed by the manufacturer at one time and identified by number on the label. Clearly identify samples by designated name, specification number, batch number, project contract number, intended use, and quantity involved. At the discretion of the Contracting Officer, samples provided may be tested by the Government for verification.

Inspection: Examine material at the job site to determine that it is the material referenced in the report of test results or certificate of compliance. A certificate of compliance shall be accompanied by test results substantiating conformance to the specified requirements.

Surface Preparations and Application Procedures: Surface preparations and application procedures will be examined by the Contracting Officer to determine conformance with the requirements specified. Approve each separate operation prior to initiation of subsequent operations.

9.5 TRAFFIC CONTROL AND PROTECTION: Place warning signs near the beginning of the work site and well ahead of the work site for alerting approaching traffic from both directions. Place small markers along newly painted lines to control traffic and prevent damage to newly painted surfaces. Mark painting equipment with large warning signs indicating slow-moving painting equipment in operation.

END OF SECTION 02761

DIVISION 2 - SITE WORK

SECTION 02951 RUNWAY RUBBER REMOVAL AND RECOVERY

PART I GENERAL

10.1 METHODS OF OPERATION: The removal of rubber shall be accomplished at the direction of the COR by the use of either high-pressure water or Chemtek's AVION 50 NexGen rubber removal chemical or equal brand based on mission requirements. The recovery of all materials generated during the removal process shall be accomplished with state-of-the-art processes and equipment

10.2 MAINTENANCE OF TRAFFIC:

Operation and Performance: The operation of equipment and the performance of work upon and in the vicinity of airfields shall be coordinated with the Contracting Officer and with the Flight Operations Officer.

Neither equipment nor personnel shall use any portion of an airfield without permission of these officers unless the runway is closed. In all cases, verbal communication shall be maintained with the control tower before and during work in the vicinity of the airfield. The control tower shall be advised when work is completed.

Landing and Take-Offs: Emergency landings and take-offs shall take precedence over all Contractor operations. When notified of an emergency situation, the Contractor shall cease all rubber removal operations and immediately clear the runway of all equipment and personnel, within fifteen minutes of notification, for a distance of at least 200 feet (60 meters) from the edge of the runway.

10.3 RUBBER REMOVAL EQUIPMENT:

Mechanical Rubber Removal Equipment: Mechanical rubber removal equipment used on asphalt or tar concrete shall be controlled to remove rubber accumulations and minimize disturbance to asphalt or tar mixtures.

Equipment to be used on Portland Cement concretes shall be controlled to remove rubber accumulations and prevent removal of hardened paste from the concrete. Basic hand tools and the following major types of mechanical equipment will be considered acceptable for this project.

o Mobile water blasting equipment shall be capable of producing a pressurized stream of water that will effectively remove rubber from the pavement surface without significantly damaging the pavement. Water pressure shall be regulated so that substantially all rubber accumulations are removed during execution of the work.

o The equipment used in the rubber removal process shall be mounted on pneumatic tires and be capable of removing rubber at a minimum rate of 10,000 square feet per hour, without damage to the pavement surface or joint seal material. Any damage done to the pavement or joint-seal material caused by an operation error shall be repaired by the Contractor at his expense within the time established for completion of the rubber removal work.

Chemical Rubber Removal Equipment: Chemical equipment shall be capable of application and removal of chemicals from the pavement surface and shall leave only non-toxic biodegradable residue.

Rubber Recovery Equipment: During the rubber removal process, Contractor shall provide continuous vacuum recovery of debris or other proven state-of-the-art recovery process that is capable of preventing fugitive debris from leaving the runway, asphalt and/or concrete surfaces. All debris recovered must be handled and disposed of by the Contractor in accordance with Section 01000, Paragraph 1.4 of this Specification. Debris includes all substances generated during the course of the removal process. No rubber removal shall be accomplished without concurrent debris recovery.

10.4 PERFORMANCE: The Contractor shall remove a minimum of 90 percent of the rubber buildup and contaminants from the runway surface and the grooves. All efforts will be made to remove 100 percent, but not at the expense of the surface integrity. The efficiency of the cleaning operation may be determined by visual inspection, static micro-texture measurement per American Society Testing and Material's Standard Method, or with a Federal Aviation Administration (FAA) approved friction- measuring device.

10.5 DELIVERY AND STORAGE: Materials that are required in the approved rubber removal process shall be delivered in original manufacturer's containers and shall be labeled with appropriate Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA), or other agency warnings, if applicable. Contractor shall maintain on site copies of all SDSs related to all materials utilized in the rubber removal and recovery process.

Materials shall be protected from the environment until their use is required during execution of the work.

10.6 UNIT PRICES: Measurements and payment will be calculated as follows:

Measurement: Rubber removal and recovery will be measured by the number of square feet of runway to be cleaned.

Payment: Rubber removal and recovery will be paid for at the contract unit price per square foot of runway rubber removed based on method of removal, pending successful results of friction testing.

10.7 WEATHER LIMITATIONS: Pavement surface shall be free of snow, ice, or slush. Surface temperature shall be at least 40 degrees F (5 degrees C) and rising at the beginning of operations. Operation shall cease during thunderstorms. Operation shall cease during rainfall except for water blasting and removal of previously applied chemicals. Water blasting shall cease where surface water accumulation alters the effectiveness of material removal.

PART 2 EXECUTION

11.1 SCHEDULE OF WORK: Submit a schedule of work to the Contracting Officer for transmittal to the Operations Officer. Describe the work to be accomplished; noting the location of work, distances from the ends of runways, taxiways, buildings, and other structures; and indicating dates and hours during which the work will be accomplished.

Schedule the work to conform to aircraft operating schedules. The Government will try to schedule aircraft operations so as to permit the maximum amount of time for the Contractor's work. However, in the event of any emergency, intense operational demands, adverse wind conditions, and other unforeseen difficulties, discontinue all work at locations in the aircraft operational area. Keep the approved schedule of work current and notify the Contracting Officer of any changes prior to beginning each day's work.

11.2 QUALITY ASSURANCE: Required Samples: Prior to the start of work, remove and recover rubber on designated test areas not less than 50 feet (15 m) in length. Use procedures, water pressures, nozzle height, nozzle spacing, nozzle angle, and equipment movement rate to achieve the required degree of rubber removal in accordance with paragraph 1.4 entitled "PERFORMANCE." Submit the test results before any further removal work will be allowed.

11.3 RUBBER REMOVAL: The pavement surface may be of Portland cement, tar, or asphalt mixtures. Chemical methods, if used, shall be compatible with pavement materials, the environment, and working personnel. Close control of water pressure and blasting time/duration shall be used to prevent disintegration damage to asphalt and tar concretes.

Extremely good control shall be exercised for porous friction courses. The Contractor shall demonstrate the ability to remove rubber at a touchdown area of the runway selected by the Contracting Officer; at least one site per runway will be chosen. Rubber removal shall be as complete as possible without damage to the pavement surface. The surface texture of the cleaned demonstration area will be compared to that of non-rubber traffic areas to determine satisfactory completion of the removal operation. After approval of the Contractor's operations the cleaned area will become the standard for rubber removal and final surface texture for the remainder of work.

Water to be used for high-pressure water equipment will be made available from Government hydrant[s]…