J-3.pdf

PDF 96 KB Posted

Attached to
Mechanical IDIQ Federal contract opportunity
Solicitation number
FA4484-13-R-0013
Issued by
Department of the Air Force Air Mobility Command

About this file

J-3

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical IDIQ, newest first.
File Type Posted
FA4484-13-R-0013-0003 _Mechanical.pdf PDF
Site_Visit_Minutes.pdf PDF
Request_for_Past_Perform.pdf PDF
FA4484-13-R-0013-0002.pdf PDF
Question_and_answers.pdf PDF
Scope_of_Work.pdf PDF
Bid_Schedule.pdf PDF
FA4484-13-R-0013-0001.pdf PDF
J-1.pdf PDF
J-2.pdf PDF
COMPLIANCE_STATEMENT1.doc DOC document
J-6.pdf PDF
C-1_1.pdf PDF
87th_SECURITY_FORCES_SQUADRON_Appendix.docx DOCX document
FA4484-R-13-0013_Mechanical_IDIQ_Solicitation.doc DOC document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: NJ130027 06/14/2013 NJ27

Superseded General Decision Number: NJ20120027

State: New Jersey

Construction Type: Building

County: Burlington County in New Jersey.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Modification Number Publication Date

0 01/04/2013

1 02/15/2013

2 04/12/2013

3 05/03/2013

4 05/17/2013

5 05/24/2013

6 06/14/2013

ASBE0014-003 05/01/2013

BURLINGTON COUNTY (City of Beverly; Townships of Cinnaminson, Delanco, Delron, Edgewater Park, Evesham, Hainesport and

Lumberton; Borough of Maple Shade; Township of Medford; Borough of Medford Lakes; Townships of Moorestown and Mt. Laurel;

Borough of Palmyra; Township of Riverside; Borough of Riverton;

Townships of Shamong, Southampton, Tabernacle, Westhampton and

Willingboro)

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement).......................$ 41.79 28.86

* ASBE0089-003 07/02/2012

BURLINGTON COUNTY (Townships of Bordentown, Burlington, Chesterfield, Easthampton, Florence, Mansfield, Mt. Holly, New

Hanover, North Hanover, Pemberton, Springfield and Woodland)

ASBESTOS WORKER/HEAT & FROST

INSULATOR ((includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement))......................$ 39.92 28.51

PAID HOLIDAYS:

The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay.

BRNJ0002-013 05/01/2012

Bricklayer.....................$ 36.95 25.37

Work on high stacks: 22% per hour additional.

BRNJ0007-012 07/01/2012

Marble setter...................$ 54.19 26.53

BRNJ0007-014 01/01/2012

TERRAZZO WORKER/SETTER...........$ 45.93 29.05

BRNJ0007-017 06/01/2012

Tile finisher..................$ 38.28 20.50

Tile setter....................$ 43.27 24.75

Tile finisher:

Work grouting all epoxy: $10.00 additional per day.

CARP0006-009 11/01/2012

CARPENTER (Scaffold Builder).....$ 41.49 56%

The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.

CARP0006-010 11/01/2012

CARPENTER

Including Acoustical

Ceiling Installation, Drywall Hanging, Formwork, Batt and Blown Insulation...$ 41.49 56%

CARP0029-006 11/01/2012

Soft floor layer...............$ 41.49 56%

CARP0454-009 07/01/2012

PILEDRIVERMAN....................$ 38.80 28.97

New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas

Day; provided that the worker works any of the three days in the five-day work week preceding the holiday and the first work day after the holiday.

CARP0715-007 11/01/2012

Millwright.....................$ 42.28 56%

Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter.

ELEC0269-017 10/01/2012

BURLINGTON COUNTY (north of a line following the west and south limits of Burlington Borough from the Delaware River, in a southeasterly direction, to the Burlington - Mt. Holly road;

then, south-southeast along the Burlington - Mt. Holly road to the town of Mt. Holly, includes Mt. Holly; then, east along the

Pennsylvania Railroad to the town of New Lisbon, includes New

Lisbon; then, continuing along the Pennsylvania Railroad to the

Ocean County line)

Electrician and cable splicer

(Includes Low Voltage Wiring)....$ 47.37 61.48% + .25

ELEC0351-001 10/01/2012

ATLANTIC COUNTY; BURLINGTON COUNTY (south of a line following the west and south limits of Burlington Borough from the

Delaware River, in a southeasterly direction, to the Burlington

- Mt. Holly road; then, south-southeast along the Burlington -

Mt. Holly road to the town of Mt. Holly, does not include Mt.

Holly; then, east along the Pennsylvania Railroad to the town of New Lisbon, does not include New Lisbon; then, continuing along the Pennsylvania Railroad to the Ocean County line);

CAMDEN, CAPE MAY, CUMBERLAND, GLOUCESTER AND SALEM COUNTIES:

Electricians:

Cable splicer on lead cable.$ 46.42 71.01% + 2.25

Electrician and cable splicer.....................$ 44.42 71.01% + 2.25

ELEV0005-004 01/01/2013

Elevator mechanic..............$ 49.84 25.185

New Year's Day, Memorial Day, Independence Day, Labor

Day, Veteran's Day, Thanksgiving Day, the Friday after

Thanksgiving Day, and Christmas Day.

PAID VACATION:

Employer contributes 2% of basic hourly rate as vacation pay credit for 6 months to 5 years of service, and 4% for 5 years or more of service.

ENGI0825-020 01/01/2013

Power equipment operators:

GROUP 1.....................$ 42.32 26.65

GROUP 2.....................$ 41.73 26.65

GROUP 3.....................$ 39.82 26.65

GROUP 4.....................$ 38.19 26.65

GROUP 5.....................$ 36.48 26.65

Hazardous waste removal work:

Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: 20% per hour additional.

New Year's Day, Washington's Birthday observed, Memorial Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day; provided

1) that the worker works three of the preceding five work days before the holiday; or, the work day before the holiday and the work day after the holiday; and, 2) that the worker works the work day before and the work day after the holiday.

DEFINITION OF GROUPS:

GROUP 1:

Backhoe, Including Backhoe Track; Boom; Concrete Paving

Machine; Crane (all types, including overhead and straddle traveling type); Drill (down-the-hole drill, rotary drill, self-propelled hydraulic drill, self-powered drill);

Elevating Grader; Excavator; Front End Loader (5 cu. yd.

and over); Piledriver (length of boom, including length of leads, shall determine premium rate applicable); Trencher

GROUP 2:

Backhoe Loader Combo; Concrete Pumper; Grader/Blade (Finish);

Hoist; Hydraulic Crane, 10 Tons and under; Front End

Loader (2 cu. yd. but less than 5 cu. yd.); Scraper; Side

Boom

GROUP 3:

Asphalt Spreader; Bulldozer;Compressor(2 or 3) (in Battery)

(within 100 ft.); Forklift; Front End Loader (1 cu. yd.

and over but less than 2 cu. yd.); Lull; Mechanic; Paver, Asphalt; Roller, Blacktop; Tractor;

GROUP 4:

Bobcat/Skid Loader; Compressor (Single); Farm Tractor; Front

End Loader (under 1 cu. yd.); Hydroseeder; Roller, Grade;

Pump, Hydraulic

GROUP 5:

Oiler

IRON0068-011 07/01/2012

(Lumberton)

IRONWORKER

Reinforcing.................$ 42.10 19.78

Structural and Ornamental...$ 44.10 19.78

IRON0350-009 07/01/2012

BURLINGTON COUNTY (south and east of a line starting from the point on the Atlantic-Burlington county line where the

Atlantic-Burlington county line crosses Route 206; then, following a line northeast through Wharton State Park to the town of Chatsworth; then, continuing along the same line, to the Burlington-Ocean county line)

Ironworkers:

Reinforcing.................$ 43.62 26.25

Structural and Ornamental...$ 44.62 26.25

IRON0399-005 07/01/2012

BURLINGTON COUNTY (north and west of a line starting from the point on the Atlantic-Burlington county line where the

Atlantic-Burlington county line crosses Route 206; then, following a line northeast through Wharton State Park to the town of Chatsworth; then, continuing along the same line, to the Burlington-Ocean county line)

IRONWORKER (Structural, Reinforcing and Ornamental)......$ 44.60 24.95

LABO0222-006 07/01/2012

LABORER

MASON TENDER:

Brick/Cement/Concrete.......$ 29.85 23.07

LABO0222-008 07/01/2012

Laborers:

Asphalt Shoveler, Asphalt

Spreader, Landscape

Laborer, Pipelayer, Power

Toole Operator and

Screedman...................$ 29.35 23.07

LABO1030-002 05/01/2011

Asbestos Removal Laborer.........$ 28.37 21.62

The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants)

PAIN0021-032 05/01/2012

BURLINGTON COUNTY (south of a line drawn between these cities:

Florence to Bustleton to Columbus to Jobstown to Pemberton to

Ongs Hat to Chatsworth to Whiting to Pinewald to Ocean Gate to

Seaside Heights)

Glazier........................$ 38.35 25.35

Work at 30 ft. above the working surface, or on a swing stage: $1.00 per hour additional.

PAIN0711-011 05/01/2013

BURLINGTON COUNTY (north of a line drawn between these cities:

Florence to Bustleton to Columbus to Jobstown to Pemberton to

Ongs Hat to Chatsworth to Whiting to Pinewald to Ocean Gate to

Seaside Heights)

Glazier........................$ 40.94 20.38

Work welding or using a cutting torch: $1.00 per hour additional.

Work on a swing stage scaffold; on a pipe scaffold providing the working height of the platform is 30 ft. or above; and on motorized lifts provided that the height of the lift platform is above the second floor or above thirty feet:

$1.00 per hour additional.

PAIN0711-018 05/01/2013

DRYWALL FINISHER/TAPER...........$ 38.00 20.10

PAIN0711-019 11/01/2012

PAINTER (Brush & Roller).........$ 36.62 19.54

PAINTER (Spray)..................$ 40.28 19.98

* PLAS0592-036 05/01/2013

CEMENT MASON/CONCRETE FINISHER...$ 38.37 29.11

PLUM0009-015 03/01/2013

BURLINGTON COUNTY (north of a line drawn from the town of

Burlington City, includes Burlington City; then, along County

Road Route 541 East, also known as High St., until it reaches the city of Mt. Holly, includes the city of Mt. Holly; then, along Madison Ave. in Mt. Holly to State Road Route 38 East;

then, along State Road Route 38 East until it crosses over

State Road Route 206 and becomes County Road Route 530; then, along County Road Route 530 to Magnolia Road, includes

Pemberton Borough; then, south on Magnolia Road in Pemberton

Township to Magnolia New Lisbon Road (Route 545); then, south on Mt. Holly Misery Road to State Road Route 70 East; then, along State Road Route 70 East to the Ocean County line)

PIPEFITTER (Including HVAC

Pipe Installation)...............$ 43.08 31.65

Service and Repair..........$ 34.03 18.53

PLUMBER (Excluding HVAC Pipe

Installation)....................$ 43.08 31.65

Service and Repair..........$ 34.03 18.53

PLUM0322-008 05/01/2013

BURLINGTON COUNTY (south of a line drawn from the town of

Burlington City, does not include Burlington City; then, along

County Road Route 541 East, also known as High St., until it reaches the city of Mt. Holly, does not include the city of Mt.

Holly; then, along Madison Ave. in Mt. Holly to State Road

Route 38 East; then, along State Road Route 38 East until it crosses over State Road Route 206 and becomes County Road Route

530, does not include Pemberton Borough; then, south on

Magnolia Road in Pemberton Township to Magnolia New Lisbon Road

(Route 545); then, south on Mt. Holly Misery Rd. to State Road

Route 70 East; then, along State Road Route 70 East to the

Ocean County line)

PIPEFITTER (Including HVAC

Pipe Installation)...............$ 43.02 32.54

PLUMBER (Excluding HVAC Pipe

Installation)....................$ 43.02 32.54

ROOF0030-027 05/01/2009

Roofer

SHINGLES....................$ 23.25 13.77

SLATE AND TILE..............$ 26.25 13.77

ALL OTHER WORK..............$ 30.00 22.70

Mopper, and operator of felt-laying machine: $.50 per hour

Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour additional.

PAID HOLIDAY:

The last working day before Christmas, to be paid at the rate of four hours pay.

SFNJ0669-006 01/01/2013

SPRINKLER FITTER (Fire

Sprinklers)......................$ 44.43 21.36

SFNJ0692-002 01/01/2013

Within 15 miles beyond the city limits of Philadelphia.

Sprinkler fitter (Fire

Sprinklers)......................$ 47.55 21.17

SHEE0027-009 06/01/2012

SHEET METAL WORKER (Including

HVAC Duct Installation)..........$ 43.08 32.52

SUNJ2004-003 01/02/2009

LABORER: Common or General......$ 19.27 12.42

PLASTERER........................$ 42.33 0.00

TEAM0469-003 05/01/2011

BURLINGTON COUNTY (east of a line drawn from the New Jersey

Turnpike to the Delaware River)

Truck drivers:

Dump Truck..................$ 34.75 24.385

Off the Road Truck..........$ 34.60 24.385 where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional.

Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour

Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level

A, B or C personal protection: $1.00 per hour additional.

New Year's Day, President's Day, Decoration Day, Independence

Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas Day.

VACATION PAY CREDIT:

Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours).

TEAM0676-002 05/01/2013

BURLINGTON COUNTY (west of a line drawn from the New Jersey

Turnpike to the Delaware River)

Truck drivers:

Dump Truck Drivers..........$ 30.70 21.485

Off the Road Truck..........$ 31.05 21.485 where the worker is in direct contact with hazardous materials, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour additional.

where personal protection A, B, C or D is NOT required:

$1.00 per hour additional.

SHIFT WORK:

An owner mandated irregular shift staring any time other than between 6:00 am and 8:00 am to receive $1.00 per hour, for each hour worked, in addition to the regular rate of pay.

New Year's Day, President's Day, Memorial Day, Independence

Day, Labor Day, Presidential Election Day, Veteran's Day

(or the day after Thanksgiving, at the option of the contractor), Thanksgiving Day, the afternoon of the day before Christmas (Dec. 24) provided that the worker works in the morning, and Christmas Day, provided that the worker works or is available for work on at least two days in the week in which the holiday occurs.

BEREAVEMENT PAY:

In case of a death in the worker's immediate famiy (mother, father, wife, husband, children, brother, sister, current mother-in-law, current father-in-law, grandparents), the worker shall be allowed leave not to exceed three (3) days straight-time pay, provided that he or she shall receive no pay unless the day of death and the burial day falls on a regular work day, and not on days off, holidays, vacation, Saturdays or Sundays.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION