Questions and Answers.pdf
PDF 41 KB Posted
- Attached to
- Little Rock AFB Counter sUAS System
- Solicitation number
- FA446026Q0382
About this file
This is a Questions and Answers document for a federal contract solicitation related to Counter-Small Unmanned Aircraft Systems (C-sUAS) equipment procurement.
The document addresses a single clarification regarding training requirements. The questioner sought clarification on whether the Government intends to procure end-user level training, noting a discrepancy between the salient characteristics, which reference training completion within seven days of delivery, and the listed item quantities, which do not identify training as a separate deliverable. The Government's response clarifies that training must be coordinated with the C-sUAS Program Manager point of contact no later than seven calendar days upon shipping the equipment, rather than constituting a separate procured deliverable. This response indicates that coordination and scheduling of training is a contractual requirement, but the actual training delivery arrangements are to be negotiated directly between the contractor and the Government's program management office.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combo RFQ.pdf | ||
| Addendum 52.212-1 & 52.212-2.pdf | ||
| Provisions and Clauses.pdf | ||
| Salient Characteristics.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Question #1: The salient characteristics for the subject solicitation state that training must be completed within seven (7) days of delivery. However, training is not currently identified as a separate deliverable within the listed item quantities.
Can you please clarify whether the Government intends to procure the required end user level training referenced in the salient characteristics?
Answer #1: Per section k. in the Salient Characteristics: “Training will be coordinated with the C-sUAS Program Manager point of contact (POC) no later than seven (7) calendar days upon shipping the equipment.”