Attachment 10 Questions and Answers.pdf
PDF 50 KB Posted
- Attached to
- Drayage Moving Service for Little Rock Air Force Base Federal contract opportunity
- Solicitation number
- FA446021Q0017
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA446021Q00170001 SF 30.pdf | ||
| Attachment 1 Performance Work Statement.pdf | ||
| Attachment 6- A1 Memo Face Covering.docx | DOCX document | |
| Solicitation - FA446021Q0017.pdf | ||
| Attachment 3 Building 284 Layout.pdf | ||
| Attachment 4 Building 288 Layout.pdf | ||
| Attachment 5 DoD Guidance on the Use of Cloth Face Coverings.pdf | ||
| Attachment 7 Coronavirus Disease 2019 (COVID-19) Factsheet.pdf | ||
| Attachment 9- Use of Masks and Other Public Health Measures.pdf | ||
| Attachment 2 Wage Determination 2015-5117 Rev 14.pdf | ||
| Attachment 8- Letter to Contractors- COVID-19.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers for Drayage Move B284, B288 4 May 2021
1. What is the distance between buildings 284 and 314?
-The distance between buildings 284 and 314 is 0.8 miles
2. What is the distance between buildings 284 and 288?
-Buildings 284 and 288 are next to each other and are less than 50 feet apart.
3. What floor of the building is the furniture located on and what floor is it being moved to in the new building?
-The location of the where all items are being moved from and where they are being moved to is on the first floor.
4. Is there access to elevators?
-All items are being moved to and from the first floor of all buildings. Elevator access is not needed.
5. What are the dates you want to move for both buildings 284 and 288 to take place?
-The time frame for the move to take place is between 14 May 2021 and 21 May 2021. The winning vendor will be notified if the start date will be earlier or later, but the overall completion date will be 21 May 2021.