Questions_and_Answers._for_Flowmeter.docx

DOCX document 12 KB Posted

Attached to
Sewer Flow meter Federal contract opportunity
Solicitation number
FA4460-16-T-0057
Issued by
Department of the Air Force Air Mobility Command

About this file

Questions and Answers for the Flow meter Solicitation FA4460-16-T-0057.

View the file

Other files for this federal contract opportunity

Other files attached to Sewer Flow meter, newest first.
File Type Posted
FA4460-16-T-0057_flowmeter_amendment_02.pdf PDF
Performance_Work_Statement_(PWS)_Flowmeter_22_June_2016.doc DOC document
Flowmeter_Solicitation.docx DOCX document
Sewer_and_Manholes_detailed.pdf PDF
Wage_Determination.docx DOCX document
Performance_Work_Statement_(PWS)_Flowmeter_22_June_2016.doc DOC document
Flowmeter_Amendment.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers:

Question:

In the Performance Work Statement Section 2.2 It mentions that the contractor is responsible for the repair and replacement of flowmeters that need such. Is this quote for just the labor and expenses to service these flow meters or is the quote to also provide replacements costs? It appears it is just a technical service contract but that wording lead me to think it could be materials.

Answer:

While technically it is based on a service to maintain and calibrate the meters we do have them go bad or get damaged beyond repair and its cheaper to replace. The contractor will bear the cost of the labor and the Government will bear the cost for the replacement meter under CLIN 0015, Alteration/Repair Costs.

Question:

Is this a follow-on requirement? If so, could you please provide the incumbent contract number for this opportunity?

Yes. FA4460-15-P-0004.