Additional Questions 1) I believe that the intent of the solicitation is to replace only the two pantographs. It is not intended to upgrade the piping to meet the UFC requirements. I have attached the standard design plate for this type of refueler loading. The plate shows a strainer control valve and thermal relief is usually included (not shown). From the photos I could not confirm that the strainer and control valve are existing. Are we to bid only the pantograph replacement only We are only.

View the file

Other files for this federal contract opportunity

Other files attached to RPR (SUS) Fuel Pantograph Arm Building 546, newest first.
File Type Posted
20150804_133750_resized.jpg JPG image
20150804_133740_resized.jpg JPG image
NKAK_15-1049_-_Site_Visit_Rosters.pdf PDF
NKAK_15-1049_-_Date_Mod.pdf PDF
Attachment_2_-_Environmental_MOA.doc DOC document
Attachment_4_-_15-1049_Schedule_of_Material_Submittals.xlsx XLSX spreadsheet
Attachment_3_-_C D_Report.doc DOC document
Attachment_5_-_EMIS_Instruction_Guide.doc DOC document
Attachment_7_-_LRAFB_Information.docx DOCX document
FA4460-15-B-0010.doc DOC document
Attachment_6_-_Wage_Determination_AR150169.docx DOCX document
Attachment_1_-_NKAK_15-1049_-_SOW.doc DOC document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions for NKAK 15-1049 – Repair/Sustain Fuel Pantograph Arms B-546

Does the exiting loading areas have hose’s currently installed to load trucks that are to be replaced with 3-inch pantograph arms?

A: No, it has a solid aluminum 3” loading arm.

If loading areas currently have pantograph arms installed, are the old arms to be replaced with new pantographs that have non-lubricated swivels?

A: Yes.

Are there any other components such as additional ball valves, double block and bleed valves, or control valves required?

A: No.

Does the loading area’s presently have Scully’s Electronic Tank Truck Systems and Grounding Verification System for overfill protection installed?

A: No, not sure if R-300 loading truck, are equip with Sculley system?

In speaking with the base fuels employees, we are required to salvage the existing loading nozzles and re-install on new loading arms. Please confirm new fueling nozzles are not required.

A: Correct. New fueling nozzles are not required.

“Can you please confirm that the Air Force requirement is for a pantograph that meets the requirements of UFGS 33 52 43.12? Some of those requirements are made from stainless steel, non-lubricated joints, maintenance free, etc.”

A: Correct.