Bidders_Plumbing_Q A.docx
DOCX document 15 KB Posted
- Attached to
- Construct (R&M) Install Utility Meters Multi Facilities Federal contract opportunity
- Solicitation number
- FA4460-15-B-0006
About this file
Additional Responses
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Aug_25_Meter_List_(Autosaved).xlsx | XLSX spreadsheet | |
| 1.__SOW_Post_Q-A.docx | DOCX document | |
| Water_Utilities_Map.pdf | ||
| Aug_25_Meter_List_with_Gas_Consumption_Estimates.xlsx | XLSX spreadsheet | |
| QandA_bidders_Utility_Meters.pdf | ||
| RFIs.docx | DOCX document | |
| NKAK_15-1033_-_Site_Visit_Rosters.pdf | ||
| 24_Aug_15_SOW.docx | DOCX document | |
| NKAK151033_Meter_List.xlsx | XLSX spreadsheet | |
| Attachment_3_-_C D_Report.doc | DOC document | |
| Attachment_6_-_Wage_Determination_AR150169.docx | DOCX document | |
| Attachment_5_-_EMIS_Instruction_Guide.doc | DOC document | |
| Attachment_7_-_LRAFB_Information.docx | DOCX document | |
| Attachment_4_-_Schedule_of_Material_Submittals.pdf | ||
| Attachment_1_-_SOW_Post_Legal.docx | DOCX document | |
| Attachment_2_-_Environmental_MOA.doc | DOC document | |
| FA4460-15-B-0006.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. – Contractor is correct. The vault is currently being removed and is no longer part of the scope of this project.
2. – Yes, contractor is required to give 2 week notice prior to removing gas service at each affected facility.
3. The project scope has changed. No scope of work is required inside the chain linked fence area at the back of the golf course. However, adjacent to the north side of the fenced area (next to the golf course cart path) the contractor will be required to hot tap the gas main and install a new gas meter and install piping/valve to bypass the meter for meter maintenance. The area will require shrubs removed, a 3 sided chain link fence installed with a gate and fence slats installed to conceal the area.
a. The work may be accomplished during normal working hours. With the requirement to hot-tap the main line, there will be no need to turn off gas or relight pilot lights basewide.
4. The scope of work that requires gas utility interruptions must be accomplished during summer months. The gas to each facility must be kept to a minimum but not to exceed 8 hours unless specifically coordinated with CE and the user’s consent due to unique facility constraints.
a. Water outages must be kept to a minimum not to exceed 8 hours.
b. Hot-tapping the main will remove the need to relight pilot lights.
c. Yes, a two week notice will be required at each facility.
5. Gas usage data has been forwarded to SrA Hevrin in 19 CONS who will convey to the bidders.
6. Hot-tapping the main will remove the need to relight pilot lights.
7. Hot-tapping the main will remove the need to relight pilot lights, thus negating the issue.
8. A base map with the water piping sizes will be provided.
9. See #8
10. Yes, the contractor will be required to flush the lines at each affected facility.
11. Individual dig permits are required for each facility, but multiple permits may be submitted at the same time.
12. Acknowledged.