This document is a Questions and Answers (Q&A) file for a Repair Glycol Tanks project. The Q&A addresses several key aspects of the project, including project timeline, site access, and technical specifications. Contractors are informed that a construction estimate is available in the RFP Section A, and they should propose the number of calendar days needed for project performance. An additional site visit is scheduled for 2 September at 8 am EST, and a site map is now included as Attachment 5 of the RFP. The landfill has equipment to remove tanks from trailers, and a previous requirement for a shelter has been removed via Amendment 1. Some details are still pending, such as the preferred manufacturer and specifications for the new glycol tank, which will be provided on a subsequent Tuesday.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
CUI
Repair Glycol Tanks Q&A
Q1: Is there a cost estimate, budget or ballpark figure for the project listed? Is there an actual start date for the project?
A1: There is a magnitude of construction estimate listed in the RFP, Section A, paragraph 1. As stated in the RFP, please propose the total number of calendar days from Notice to Proceed (NTP) that you can begin performance as well as the total number of calendar days to complete performance. The actual start date of the project will depend on the award of a purchase order and the proposed total number of calendar days.
Q2. What are the specifications of the shelter?
A2. Please see amendment 1, the need for the shelter has been removed from the
SOW.
Q3. Is there a site map that you can provide for the project?
A3. Amendment 1 now includes the site map as an attachment (See Attachment 5 of the RFP).
Q4. Does the landfill have the capabilities to offload the tanks from a trailer?
A4. Yes, landfill has equipment to remove the tanks from a trailer.
Q5. Can a preferred manufacture and specification be provided for the new glycol tank?
A5. The answer to this question will be provided on Tuesday.
Q6. It was stated during the initial site visit that another scheduled site visit would be scheduled. When can contractors get access to the site for an additional site visit to view the existing tank setup? Please advise.
A6. An additional site visit will be provided 2 September at 8 am EST.