QUESTIONS AND ANSWERS

View the file

Other files

File Type Posted
Amendment0003.pdf PDF
PerformanceWorkStatement12-06.pdf PDF
ConformedSolicitationFA4452-08-R-0003-12-06.doc DOC document
Amendment0002.pdf PDF
PerformanceWorkStatement11-26.doc DOC document
FA4452-08-R-0002-Amended26Nov07.pdf PDF
Amendment0001.pdf PDF
FA4452-08-R-0002PerfPlan-Attach2.pdf PDF
FA4452-08-R-0002.pdf PDF
AppendixC-AMCForm246.pdf PDF
FA4452-08-R-0002APPENDIXA.pdf PDF
FA4452-08-R-0002PastPerformanceQuestionnaire-Attach3.pdf PDF
AppendixB-AFForm1522.pdf PDF
PerformanceWorkStatement11-14.doc DOC document
ExecutiveSummary-FA4452-08-R0002.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS FOR FA4452-08-R-0002

FLIGHT ATTENDANT TRAINING

QUESTION 1. Both the Pricing and Performance Work Statement sections show different Air Force designations for the G-III, G-IV, and G-V aircraft. We believe the following AF designations are correct:

G-III: C-20B

G-IV: C-20H

G-V: C-37A

If the above information is correct, request the Pricing and Performance Work Statement (PWS) sections be revised accordingly.

ANSWER: The AF designations listed above are correct. The solicitation and PWS will be forthcoming and revised accordingly.

QUESTION 2. Item 1.2.5 In-flight Illness Training, PWS: States the contractor shall provide American Red Cross Cardio Pulmonary Resuscitation (CPR) Certification as an optional task.

a. If the contractor currently provides American Heart Association Certified CPR training, will this be acceptable?

b. In the above statement, what is meant by “as an optional task”? Does the student have the option of not taking this training?

ANSWER: If a contractor provides American Heart Association Certified CPR training as part of the normal off-the-shelf training course please include this information as part of your proposal. The CPR training has been included as “optional” providing the Government an option to accept or decline the training for an additional cost. The contractor will be advised through delivery orders whether CPR training will be included for each training ordered.

QUESTION 3. Item 1.2.9 Fire Fighting Procedures, PWS: States the contractor shall demonstrate techniques and procedures for extinguishing fires on-board an aircraft utilizing both the halon and water fire extinguisher.

The Clean Air Act dictated that production of Halon 1301 would cease by December 31, 1993. As such, the utilization of new agents as well as recycling of existing Halon would provide the source of fire suppressants beyond this phase out date. Although the Act did not make ownership or use of Halon illegal, there are potential environmental and health concerns. Thus, if the contractor trains on this type of fire extinguisher but uses environmental friendly chemical fire fighting agents instead of Halon, is this acceptable?

ANSWER: All Air Force DV Aircraft still have water fire extinguishers. Each student will not need to operate the water extinguisher but each student should observe one in action. The halon extinguishers have been changed to halitron extinguishers and as such halitron extinguishers could be demonstrated.

QUESTION 4. Items 1.3 Deliverables and Item 4.7.4, PWS: Both items make reference to Certificates of Training being provided to students upon course completion. Due to the need for a thorough review of student records and to follow current quality control procedures, no Training Records or Certificates of Training are released to any of our students upon course completion. Be aware a Certificate of Training which acknowledges successful course completion cannot be released until the student’s Training Records are reviewed and validated. As such, request Certificates of Training be mailed to the QAP within 10 working days of student course completion.

ANSWER: PWS will be amended to reflect Certificates of Training to be mailed to the QAP within 10 working days of student course completion.

In addition, under Item 1.3 Deliverables, it appears a number of PWS paragraphs referenced are not correct.

ANSWER: PWS will be updated to reflect correct PWS paragraphs.

QUESTION 5. Item 4.7.1, PWS: States the Flight Attendant Emergency Procedures Manual is to be brought to the training session by the flight attendant student. Request additional copies of the Flight Attendant Emergency Procedures Manual are provided to the contractor for instructor reference and use. In addition, request sufficient copies of all revisions/updates to this manual be provided to the contractor in a timely manner.

ANSWER: The successful contract will be provided a complete copy of the Flight Attendant Emergency Procedures Manual upon award. In addition, the Government will provide sufficient copies of all revisions/updates to this manual in a timely manner.

QUESTION 6. Due to the anticipated time and effort involved, there is concern regarding the quick turnaround being requested (i.e., due date: Monday, 3 Dec 07).

Accounting for the Thanksgiving Holiday, the response time is further reduced. As such, request the due date be extended to Monday, 10 Dec 07.

ANSWER: The response date will be extended to 10 Dec 07.