Questions and Answers.pdf
PDF 78 KB Posted
- Attached to
- B1305 and B1355 Water Heater Renovation
- Solicitation number
- FA442722R0006
About this file
This document contains questions and answers related to a federal solicitation for water heater renovation services. The solicitation is a firm-fixed price, Service Disabled Veteran Owned Small Business set-aside issued by the Department of the Air Force Air Mobility Command for work at B1305 and B1355 dormitories. The work includes replacing boilers, indirect water heaters, and circulating pumps along with associated housekeeping pads and mechanical room lighting. The period of performance and award amount are between $500,000 to $1,000,000. Offerors shall submit proposals in accordance with instructions in Section L by the close of business on June 24, 2022. Questions must be submitted in writing to both the contracting specialist and contracting officer by this same date, with answers to be posted on SAM.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1355_1.pdf | ||
| 1305_2_3.pdf | ||
| 1355_3.pdf | ||
| 1305_1.pdf | ||
| 1355_2.pdf | ||
| Solicitation Amendment FA442722R00060003 SF 30.pdf | ||
| Attendance Sheet 21 June 2022.pdf | ||
| Solicitation Amendment FA442722R00060002 SF 30_signed.pdf | ||
| Solicitation Amendment FA442722R00060001 SF 30.pdf | ||
| B1305 Vicinity map.pdf | ||
| B1355 Vicinity map.pdf | ||
| Solicitation - FA442722R0006.pdf | ||
| Past Performance Questionnaire (PPQ).docx | DOCX document | |
| SOW XDAT 21-1020 REPAIR DHW B1355 Rev1.docx | DOCX document | |
| SOW XDAT 21-1073 REPAIR DHW B1305 Rev1.docx | DOCX document | |
| Financial Institution Reference Sheet.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions/Answers
Q1: Are there any drawings for the 35% to submit with our proposals?
A1: No. It is to be submitted during contract performance.
Q2: The SOW is asking for a NICT IV there is no Fire alarm associated with this job do we need this?
A2: Not Required. Work on the fire alarm panels in the mechanical room is not in scope.
Q3: The SOW is asking for traffic control, what is this for?
A3: This should not be required based on project scope.
Q4: The SOW is asking for lighting to be replaced what is this for?
A4: Replace mechanical room ballasts and bulbs with energy efficient LED lights.
Q5: Can the super Intendent be both safety and quality control?
A5: Per UFGS 01 45 00.00 20 Quality Control "Provide a QC Manager at the work site to implement and manage the QC program [, and to serve as the Site Safety and Health Officer (SSHO) as detailed in Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS]. [In addition to implementing and managing the QC program, the QC Manager may perform the duties of Project Superintendent."
Q6: There is mold on the walls will this need to be replaced?
A6: Remediate the mold in mechanical room. Replace section of wall if necessary.
Q7: Is a Bid Bond required?
A7: No.
Q8: Can we have as-builts of dorms, in particular floor plans?
A8: Unable to locate the as-builts. If they are found, they will be made available.
Q9: Are housekeeping Concrete pads required A9: Housekeeping pads for the boilers and indirect water heaters are required where the existing ones are deteriorated or too small for new equipment. For the circulating pumps it is preferred that they be ground mounted end suction pumps as opposed to inline pumps. These will also need housekeeping pads if the existing ones cannot be used.
Q10: Will the sign in sheet be posted?
A10: Yes, it shall be posted to SAM.gov as an attachment.
Q11: Can you provide document UFC 3-410-01, Appendix D?
A11: This should be available online