Amendment 4 - Q and A.pdf
PDF 68 KB Posted
- Attached to
- Acoustic Curtain System - Travis AFB, CA Federal contract opportunity
- Solicitation number
- FA442721Q0098
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 4 - Acoustic Curtain System Combo - Revised.pdf | ||
| Amendment 4 - S1.3 Ceiling Framing Plan & Details.pdf | ||
| Amendment 4 - AC7 Main Studio Reflected Ceiling Plan.pdf | ||
| Amendment 3 - Site visit Q and A.pdf | ||
| Acoustical Curtain System Statement of Work Review_edit 2.pdf | ||
| Acoustical Curtain System Statement of Work Review final.pdf | ||
| Contract Security Clause.pdf | ||
| Acoustic Curtain System Combo.pdf | ||
| Acoustical Curtain System Attachment 1.pdf | ||
| Attachment 1 - Real ID Act information.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA442721Q0098 - Acoustic Curtain System – Amendment 4 Q and A Response date: 25 August 2021 8:00 AM, PDT
1. Do we need to carry any costs to cover permit fees or are the drawings we were provided already approved to be built?
-As far as I know, all permits needed have already been processed/seen by CE, which would be the authority to approve any drawings or any work performed on any of the facilities on base.
2. Will the fire alarms be required to be moved as they will now be covered by a curtain?
-In accordance with the SOW, separate panels will be used to curtain the areas, instead of a single piece of fabric, we could strategically accommodate the gaps between the panels to keep the fire alarms visible.
3. On the provided drawings there is no detail on structural backing for the hanging of the brackets, for the weight of the curtains we would expect the need for backing in the walls. Please confirm what the requirements are, if any.
-Due to concerns with HVAC vents and other structures on the ceiling, it was decided by Travis AFB CE the best course of action would be to hang the curtains from the wall. I was hoping to provide contact info from a SME on CE, but at this time I’m unable to do so.
4. Please provide as-builts for the building that include what is above the ceiling in those spaces
(MEP), paint color of the room, and ceiling/wall details at a minimum.
-I’m enclosing some drawings from our Building Plans and I hope this drawings help answer this question.
5. Do we need to plan on renting temporary restrooms/handwash stations for the construction team or can we plan to have them use the facilities on site?
-The construction team will be welcome to use our facilities on site, or are welcome to procure their own. Whatever they decide will be fine with us.