Atch 4 AF66form 21 Mar 11.xls

XLS spreadsheet 29 KB Posted

Attached to
Base Roof Repairs Federal contract opportunity
Solicitation number
FA4427-11-R-0102
Issued by
Department of the Air Force Air Mobility Command

About this file

Amended Atch 4 Schedule of Material Submittals

View the file

Other files for this federal contract opportunity

Other files attached to Base Roof Repairs, newest first.
File Type Posted
Q A 2 IDC Roof Repair.docx DOCX document
QUESTIONS AND ANSWERS.docx DOCX document
0-3 SPECS 01000.doc DOC document
0-9 SPECS 07416.doc DOC document
1-0 SPECS 07510.doc DOC document
1-1 SPECS 075419.doc DOC document
0-6 SPECS 06100.doc DOC document
0-2 SPECS COVER - INDEX.doc DOC document
0-5 SPECS 05300.doc DOC document
1-2 SPECS 07550.doc DOC document
1-4 SPECS 09900 .doc DOC document
1-3 SPECS 07600.doc DOC document
0-4 SPECS 02110.doc DOC document
0-8 SPECS 073113.doc DOC document
0-7 SPECS 07220.doc DOC document
Atch 6 Past Performance Survey 21 Mar 11.doc DOC document
11R0102-0001 CONFORMED BASE ROOF.doc DOC document
11R0102-0001 Amendment 1.doc DOC document
11R0102-0001 Fill In Section B-K Base Roofs.doc DOC document
Atch 4-Schedule of Submittals.pdf PDF
Atch 5- Task Description.docx DOCX document
Atch 6 - Past Performance Survey Correct.docx DOCX document
B-K IDC Roof Repair.doc DOC document
Solicitation Roof Repair.doc DOC document
Atch 3- WD.docx DOCX document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT TITLE: IDC Base Roof RepairCONTRACT NUMBER
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERITEM OR DESCRIPTION OF

ITEM, CONTRACT REFERENCE,

TYPE OF SUBMITTAL NUMBER OF COPIES REQUIRED REQUIRED SUBMISSION DATE DATE RECEIVED IN CONTRACTING RETURN SUSPENSE DATE SUBMITTAL NUMBERS DATE

CONTRACTOR

NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
CERTIFICATION OF
COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER’S RECOMMENDATIONSMANUFACTURER’S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSAPPROVEDDIS-

APPROVED

1Accessories and Nails, Sect 06100, Para 1.05.A.13330-P
2Sheathing, Sect 06100, Para 1.05.A.2330-P
3N/A
4Submittals, Sect 05300, Para 1.2330-P
5Submittals, Sect 07416, Para 1.5330-P
6Warranties, Sect 07416, Para 1.7310-A
7Sect 07510, Para 1.06.A, 1.06B3330-P
8Sect 07510, Para 1.06.C330-P
9Sect 07510, Para 1.06.H (1) (2)3330-P
10Sect 07510, Para 1.06.E330-P
11Sect 07510, Para 1.06.F330-P
12Sect 07510, Para 1.06.E3330-P
13Sect 07600, Para 1.03.A3330-P
14Sect 07550, Para 2.1, 1.073330-P
15Material, Sect 07550, Para 2.23330-P
16Sect 07220, Para 1.023330-P
17Sect 073113, Para 1.3, 1.533330-P
18Sect 075419, Para 1.3, 1.8333330-P
LEGEND FOR SUBMITTALS:10-A-SUBMIT 10 DAYS AFTER COMPLETION OF WORK (ITEM or ITEMS) DONE
30-P-SUBMIT WITHIN 30 DAYS PRIOR TO WORK, USE, OR INSTALLATION TO BE DONE
30-PP-SUBMIT WITHIN 30 DAYS PRIOR TO PLACEMENT OF ITEMS TO BE DONE
30-PW -SUBMIT WITHIN 30 DAYS PRIOR TO START OF WORK TO BE DONE
30-P&A -SUBMIT WITHIN 30 DAYS & NEED APPROVAL BEFORE USE

&RFA4427-11-R-0102-01

&LAttachment #4 21 Mar 2011&RPage1 0f 1