This document is a Request for Information (RFI) related to a fiber optic installation at the LMERWS facility. The key details are:

The Air Education and Training Command is issuing a Request for Quote (RFQ) for fiber connectivity to the LMERWS facility at Ebbing ANGB, Fort Smith, AK. The service required includes the purchase and installation of 24 strands of single-mode fiber optic cable from Building 182 to the LMERWS control panel, a distance of approximately 850 feet. The RFI contains a series of questions and answers related to the installation, including requirements for underground conduits, manholes, pull strings, internet speeds, and IP addresses. The government confirms that a dedicated internet circuit is not required, only a dedicated fiber run. The solicitation will be available on sam.gov, and all prospective contractors must be registered in the System for Award Management (SAM) prior to submitting proposals.

View the file

Other files for this federal contract opportunity

Other files attached to Fiber Optic Installation at LMERWS Facility, newest first.
File Type Posted
Attachment 6 - Fiber installation RFI.pdf PDF
Attachment 6 - Fiber installation RFI.pdf PDF
Attachment 6 - Fiber installation RFI.pdf PDF
Combined_Synopsis_Solicitation.pdf PDF
Attachment 1 - PWS for FA441924Q0061.pdf PDF
Attachment 2 - Evaluation Factors for FA441924Q0061.pdf PDF
Attachment 3 - Wage Determination.pdf PDF
Attachment 4 - Instructions to Offerors for FA441924Q0061.pdf PDF
Attachment 5 - Clauses and Provisions.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI# Date Submitted Question Date of

Response Government Response

1 9/4/2024 Will we still need to provide the short section of underground conduit from the SAP building j-box to the LMERWS?

9/4/2024 Yes the contractor will need to provide this.

2 9/11/2024 Are there any manholes we will be pulling our fiber through? If yes, how many? Also, if yes, will we be responsible for pumping water out of manholes?

9/12/2024 There are 2 hand holes and 1 manhole, and the contractor is not responsible for pumping water out of them.

3 9/11/2024 Is there a pull string in the existing duct bank we will be pulling our fiber through? 9/12/2024 The contractor will need to provide a pull string.

4 9/12/2024 What is the exact speed of the internet to be installed? 9/12/2024

Since fiber will be installed, the speed of the internet shouldn’t be a factor as long as the fiber is not damaged and the ends are terminated corrected with decibel loss fit to industry standards.

5 9/12/2024 Do you need Static IPs, if so how many? 9/12/2024 Static or Dynamic IPs shouldn’t be a factor because everything is going to be government network and whether it is one or the other will be decided internally.

6 9/12/2024 Please confirm that it is a dedicated internet circuit that would be required. 9/12/2024 No dedicated internet circuit will be required. The requirement is just for a dedicated fiber run.