Joint_Base_Charleston_Generator_Monitoring_RFI_Responses.pdf
PDF 126 KB Posted
- Attached to
- Charleston Generator Monitoring System
- Solicitation number
- FA441826Q0082
About this file
This document is the official Government Responses to Requests for Information (RFI) from the Department of the Air Force Joint Base Charleston for a Generator Fleet Monitoring & Cybersecurity Integration project. The Government will procure a turn-key monitoring solution for approximately 65 generator systems and associated Automatic Transfer Switch (ATS) units across the Air Base and Naval Weapons Station. The solution must be delivered by December 18, 2026, and will operate under a Firm-Fixed-Price (FFP) contract structure. All proposed hardware, software, and configurations must strictly comply with Department of the Air Force and DoD cybersecurity mandates, including FIPS 140-2/140-3 cryptographic validation for all data-in-transit, DISA Approved Products List (APL) requirements for managed switches, and Trade Agreements Act (TAA) compliance. The project scope is strictly monitoring-only with no remote control capabilities permitted.
The contractor must provide a complete edge hardware package in weatherproof NEMA 4X enclosures at each generator site, including protocol conversion gateways (Modbus, J1939, CDL, ProtoNode) for approximately 40 older Cummins units with PCC controllers, a FIPS-validated inline security appliance (such as Fortinet FortiGate Rugged 60F or Cisco ISA 3000) as a compensating control, a centralized HMI display with audible and visual alarm annunciation, DC power buffering, and onboard data buffering with minimum 30 days of offline logging. The system must support future expansion capacity of 25% (minimum 82 total nodes) without software replacement. The Government will provide all physical network cabling and drops, IP addressing, VPN parameters, and standard operating power. The contractor is responsible for initial vulnerability scanning and providing standard RMF artifacts, while formal RMF approval and Authority to Connect (ATC) are Government responsibilities. No pre-award site visits, network diagrams, or facility drawings will be provided due to operational security and critical infrastructure protection protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Generator Equipment List.xlsx | XLSX spreadsheet | |
| SOW Gen Remote Monitoring.pdf | ||
| Wage Determination No._ 2015-4427-33.pdf | ||
| Solicitation - FA441826Q0082.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
JOINT BASE CHARLESTON (628TH AIR BASE WING)
Document Type: Official Responses to Contractor Requests for Information (RFI)
Project Title: Generator Fleet Monitoring & Cybersecurity Integration
1. INSTRUCTIONS TO OFFERORS
This document constitutes the official Government responses to Requests for Information (RFIs) submitted by prospective contractors.
1. Contractual Precedence: These responses clarify and supplement the technical specifications, Statement of Work (SOW), and solicitation requirements.
2. Pricing Baseline: Offerors must base their Firm-Fixed-Price (FFP) proposals on the explicit directions, assumptions, and guidance provided below.
3. Security Standards: All proposed hardware, software, and configuration methodologies must strictly adhere to the Department of the Air Force and DoD cybersecurity mandates referenced herein.
2. RFI QUICK-REFERENCE INDEX
RFI
Topic / Area of Inquiry Direct Policy / Standard Reference
Network Diagrams, Switch Inventories &
IP Addressing
Controlled Unclassified Information
(CUI) Policy
FIPS 140-2 / FIPS 140-3 Cryptographic
Validation
DAFGM2026-32-01 (Paras 3.3.5, 3.4.5.1.2, 3.4.7)
RFI
Topic / Area of Inquiry Direct Policy / Standard Reference
03 Pre-Award Site Visits Joint Base Charleston OPSEC
Guidelines
04 Network Switch Replacement Boundaries DAFGM2026-32-01 (Para 3.6.2) / DISA
APL
05 Testing & Acceptance Criteria Post-Installation Closeout
Requirements
Government-Furnished Network
Connectivity & IPs SOW Section Boundary
07 Monitoring Platform / OEM Equivalency Brand Name or Equal Policy
Minimum Monitored Devices & Future
Capacity Fleet Scaling & Hardware Baseline
Known Incompatible Generators / ATS
Controllers
LonWorks-to-Modbus Protocol
Gateways
Vulnerability Scanning & Remediation
Responsibility
DAFGM2026-32-01 (Paras 3.3.10 &
3.3.12)
Identification of Existing Government
Switches Base Infrastructure Boundaries
Historical Trending, Event Logging &
Data Retention Buffering and Logging Minimums
13 Unknown/Legacy Interfaces Under FFP FAR Contract Modification Procedures
FortiGate Licensing & Management
Requirements IPsec VPN Tunnel Baseline
15 Initial Configuration Responsibility Post-Award Gov-Furnished IP / VPN
Parameters
16 Trade Agreements Act (TAA) Compliance TAA Federal Mandate
Cabling & Network Drop Physical
Boundaries SOW Demarcation (RJ45 Hand-off)
Topic / Area of Inquiry Direct Policy / Standard Reference
18 Acceptability of Unmanaged Switches DAFGM2026-32-01 (Para 3.6.2) / DISA
APL
Generator/ATS Site Photos & Estimating
Assumptions Phased Post-Award Physical Discovery
General Solicitation Drawings & Critical
GIS Site Data
Operational Security (OPSEC) / Critical
Infrastructure
System Functional Scope: Monitoring vs.
Control Monitoring-Only Policy
Civil Network Infrastructure Cabling
Boundary
SOW Demarcation (Civil Works
Excluded)
Hardware, Enclosures & Managed
Switches
Weatherproof NEMA 4X & DISA APL
Mandates
Cybersecurity, RMF & FIPS Compliance
Framework COIN Enclave RMF & GFE Scans
Proposal Pricing Basis & Differing Site
Conditions
Fleet Size Schedule & Standard FAR
Clauses
Functional Requirements: Telemetry &
Retention Telemetry Point List & Data Buffering
Pre-Award Network Topology & CUI Data
Releases
Controlled Unclassified Information
(CUI) Post-Award
Physical Demarcation Point & Civil
Infrastructure RJ45 Enclosure Termination Boundary
29 Contractor Switch Integration Guidelines DISA APL Managed Switch
Requirements
30 Permanent Equipment Power Provision Gov-Furnished Power (AC/DC) &
Buffering
Standalone Server, Operator Stations &
Central HMI
Centralized HMI & Local Infrastructure
Scope
Topic / Area of Inquiry Direct Policy / Standard Reference
Cybersecurity Framework, RMF Artifacts
& FIPS
COIN / DAFGM2026-32-01 Compliance
Operational Testing & Final System
Acceptance End-to-End Configuration Validation
Target Delivery Date (December 18, 2026) Final Closeout & Lead-Time Phasing
Operational Security & Pre-Award Site
Access Joint Base Charleston OPSEC Policy
Mandate for FIPS-Validated Inline
Security Appliances
FIPS Cryptographic Compensating
Controls
Enclave Traffic Encryption vs. Firewall
Isolation
DAFGM2026-32-01 IPsec Tunnel
Mandate
Required Bid Items: Enclosures, Buffers, HMI, Alarms Turn-key Firm-Fixed-Price Scope
3. OFFICIAL RFI RESPONSES
RFI-01: Network Diagrams, Switch Inventories & IP Addressing Schemes
Government Response: No pre-award network diagrams or IP schemes will be provided. This information is Controlled Unclassified Information (CUI) and will only be provided to the winning contractor post-award on a need-to-know basis. The Government
(628 CS / CE) will provide all IP addressing, subnetting, and VLAN configurations post-award.
RFI-02: FIPS 140-2 / FIPS 140-3 Cryptographic Validation
Government Response: Yes, FIPS validation is mandatory. Per DAFGM2026-32-01
(Paras 3.3.5, 3.4.5.1.2, 3.4.7), all data-in-transit traversing the base network enclave must utilize FIPS 140-2 or FIPS 140-3 validated encryption (e.g., IPsec VPN tunnel, TLS
1.3, SSH v2.0+). If an edge gateway is not natively FIPS-validated, the contractor must bundle an approved inline FIPS-validated security appliance (e.g., Cisco ISA 3000, Fortinet FortiGate Rugged 60F) as a compensating control.
RFI-03: Pre-Award Site Visits
Government Response: Due to operational security, time constraints, and the geographic dispersion of generator assets across Joint Base Charleston (Air Base and NWS), pre-award site visits will not be conducted. Offerors must base their proposals on the generator schedule and technical specifications provided in the solicitation.
RFI-04: Network Switch Replacement (Base Infrastructure vs. Contractor
Hardware)
Government Response: Offerors will NOT replace base network infrastructure switches.
Base switches are Government-owned and maintained by the 628th Communications
Squadron. However, per DAFGM2026-32-01 (Para 3.6.2), any switch provided by the contractor inside vendor enclosures (such as the HMI panel) MUST be a managed switch on the DISA Approved Products List (APL). Unmanaged switches are strictly prohibited.
RFI-05: Testing & Acceptance Criteria
Government Response: System acceptance criteria includes:
1. Verified end-to-end data communication from each generator controller to the central monitoring interface/HMI.
2. Telemetry point validation (Engine Running/Not Running, Auto/Manual mode, Common Fault, battery voltage, fuel level).
3. Alarm/event annunciation, acknowledgment, and audible/visual alert verification.
4. FIPS-validated encrypted tunnel operational validation.
5. Submission of post-installation documentation: as-built wiring/network diagrams, IP tables, configuration backups, and RMF artifact documentation.
RFI-06: Government-Furnished Network Connectivity & IP Addressing
Government Response: Yes. The Government (628 CS) will provide physical network drops (cabling/terminations) to the generator enclosure locations and furnish all required private IP addressing and network routing. The contractor ’s scope is edge hardware installation, controller interfacing, and logical configuration to the provided drop.
RFI-07: Monitoring Platform / OEM Equivalency
Government Response: This is an open-architecture, brand-name-or-equal solicitation.
Offerors may propose an equivalent monitoring platform provided it meets all functional monitoring capabilities, protocol integration requirements (Modbus, J1939, CDL, etc.), TAA compliance, and DAF/DoD cybersecurity mandates.
≈ 65
RFI-08: Minimum Monitored Devices & Spare Capacity
Government Response: The baseline project scope encompasses approximately generator systems (and associated ATS units where applicable). The proposed system architecture and central software/HMI must support these units plus a minimum future expansion capacity (minimum total nodes) without requiring software replacement or major architectural redesign.
RFI-09: Known Incompatible Generators / ATS Controllers
Government Response: As detailed in the provided generator list, approximately older Cummins units (equipped with PCC 2100/3100/3200 controllers) require LonWorks-to-Modbus protocol gateways (e.g., FT-10 cards / ProtoNodes). Offerors must include necessary protocol translation gateways/cards in their proposal. Full OEM engine controller replacements are not required.
RFI-10: Vulnerability Scanning & Remediation Responsibility
Government Response: This is a joint responsibility per DAFGM2026-32-01 (Paras
3.3.10 & 3.3.12). The contractor must conduct initial vulnerability scans of all delivered hardware/firmware, provide scan reports, and document mitigations prior to final acceptance. The Government (CE ISSM/ISSO and 628 CS) will perform validation scans using Government Furnished Equipment (GFE) prior to granting Authority to Connect
(ATC) to the network enclave.
RFI-11: Identification of Existing Switches to Remain in Service
Government Response: See response to Question 4 (RFI-04). All existing base facility network switches remain in service under Government management. The contractor is only responsible for contractor-furnished switches within their own assemblies (which must be DISA APL managed switches).
RFI-12: Historical Trending, Event Logging & Data Retention
Government Response: Yes. Edge devices must provide onboard data buffering
(minimum days of offline event/fault logging during network loss). The central monitoring/HMI solution must provide historical trending, alarm logging, and minimum -year searchable event retention.
65 25%
RFI-13: Unknown/Legacy Interfaces Under Firm-Fixed-Price (FFP)
Government Response: Offerors should structure their fixed-price proposal using the provided generator schedule, pricing standard communication modules/gateways
(Modbus, J1939, CDL, ProtoNode) across the fleet. Discovery will occur in phases during deployment. Any edge unit requiring modifications fundamentally outside the scope of the solicitation will be addressed via standard FAR contract modification procedures with the
Contracting Officer.
RFI-14: FortiGate Licensing & Management
Government Response: Standard/Unified threat protection licensing is sufficient.
Enterprise subscriptions or centralized FortiManager licenses are not required. The primary purpose of the appliance is to establish a FIPS-compliant IPsec tunnel to the base enclave.
RFI-15: Initial Configuration
Government Response: The vendor is not expected to know the base network configurations prior to installation. Post-award, the Government (628th Communications
Squadron / CE Cyber) will provide the required IP addressing schemas, subnets, and pre-shared VPN parameters for the vendor to configure the appliances.
RFI-16: TAA Compliance
Government Response: Yes, Trade Agreements Act (TAA) compliance is strictly mandatory for all hardware procured for this project, including any third-party security appliances (e.g., Fortinet).
RFI-17: Cabling & Network Drops
Government Response: Confirmed. As defined in the Statement of Work, the
Government is responsible for routing external physical network cabling to the generator sites. The vendor's physical network responsibility ends at the RJ45 handoff inside their provided enclosure.
RFI-18: Unmanaged Switch in HMI Panel
Government Response: No, an unmanaged switch is not acceptable. Per the newly released Department of the Air Force Guidance Memorandum DAFGM2026-32-01 (Para
3.6.2), all control systems must utilize managed network switches that are on the DISA
Approved Products List (APL) to enforce physical and logical port security. The vendor must revise their quote to include a compliant managed switch.
RFI-19: Generator/ATS Photos & Information
Government Response: Due to time and manpower constraints, the Government will not be providing the requested site photos prior to the quote deadline. The vendor should proceed by assuming all unverified units require the additional communication cards/ProtoNodes and price them into the proposal accordingly. Physical verification can be performed by the vendor during the phased installation process.
RFI-20: General Solicitation, Drawings & Site Data
Government Response:
In accordance with operational security (OPSEC) and critical infrastructure protection guidelines, no electrical one-line diagrams, building floor plans, GIS/KMZ files, telecommunications room locations, or pre-award site visits will be provided.
Offerors must base their firm-fixed-price proposals on the generator schedule and specifications provided in the solicitation. Detailed physical mounting locations and facility access will be coordinated post-award during the project kickoff and phased rollout.
RFI-21: System Scope: Monitoring vs. Control
Government Response:
This project is strictly MONITORING ONLY. No remote-control capabilities (e.g., remote generator start/stop, remote ATS transfer, or remote exercise initiation) are permitted or required.
The system is an independent, turn-key monitoring solution delivering engine telemetry (Run/Stop, Auto/Manual, Faults, Battery Voltage, Fuel Level) to the contractor-provided central HMI display. Base GIS mapping engines and sequence-of-events recording are out of scope.
RFI-22: Network Infrastructure & Cabling Boundary
Government Response:
As stated in the SOW, the Government (628 CS) is responsible for routing all external physical network cabling and installing active network drops to the generator enclosures. The Contractor is NOT responsible for civil trenching, boring, or pulling base fiber/copper between buildings.
The Contractor ’s responsibility begins at the RJ45 handoff inside the contractor-furnished generator enclosure.
RFI-23: Hardware, Enclosures & Managed Switches
Government Response:
Offerors must provide turn-key edge hardware packages in weatherproof, lockable
NEMA 4X enclosures mounted adjacent to or on the generator housings.
Protocol conversion gateways (Modbus, J1939, CDL, ProtoNode for older
Cummins units) must be included by the offeror to interface with the existing controllers listed in the equipment schedule. Full engine controller replacements are not required.
Per DAFGM2026-32-01 (Para 3.6.2), any network switch provided by the contractor (e.g., inside the HMI assembly) must be a managed switch listed on the
DISA Approved Products List (APL).
RFI-24: Cybersecurity, RMF & FIPS Compliance
Government Response:
The system will reside within the Civil Engineering control systems network enclave
(COIN).
FIPS 140-2/3 validation is mandatory for all data-in-transit traversing the network enclave. If edge gateways lack native FIPS validation, an inline FIPS-validated micro-firewall (e.g., Cisco ISA 3000, Fortinet FortiGate Rugged 60F) must be bundled as an approved compensating control.
All hardware must be TAA compliant. Wireless, Bluetooth, and cellular connections are strictly prohibited (DAFGM2026-32-01, Para 3.4.5.1.6).
The Contractor is responsible for providing standard vendor RMF artifacts
(hardware/software lists, port/protocol/service sheets, architecture diagrams, and initial vulnerability scan results). Formal RMF package submission into eMASS and
ATO/ATC approvals are Government responsibilities.
RFI-25: Proposal Basis & Differing Conditions
Government Response: Pricing must be based on the units listed in the solicitation. Physical discovery and verification of unconfirmed communication cards will take place post-award during the phased installation. Any unforeseen condition fundamentally outside the solicitation scope will be handled via standard FAR contract modification procedures with the Contracting Officer.
RFI-26: Required Monitoring Functions
Government Response: This project is strictly MONITORING ONLY. No remote control capabilities (e.g., remote generator start/stop, remote exercise, or remote ATS transfer commands) are permitted or required. The system will deliver basic engine telemetry
(Run/Stop, Auto/Manual, Faults, Battery Voltage, Fuel Level) to the contractor-provided central HMI display. Onboard edge devices must provide data buffering (minimum days of offline event/fault logging during network loss), and the central software/HMI solution must provide historical trending and a minimum of -year searchable event retention. Polling and screen-refresh intervals are expected to align with standard industry monitoring practices for utility systems.
RFI-27: Existing Network Infrastructure, Diagrams & Drawings
Government Response: In accordance with operational security (OPSEC) and critical infrastructure protection guidelines, no electrical one-line diagrams, physical floor plans, GIS/KMZ files, telecommunications room locations, switch models, or pre-award network topologies will be provided. This information is Controlled Unclassified Information (CUI) and will only be provided to the winning contractor post-award on a need-to-know basis.
Detailed physical mounting locations and facility access will be coordinated post-award.
RFI-28: Network Construction & Cabling Boundary
Government Response: As stated in the SOW, the Government (628 CS) is responsible for routing all external physical network cabling and installing active network drops to the generator enclosures. The Contractor is NOT responsible for civil trenching, boring, building penetrations, or pulling base fiber/copper between facilities. The Contractor ’s physical boundary and responsibility begins at the RJ45 handoff inside the contractor-furnished generator enclosure.
RFI-29: Network Switch Replacement
Government Response: Offerors will NOT replace base network infrastructure switches.
Base switches are Government-owned and maintained by the 628th Communications
Squadron. However, per DAFGM2026-32-01 (Para 3.6.2), any network switch provided by the contractor inside vendor enclosures (such as the HMI panel) MUST be a managed switch listed on the DISA Approved Products List (APL). Unmanaged switches are strictly prohibited.
RFI-30: Permanent Equipment Power
Government Response: The Government will provide standard operating power options
(AC) at the HMI location and DC starting battery access ( ) at the generator enclosures. If the contractor's specific monitoring components require secondary power conditioning, the contractor must supply appropriate AC/DC power supplies or surge protection within their enclosures as part of their turn-key proposal.
12 VDC/24 VDC
RFI-31: Server, Operator & HMI Equipment
Government Response: The contractor must provide a complete, standalone centralized HMI package (display, processor, and mounting enclosure) to monitor fleet-wide status, telemetry, and alarms. On-premise server architecture and physical server-room rack space are out-of-scope. Redundancy, concurrent user count, and backup systems must align with standard commercial best practices for a -node fleet.
RFI-32: Cybersecurity, RMF & FIPS Compliance
Government Response: The system will reside within the Civil Engineering control systems network enclave (COIN). FIPS 140-2/3 validation is mandatory for all data-in-transit traversing the network enclave. If edge gateways lack native FIPS validation, an inline FIPS-validated micro-firewall (e.g., Cisco ISA 3000, Fortinet FortiGate Rugged 60F) must be bundled as an approved compensating control. Wireless, Bluetooth, and cellular connections are strictly prohibited (DAFGM2026-32-01, Para 3.4.5.1.6). The Contractor is responsible for providing standard vendor RMF artifacts (hardware/software lists, port/protocol/service sheets, architecture diagrams, and initial vulnerability scan results).
Formal RMF package submission into eMASS and ATO/ATC approvals are Government responsibilities.
RFI-33: System Acceptance Criteria
Government Response: System acceptance criteria includes:
1. Verified end-to-end data communication from each generator controller to the central monitoring interface/HMI.
2. Telemetry point validation (Engine Running/Not Running, Auto/Manual mode, Common Fault, battery voltage, fuel level).
3. Alarm/event annunciation, acknowledgment, and audible/visual alert verification.
4. FIPS-validated encrypted tunnel operational validation.
5. Submission of post-installation documentation: as-built wiring/network diagrams, IP tables, configuration backups, and RMF artifact documentation.
RFI-34: December 18, 2026 Delivery Date
Government Response: The December 18, 2026 date represents the final target date for physical installation, operational testing, and submission of final project closeout deliverables. Offerors may propose an alternate phased timeline if required by equipment lead times, which will be evaluated during the source selection process.
RFI-35: Site Visit
Government Response: Due to operational security, time constraints, and the geographic dispersion of generator assets across Joint Base Charleston, pre-award site visits will not be conducted. Offerors must base their proposals on the generator schedule and technical specifications provided in the solicitation.
RFI-36: Requirement for FIPS-Validated Inline Appliance
Contractor Query: Please confirm that the Fortinet device or similar is indeed required and should be included in the bid.
Government Response: Yes, confirmed. In accordance with Department of the Air Force and DoD cybersecurity mandates (and DAFGM2026-32-01), all devices operating on the
Civil Engineering Control Systems network (COIN) must comply with FIPS cryptographic standards. Because the proposed edge gateway lacks native FIPS 140-2/3 validation, an inline, FIPS-validated security appliance (such as a Fortinet FortiGate Rugged 60F, Cisco
ISA 3000, or equivalent TAA-compliant device) must be included in the proposal as an approved compensating control.
RFI-37: Encryption vs. Firewall/Isolation
Contractor Query: Please confirm whether the traffic needs to be encrypted, and if not, that the gateway acts simply as a firewall and management access point.
Government Response: Traffic MUST be encrypted using FIPS-validated cryptography.
Per DAFGM2026-32-01 (Paras 3.3.5 & 3.4.7), all telemetry data-in-transit traversing the network enclave must be protected via FIPS-validated cryptographic modules (e.g., establishing a secure IPsec VPN tunnel from the edge appliance back to the central enclave boundary). The inline appliance serves as both a FIPS encryption endpoint and a stateful firewall.
RFI-38: Inclusion of Enclosures, Power Buffering, Central HMI, and Alarms
Contractor Query: Please confirm for each item whether we should include it in the bid
(Padlockable enclosure, DC power buffer, Centralized HMI, Audible/Visual alarm annunciation) and whether they should be broken out in a supplement or included in the primary submission.
Government Response: All four (4) items ARE REQUIRED and must be included in the primary firm-fixed-price proposal/CLIN structure as part of the turn-key solution:
1. Padlockable Enclosure: Required. A lockable, weatherproof NEMA 4X enclosure must be provided at each generator site to house the gateway, security appliance, and associated hardware (DAFGM2026-32-01, Para 4.5.1).
2. DC Power Buffer: Required. The contractor must provide power conditioning/buffering to prevent brownouts/reboots of the gateway and security appliance during generator engine cranking.
3. Centralized HMI: Required. The contractor must provide a complete centralized
HMI package (display, processor, and mounting enclosure) to monitor fleet-wide status, telemetry, and alarms. (Reminder: Per DAFGM2026-32-01 Para 3.6.2, any internal network switch within the HMI enclosure must be a DISA APL managed switch).
4. Audible and Visual Alarm Annunciation: Required. The central HMI package must include audible (buzzer/horn) and visual (strobe/beacon) alarm indicators for active generator/ATS fault conditions.
12 VDC/24 VDC
File details come from the government source that posted it. Updated .