This is a Statement of Work (SOW) for IT cable installation services at the 841st Transportation Battalion Modular Office Building located at 2596 Basin Road, North Charleston, SC 29406, on the Naval Weapon Station of Joint Base Charleston. The project is procured on a Firm Fixed Price (FFP) basis and requires the contractor to furnish all personnel, supervision, management, vehicles, labor, tools, materials, transportation, handling, and safety equipment necessary to complete the installation.
The scope of work includes installing CAT6 wire with 35-40 network drops from a central network switch and/or patch panel to individual office spaces throughout the modular building. The contractor must install wall plates for both NIPR data/VoIP and network cables, and provide and install Avaya VoIP model #9611G phones. Work shall be performed between 0800 and 1600 hours, Monday through Friday, excluding 11 specified federal holidays. The contractor is responsible for coordinating security access with the 841st Security Officer (Mr. John Wood, 843-296-4172) at least 10 days prior to work by new individuals. The primary Point of Contact for oversight, quality assurance, and inspections is the Contracting Officer's Representative (COR), Mr. Michael Mantica (843-794-0536, Michael.a.mantica.civ@army.mil), with an alternate POC, Mr. Daniel Hollington (843-830-5888). The contractor bears full liability for all damages or losses caused by fault or negligence, including restoration of any damage resulting from operations. Floor penetrations through sealed conduits are limited to a maximum diameter of 3 inches, interior wall openings must be covered by standard 2x4 white faceplates with cabling routed through the floor, and exterior wall breaches are prohibited. Specifically, the contractor is authorized one drill hole in the network closet, one total hole in the conference room, and two total holes in a larger office.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Description/Specifications
841st Transportation Battalion Modular Office Building IT Cable Installation
30 July 2025
The purpose of this procedure is to provide uniform guidance with respect to policy and responsibilities for the IT cable installation in the modular office building for 841st Transportation Battalion located in Charleston, South Carolina 29406.
1. GENERAL REQUIREMENTS
1.1 SCOPE OF WORK
FIRM FIXED PRICE (FFP): The Contractor shall furnish all personnel, supervision, management, vehicles, labor, tools, materials, transportation, handling and safety equipment necessary to provide the required IT cable installation within the 841st Transportation Battalion Modular Office Building as detailed below. Firm-Fixed Price for this Purchase Order will include all expected costs and charges including the following:
a) Wire (CAT6) with 35-40 network drops in a long term temporary modular office BLDG from a central network switch and/or patch panel to individual office spaces. They will install wall plates for both NIPR data/VoIP and network cables from the network switch/patch panel to the individual offices or workstations. The contractor will provide and install Avaya VoIP model # 9611G phone as seen in the diagram below.
2. FLOOR PLAN
3. LOCATION
The 841st Transportation Battalion is located on the Naval Weapon Station of Joint Base Charleston.
Specific (approximate) location of mobile office building set up is: 2596 Basin Road, North Charleston, SC 29406. This is in the vicinity of “TC Dock”. Contractor shall use the commercial entrance off Virgina Avenue.
4. POINT OF CONTACT
The primary Point of Contact (POC) for this project, who will oversee and conduct Quality Assurance, Delivery, Inspections, Processing Invoices, Damage Reports, etc., is the COR, Mr. Michael Mantica.
His phone number is 843-794-0536 and email is Michael.a.mantica.civ@army.mil. Alternate POC will be the S4, Mr. Daniel Hollington. His phone number is 843-830-5888. Any email correspondence shall include both the primary and alternate POCs.
5. CONTRACTOR RESPONSIBILITIES
The Contractor is responsible for coordinating with the 841st Security Officer for access onto the Naval Weapon Station. This shall be done at least 10 days prior for new individuals. The Security Officer is Mr. John Wood. His phone number is 843-296-4172 and email is john.w.wood12.civ@army.mil.
6. WORKING HOURS
Work shall be performed and completed between 0800 and 1600, Monday through Friday, except for Federal Holidays as detailed below.
7. FEDERAL HOLIDAYS
The following Federal holidays shall be observed as indicated below. If a regular workday falls on a holiday, the delivery, pick-up, or services shall not be performed on that day. If a holiday falls on a Saturday, the preceding Friday is observed as a Federal Holiday. If a holiday falls on a Sunday, the following Monday is observed as a Federal holiday. Below are the Federal Holidays to be observed:
1. New Year’s Day
2. MLK Day
3. President’s Day
4. Memorial Day
5. Juneteenth
6. Independence Day
7. Labor Day
8. Columbus Day
9. Veteran’s Day
10. Thanksgiving Day
11. Christmas Day mailto:Michael.a.mantica.civ@army.mil mailto:john.w.wood12.civ@army.mil
8. DAMAGES
The Contractor shall be liable for all damages or losses caused by the fault or negligence of their agents, employees, or equipment. The Contractor shall fully restore any damage resulting from their operations.
Approved floor penetrations through a sealed conduit are restricted to a maximum diameter of 3 inches.
If wall penetrations are required, they must not breach any exterior walls. Furthermore, any interior wall opening must be small enough to be completely covered by a standard 2x4 white faceplate, with cabling routed through the floor instead.
1st) Drill: One (1) hole in the network closet.
2nd) Drill: One (1) total holes (red circle) on the Floor: (1 on the floor, 1 on the wall jack) in the conference room.
3rd) Drill: Two (2) total holes (red circle) on the Floor: (2 on the floor, 2 on the wall jack) in a larger office.
8.1 The Contractor shall be responsible for all damages to persons or property resulting from the Contractor’s labor personnel and sub-Contractors fault or negligence as well as, for the payment of any civil fines or penalties which may be assessed by any Federal, State, or Local regulatory agency as a result of the Contractor’s labor personnel or sub-Contractor’s violation of any Federal, State, or Local law, Regulation or permit condition or associated requirement.
| Statement of Work (SOW) Description/Specifications |
| 1. GENERAL REQUIREMENTS |
| 2. FLOOR PLAN |
| 3. LOCATION |
| 4. POINT OF CONTACT |
| 5. CONTRACTOR RESPONSIBILITIES |
| 6. WORKING HOURS |
| 7. FEDERAL HOLIDAYS |
| 8. DAMAGES |
File details come from the government source that posted it. Updated .