SHEET TITLE ORIGINAL DATE REVISION REVISION DATE
G001 TITLE SHEET 8/21/2015
G100 BASIS OF DESIGN 8/21/2015
G200 CONSTRUCTION PHASING PLAN (CSPP) 8/21/2015
G201 CSPP - PARTIAL AIRSPACE IMAGINARY SURFACES 8/21/2015
G202 CSPP - NOTES 8/21/2015
C001 CIVIL ABBREVIATIONS AND GENERAL NOTES 8/21/2015
C101 EXISTING SITE AND DEMOLITION PLAN - AREA 1 8/21/2015
C102 EXISTING SITE AND DEMOLITION PLAN - AREA 2 8/21/2015
C103 EXISTING SITE AND DEMOLITION PLAN - AREA 3 8/21/2015
C104 EXISTING SITE AND DEMOLITION PLAN - AREA 4 8/21/2015
C105 EXISTING SITE AND DEMOLITION PLAN - AREA 5 8/21/2015
C106 EXISTING SITE AND DEMOLITION PLAN - AREA 6 8/21/2015
C107 EXISTING SITE AND DEMOLITION PLAN - AREA 7 8/21/2015
C201 SITE PLAN - AREA 1 8/21/2015
C202 SITE PLAN - AREA 2 8/21/2015
C203 SITE PLAN - AREA 3 8/21/2015
C204 SITE PLAN - AREA 4 8/21/2015
C205 SITE PLAN - AREA 5 8/21/2015
C206 SITE PLAN - AREA 6 8/21/2015
C207 SITE PLAN - AREA 7 8/21/2015
C211 MARKING PLAN - AREA 1 8/21/2015
C212 MARKING PLAN - AREA 2 8/21/2015
C213 MARKING PLAN - AREA 3 8/21/2015
C214 MARKING PLAN - AREA 4 8/21/2015
C215 MARKING PLAN - AREA 5 8/21/2015
C216 MARKING PLAN - AREA 6 8/21/2015
C217 MARKING PLAN - AREA 7 8/21/2015
C220 MARKING DETAILS 8/21/2015
C221 MARKING DETAILS 8/21/2015
C301 GRADING AND STORM DRAINAGE PLAN - AREA 1 8/21/2015
C302 GRADING AND STORM DRAINAGE PLAN - AREA 2 8/21/2015
C303 GRADING AND STORM DRAINAGE PLAN - AREA 3 8/21/2015
C304 GRADING AND STORM DRAINAGE PLAN - AREA 4 8/21/2015
C305 GRADING AND STORM DRAINAGE PLAN - AREA 5 8/21/2015
C306 GRADING AND STORM DRAINAGE PLAN - AREA 6 8/21/2015
C307 GRADING AND STORM DRAINAGE PLAN - AREA 7 8/21/2015
C310 TAXIWAY PROFILES 8/21/2015
C311 TAXIWAY PROFILES 8/21/2015
LIST OF DRAWINGS C320 CROSS SECTIONS 8/21/2015
C321 CROSS SECTIONS 8/21/2015
C322 CROSS SECTIONS 8/21/2015
C323 CROSS SECTIONS 8/21/2015
C324 CROSS SECTIONS 8/21/2015
C620 PAVING SECTIONS 8/21/2015
C621 PAVING DETAILS 8/21/2015
C622 PAVING DETAILS 8/21/2015
C630 GRADING AND STORM DRAINAGE DETAILS 8/21/2015
C640 UTILITY DETAILS 8/21/2015
C641 UTILITY DETAILS 8/21/2015
C700 EROSION CONTROL PLAN - OVERALL 8/21/2015
C711 INITIAL EROSION CONTROL PLAN - AREA 1 8/21/2015
C712 INITIAL EROSION CONTROL PLAN - AREA 2 8/21/2015
C713 INITIAL EROSION CONTROL PLAN - AREA 3 8/21/2015
C714 INITIAL EROSION CONTROL PLAN - AREA 4 8/21/2015
C715 INITIAL EROSION CONTROL PLAN - AREA 5 8/21/2015
C716 INITIAL EROSION CONTROL PLAN - AREA 6 8/21/2015
C717 INITIAL EROSION CONTROL PLAN - AREA 7 8/21/2015
C721 INTERMEDIATE EROSION CONTROL PLAN - AREA 1 8/21/2015
C722 INTERMEDIATE EROSION CONTROL PLAN - AREA 2 8/21/2015
C723 INTERMEDIATE EROSION CONTROL PLAN - AREA 3 8/21/2015
C724 INTERMEDIATE EROSION CONTROL PLAN - AREA 4 8/21/2015
C725 INTERMEDIATE EROSION CONTROL PLAN - AREA 5 8/21/2015
C726 INTERMEDIATE EROSION CONTROL PLAN - AREA 6 8/21/2015
C727 INTERMEDIATE EROSION CONTROL PLAN - AREA 7 8/21/2015
C731 FINAL EROSION CONTROL PLAN - AREA 1 8/21/2015
C732 FINAL EROSION CONTROL PLAN - AREA 2 8/21/2015
C733 FINAL EROSION CONTROL PLAN - AREA 3 8/21/2015
C734 FINAL EROSION CONTROL PLAN - AREA 4 8/21/2015
C735 FINAL EROSION CONTROL PLAN - AREA 5 8/21/2015
C736 FINAL EROSION CONTROL PLAN - AREA 6 8/21/2015
C737 FINAL EROSION CONTROL PLAN - AREA 7 8/21/2015
C740 EROSION CONTROL DETAILS 8/21/2015
C741 EROSION CONTROL DETAILS 8/21/2015
E001 ELECTRICAL LEGEND, ABBREVIATIONS, AND GENERAL NOTES 8/21/2015
E101 EXISTING AND DEMO ELECTRICAL PLAN - AREA 1 8/21/2015
E102 EXISTING AND DEMO ELECTRICAL PLAN - AREA 2 8/21/2015
E103 EXISTING AND DEMO ELECTRICAL PLAN - AREA 3 8/21/2015
E104 EXISTING AND DEMO ELECTRICAL PLAN - AREA 4 8/21/2015
E105 EXISTING AND DEMO ELECTRICAL PLAN - AREA 5 8/21/2015
E106 EXISTING AND DEMO ELECTRICAL PLAN - AREA 6 8/21/2015
E107 EXISTING AND DEMO ELECTRICAL PLAN - AREA 7 8/21/2015
E108 EXISTING AND DEMO ELECTRICAL PLAN - AREAS 8 8/21/2015
E201 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 1 8/21/2015
E202 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 2 8/21/2015
E203 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 3 8/21/2015
E204 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 4 8/21/2015
E205 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 5 8/21/2015
E206 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 6 8/21/2015
E207 ELECTRICAL LIGHTING LAYOUT PLAN - AREA 7 8/21/2015
E208 ELECTRICAL LIGHTING LAYOUT PLAN - AREAS 8 8/21/2015
E301 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 1 8/21/2015
E302 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 2 8/21/2015
E303 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 3 8/21/2015
E304 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 4 8/21/2015
E305 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 5 8/21/2015
E306 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 6 8/21/2015
E307 ELECTRICAL LIGHTING CIRCUITING PLAN - AREA 7 8/21/2015
E308 ELECTRICAL LIGHTING CIRCUITING PLAN - AREAS 8 8/21/2015
E401 AIRFIELD LIGHTING VAULT AND REGULATOR SCHEDULE 8/21/2015
E501 GROUNDING AND MISC. DISTRIBUTION DETAILS 8/21/2015
E502 PULLCAN AND HANDHOLE DETAILS 8/21/2015
E503 HANDHOLE DETAILS 8/21/2015
E504 HANDHOLE DETAILS 8/21/2015
E601 BASE CAN DETAILS 8/21/2015
E602 BASE CAN INSTALLATION/SETTING TOLERANCES 8/21/2015
E603 SUGGESTED INSTALLATION METHOD - FLEXIBLE PAVEMENT 8/21/2015
E604 BASE CAN DETAILS 8/21/2015
E605 BASE CAN DETAILS 8/21/2015
E606 LIGHTING FIXTURE DETAILS - TAXIWAY EDGE 8/21/2015
E607 SIGNAGE DETAILS 8/21/2015
E608 SIGNAGE SCHEDULE 8/21/2015
construction time of performance DATES (to be written in by contractor)
Ite m
Item Description
P re d e ce ss o r
Ite m
C a le n d a r d a ys fr o m p re d e ce ss o r ite m to s ta rt d a te
D u ra tio n ca le n d a r d a ys
(i n cl u d in g a ve ra g e a d ve rs e w e a th e r d a ys
D a ys fr o m
N T
P to
It e m C o m p le tio n
D a te
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
1 Notice To Proceed 2 Preparation & Submittals 1 0 90 90 3 Work Zone 1a 2 0 42 132 4 Work Zone 1 2 0 105 195 5 Work Zone 2b 4 0 5 200 6 Work Zone 2a 4 25 5 225 7 Work Zone 2 4 0 30 225 8 Work Zone 3a 7 0 5 230 9 Work Zone 3 7 0 30 255 10 Work Zone 4 9 0 30 285
C o n s tr u c ti o n
| _G001 |
| _G100 |
| _G200 |
| _G201 |
| _G202 |
| C001 |
| C101 |
| C102 |
| C103 |
| C104 |
| C105 |
| C106 |
| C107 |
| C201 |
| C202 |
| C203 |
| C204 |
| C205 |
| C206 |
| C207 |
File details come from the government source that posted it. Updated .