FA441816Hoist_Addendum_1_Question_and_Answers.docx

DOCX document 20 KB Posted

Attached to
FA441816HOIST Federal contract opportunity
Solicitation number
FA441816HOIST
Issued by
Department of the Air Force Air Mobility Command

About this file

SITE VISIT QUESTIONS AND ANSWERS

View the file

Other files for this federal contract opportunity

Other files attached to FA441816HOIST, newest first.
File Type Posted
PWS_Hoists_Cranes_and_Lifts_19_Aug_16_(REVISED).docx DOCX document
Attachment_1-Pricing_Worksheet_(22_July_2016).xls XLS spreadsheet
PWS_Hoists_Cranes_and_Lifts_71816_(REVIEWED).pdf PDF
Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum#1 Solicitation FA441816HOIST

Question and Answers 19 August 2016

The purpose of this addendum is as follows:

1. Provide answers to vendor questions:

2.

a. Question 1:

b.

c. We are looking at performing all load testtests in a one month period,toperiod, to keep cost down, within the first month of the contract, would that be possible to schedule?

Answer 1: Answer: No. Early load testing will invalidate current certifications and any previous visual inspections performed. It is the Government’s desire to have load tests conducted in conjunction with the scheduled Preventive Maintenance Inspections (PMI) where load tests may be required. It is preferred that the Contractor’s submitted schedule represent a more evenly balanced monthly workload for PMI and applicable load tests as well as meet any other scheduling requirements of the Performance Work Statement (PWS).

Question 2: When it comes time to load test the cranes will we also be load testing the above ground vehicleVehicle lifts too? Or are those exempt formfrom the load test?

Answer:Answer 2: There are no perdioical load testperiodic load tests requirements, those units are only load tested if there is a repair that would require a load test. Repairs are not included in the firm fixed price contract line item.

3. Change paragraph 1.1. to provide clarification on inspection schedule submittal requirement. The following has been inserted into paragraph 1.1.

The preventive maintenance shall be performed not later than 12 months and no earlier than 9 months of the last inspection. The government will provide a report illustrating the last inspection performed on each item identified in appendix B within 10 days of award.

4. Change paragraph 1.1. to allow the use of water weights with concurrence of the COR. The following has been inserted into paragraph 1.1.

All weight tests are preferred to be conducted using solid weights although use of water weights will be considered on a case by case basis with COR concurrence.