Questions_and_Answers.docx
DOCX document 13 KB Posted
- Attached to
- RAISED FLOORING SYSTEM W/CARPET Federal contract opportunity
- Solicitation number
- FA441719Q0232
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Statement_of_Work_Raised_Flooring_System_and_Carpet.docx | DOCX document | |
| FA441719Q0232_Raised_Flooring_System_w-Carpet.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Do you have a POC at AccessFloorSystems.com you can share with us?
Response: Yes, please see below.
Email: sales@accessfloorsystems.com Website: www.accessfloorsystems.com Contact: Luke Anton 985 898 0880
2. It is recommended that the carpet not be put on at the factory as the sealant used does not allow product longevity. It is recommended that the installer perform this onsite with a semi-permanent adhesive so it can be pulled up if you need access to the flooring system. Otherwise, the sealant will not allow this and anytime you need to pull something up you will have to replace the entire floor panel versus potentially just the carpet tile.
Response: We would like the permanent carpet tile and for it to be installed at the factory.
3. Do you have floor plans for the building?
Response: Yes, there is a floor plan available. Please contact the contract specialist directly to request a copy.