Questions and Answers.pdf
PDF 223 KB Posted
- Attached to
- FY22 CVIS Undercarriage Screeners
- Solicitation number
- FA440722Q0012
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 Performance Work Statement-Amended.pdf | ||
| RFQ GPE-Amended.docx | DOCX document | |
| RFQ GPE.docx | DOCX document | |
| Attachment 1 - Performance Work Statement.pdf | ||
| FY-19 NATIONAL DEFENSE AUTHORIZATION ACT (NDAA) SECTION 889 CERTIFICATION FORM Soliciation.pdf | ||
| SSJ-REDACTED_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. What is the distance from the scanning unit on the road to where the monitoring office is located, where the computer and monitor will be placed? The scanning unit will be in the building and the distance will be approx. 25 to 30 foot from the monitoring station.
2. Is there any power in the vicinity of where the unit will be located? Yes, CE came out earlier and established that there was power were it will be needed.
3. Are there any light poles nearby? Yes, outside of the building.
4. Are there wires for data that has to be pulled too from the unit to the pole where the ALPR and
Bosch camera will be installed? The cameras will be installed inside of the building, the installer will be able to make the proper pulls.
5. Will the base allow the roads to be dug for the placing pipes in, for protecting and pulling the wire through? Yes, CE has already signed off on doing the digging for the placement of the system. No roads will be affected, just inside of the building.
6. What kind of vehicles will be scanned - will commercial vehicle like 18 wheelers be scanned?
Yes, 18 wheelers, gas trucks, garbage trucks, ect...
7. Does the base have any engineering group who can do this work? The installer will do the install and CE will do the digging in order for the system to be put into place.
8. It has been established that the base Civil Engineer Squadron would perform all concrete work to accommodate the recessed mounting of the scanner unit and its conduit raceway below floor level at each location? Correct
9. That the work stations for the scanner units would be at the center of the building between the two inspection bays and all furniture/accommodation will be furnished and installed by the customer? Correct
10. The Bosch cameras will be viewable at the scanner work stations and the office area? Correct
11. The Bosch cameras specified are not PTZ cameras. Are fixed cameras acceptable? Yes, that is acceptable
12. There are only the need for two Bosch cameras for this project? Correct
13. Adequate power and communications network infrastructure is in place for this project? Correct
14. Will the revised PWS reflect these items? Yes