Text version
1. What floor will the top load washer, stackable dryers, and combos
Bldg 1830 (1st Floor) – 16 Top load washer, 8 Stackable Dryers (= 16 Dryers) Bldg 1820 (1st Floor) – 16 Top load washer, 8 Stackable Dryers (= 16 Dryers) Bldg 1850 (3 Floors) – 10 Stackable washer/dryer Combo on each floor (30 Total)
2. With this many units there will be a ton of cardboard to deal with, is there dumpsters available to dispose of all of it?
We can make sure a dumpster is available.
3. The old equipment that is being removed, will we have to remove it from the base?
Not being removed from base, but will need to be moved to another location on base.
4. What kind of access will we have to the dorms? Will we be able to work 10-14 hours to try and get the job done?
Typical Hours of Operation for our office is 0700-1600, but do to this project needing to be completed we can extend those hours not to exceed 12 hrs. being available.