A. Project Title: REPAIR (SUS) VARIOUS BUILDING SYSTEMS, COMM FAC; BUILDING 861, Scott AFB IL.
B. Proposals are due by 17 Aug 18 at 01:00 PM (CDT).
C. The Period of Performance w ill be the total number of days follow ing Notice to Proceed (NTP)> D. The project magnitude is betw een $5,000,000 and $10,000,000.
E. This solicitation is a total small business set-aside IAW FAR 19.502-2. NAICS code is 236220.
F. Notice to Offerors: Funds are not presently available for this project. No aw ard w ill be made under this solication until funds are available.
G. A pre-proposal conference/site visit w ill be held on 12 July 18 at 1:00 PM (CDT). All parties w ill meet at the 375th Contracting Squadron conference room in bldg 52, Scott AFB IL 62225.
H. The Government reserves the right to cancel this solicitation/RFP either before or after the RFP closing date.
JORGE ALVAREZ 618-256-6012
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
22-Jun-2018
(RFP)
(IFB)
X
CALL:
REPAIR (SUS) VARIOUS BUILDING SYSTEMS, COMM FAC; BUILDING 861
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________ Section L & M
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________17 Aug 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
375 CONS/PK
201 E WINTERS STREET BLDG 50
SCOTT AFB IL 62225-5015
FA4407
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
VDYD 15-1246
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
FA440718R0004 51
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA440718R0004
Section A - Solicitation/Contract Form
SOLICITATION POINTS OF CONTACT
Your attention is directed to Section L, Paragraph L-2, Proposal Preparation Instructions, and Section M – Evaluation Factors for Award. The Government may award a contract without discussions, based solely on initial offers received.
SOLICITATION POINTS OF CONTACT
Both individuals listed below are to be included in all correspondence regarding this solicitation:
SSgt Jorge Alvarez at jorge.alvarez.7@us.af.mil Mr. Jody Noram at jody.noram.1@us.af.mil
PRE-PROPOSAL CONFERENCE AND SITE VISIT
In accordance with FAR 52.236-27, a pre-proposal conference / site visit will be conducted at Scott AFB on 12 July 2018 at 1:00 PM CDT. The pre-proposal conference will feature a briefing of solicitation requirements to be followed by a project site visit. Prospective offerors desiring to attend are required to submit a request to attend to SSgt Jorge Alvarez AND Mr. Jody Noram no later than 9 July 2018 at 09:00 AM CDT.
Request for base entry must be received no later than 9 July 2018 at 09:00 AM CDT. Requests must include requestor’s full name (first,middle,last), date of birth, driver’s license number and state issued, as well as company name. To receive a base visitor’s pass for access to the base, personnel must possess form(s) of identification in accordance with Attachment 15, REAL ID Act Information, to this solicitation. Entry to Scott AFB is at the Main (Shiloh) Gate on Seibert Rd. Please allow extra time to obtain your pass. It is highly recommended that visitors arrive at the gate at least two hours prior to the scheduled site visit time. FAILURE TO SUBMIT YOUR
INFORMATION FOR BASE ACCESS BY THE DATE AND TIME INDICATED MAY RESULT IN
ACCESSS BEING DENIED.
Offerors must ensure all information required to access Scott AFB is submitted in a timely manner. Failure to adhere strictly to base access requirements may result in a denial of access to the base. Although all reasonable efforts will be made by the Contracting Office to ensure base access is granted to all potential offerors, the final determination regarding base access is within the sole and exclusive discretion of the USAF Security Forces, and access may be granted or denied at the USAF Security Forces sole and exclusive discretion. Offerors that do not attend or are otherwise denied base access are not relieved any obligations by virtue of being absent from the walkthrough.
SUBMISSION OF QUESTIONS / REQUESTS FOR INFORMATION (RFI)
Questions regarding this solicitation shall be submitted in writing to SSgt Jorge Alvarez AND Mr. Jody Noram. All questions must be received no later than close of business one week prior to the closing date of the solicitation in order to allow time for responses: 18 July 2018 at 3:00 PM local time.
SUBMISSION OF PROPOSALS
Offers shall ONLY be sent to SSgt Jorge Alvarez and Mr. Jody Noram. Any offer(s), proposal documentation, (in particular, cost information shared with persons outside of the USAF Contracting Squadron) could, at the sole and exclusive discretion of the Government Contracting Officer, result in an offer being deemed non-responsive and be excluded from further consideration.
This is an all-electronic solicitation release. Offerors are responsible for submitting proposals electronically by the date/time specified in Block 13 of the SF1442, and addressed only to the Government office designated in the solicitation. Proposals shall be submitted using the AMRDEC SAFE File Exchange Website at https://safe.amrdec.army.mil/safe.
Instructions for using AMRDEC may be found at https://safe.amrdec.army.mil/safe/Guide.aspx.
You must mark your AMRDEC submittal as FOUO – LIMITED DISTRIBUTION DOCUMENT (Under “Email Settings” select the radio button below the text “FOUO”, then click the dropdown box beneath the Radio Button and select “LIMITED DISTRIBUTION DOCUMENT”). Offerors shall only send proposals through AMRDEC to SSgt Jorge Alvarez at jorge.alvarez.7@us.af.mil and Mr. Jody Noram at jody.noram.1@us.af.mil).
NOTE: The method of completion for Representations and Certifications is at System for Award Management (SAM) at https://www.sam.gov/portal/SAM/.
If you are unable to use this method, contact SSgt Jorge Alvarez AND Mr. Jody Noram prior to the scheduled receipt of offers in Block 13 of SF1442. Failure to complete all required Representations and Certifications may render your proposal ineligible for award.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot
REPAIR VARIOUS BUILDING SYSTEMS, B861
FFP
Base Bid - The contractor shall perform all efforts needed to execute this project.
This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachments within Section J.
FOB: Destination
NET AMT
0002 1 Lot
TOTAL PROPOSED PRICE
FFP
Total proposed price to include base bid (CLIN 0001), plus Bid Option CLINS 1001, 1002, 1003, 1004, 1005 & 1006.
1001 1 Lot OPTION Bid Option One (Downspouts and Hangers)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 3, paragraph o., page 5 of 15.
1002 1 Lot OPTION Bid Option Two (Exterior Building)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 3, paragraphs p. & q., page 5 of 15.
1003 1 Lot OPTION Bid Option Three (Restrooms & Plumbing)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 3, paragraphs r. and s., page 6 of 15 as well as Section 4, paragraphs f., g., & h., pages 7 and 8 of 15.
1004 1 Lot OPTION Bid Option Four (Interior Lights)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 3, paragraph t., page 6 of 15.
1005 1 Lot OPTION Bid Option Five (Wing B2 and D2 Work)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 4, paragraphs i., j., and k, page 8 of 15.
1006 1 Lot OPTION Bid Option Six (Termite Treatment)
FFP
The contractor shall perform all efforts needed to execute this bid option. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform repair of various building systems within building 861 as per Attachment 1 - Statement of Work (8 Aug 18), Section 4, paragraph l., page 8 of 15.
1007 1 Square
Foot
OPTION Square Foot Electrical Work Above Drywal
FFP
The contractor shall perform all efforts needed to execute the work described within Attachment 21 - RFI # 159. The contractor will provide a square foot cost to replace. Once construction has started the contractor will provide total amount of work in square feet. This includes, without limitation providing, all plant, labor, materials, equipment, transportation, and supervision necessary to perform the work.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 1001 Destination Government Destination Government 1002 Destination Government Destination Government 1003 Destination Government Destination Government 1004 Destination Government Destination Government 1005 Destination Government Destination Government 1006 Destination Government Destination Government 1007 N/A N/A N/A Government
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
1001 N/A N/A N/A N/A
1002 N/A N/A N/A N/A
1003 N/A N/A N/A N/A
1004 N/A N/A N/A N/A
1005 N/A N/A N/A N/A
1006 N/A N/A N/A N/A
1007 N/A N/A N/A N/A
CLAUSES INCORPORATED BY REFERENCE
52.211-10 Commencement, Prosecution, and Completion of Work APR 1984
Section G - Contract Administration Data
Section G - Contract Administration Data
1.1 ADMINISTRATIVE MATTERS
Mailing address and telephone number for the 375th Contracting Squadron Construction Flight:
375th Contracting Squadron/PKA 201 E. Winters St., Bldg 52 Scott AFB IL 62225-5015
(618) 256-9323
1.2 CONTRACTOR’S CONTRACT ADMINISTRATION
To Be Completed By The Contractor:
Name and Title: _____________________________________________________________
Responsible Office: __________________________________________________________
Address: ___________________________________________________________________
Telephone Number: __________________________________________________________
Email: _____________________________________________________________________
Cage Code: _________________________________________________________________
Duns Number: _______________________________________________________________
Tax Identification Number: _____________________________________________________
1.3 INDIVIDUAL(S) AUTHORIZED TO NEGOTIATE OR DISCUSS PROPOSAL
Name of Primary: _____________________ Name of Alternate: _______________________
Address: ____________________________ Address: _______________________________
Telephone #: _________________________ Telephone #: ____________________________
Alternate #: __________________________ Alternate #: _____________________________
Email: ______________________________ Email: __________________________________
1.4 BONDING CAPACITY
Name of Surety:_______________________________________________________________
Address of Surety: _____________________________________________________________
Bonding Capacity (Per Project): $________________________ Bonding Capacity (Aggregate): $________________________ Bonding Capacity (Remaining): $________________________
252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7004 DOD Progress Payment Rates OCT 2014
CLAUSES INCORPORATED BY FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Invoice 2-in-1
(Contracting Officer: Insert applicable document type(s). Note: If a “Combo” document type is identified but not supportable by the Contractor's business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
DESTINATION
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC F87700 Issue By DoDAAC FA4407 Admin DoDAAC FA4407 Inspect By DoDAAC N/A Ship To Code N/A Ship From Code N/A Mark For Code N/A Service Approver (DoDAAC) N/A Service Acceptor (DoDAAC) F3S356
(Invoices to be submitted in WAWF under this DoDAAC) Accept at Other DoDAAC N/A LPO DoDAAC N/A DCAA Auditor DoDAAC N/A Other DoDAAC(s) N/A (*Contracting Officer: Insert applicable DoDAAC information or “See schedule” if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
WAWF Acceptor: Jody.noram.1@us.af.mil Buyer/Contract Administrator: jorge.alvarez.7@us.af.mil Contracting Officer: rodney.brown.10@us.af.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
WAWF Acceptor: jody.noram.1@us.af.mil Buyer/Contract Administrator: jorge.alvarez.7@us.af.mil Contracting Officer: rodney.brown.10@us.af.mil
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
(End of clause)
Section H - Special Contract Requirements
SPECIAL CONTRACT REQUIREMENTS
1.0 Required Insurance (IAW FAR 28.306(b))
Reference FAR clause 52.228-5 -- Insurance -- Work on a Government Installation, "the contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
(a) Workmen's Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
(b) General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
(c) Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
(d) The Certificate of Insurance shall provide for thirty (30) days written notice to the contracting officer by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned “Insurance” clause.
1.1 Subcontracting Responsibilities
The contractor shall be responsible for the management and performance of all subcontractors. The contractor shall ensure that all work elements are completed within the stated requirements.
1.2 Performance And Payment Bonds
Contractor shall furnish Performance and Payment Bonds (Standard Form 25/25A) from authorized sureties only;
the list can be obtained at http://fms.treas.gov/c570/c570_a-z.html#i. A notice to proceed shall not be issued and no work shall begin until good and sufficient surety has been received and accepted by the contracting officer.
Contractors shall refer to 52.228-13 Alternative Payment Protections and 52-228-15 Performance and Payment Bonds – Construction for further guidance.
1.3 Proposal Guarantee (BID BOND)
Individual proposal guarantees (bid bonds) of at least 20% of the proposed price may be required from all offerors competing for award.
1.6 Installation Rules And Regulations
The rules and regulations of the installation where services are performed shall apply to the contractor and his employees while on the premises of such installation. These regulations included but are not limited to: presenting valid identification for base entrances, state registration and covered insurance for contractor-owned and/or privately owned vehicles, obeying all posted directives, and providing strict adherence to security police direction in instances where security police have been dispatched to a particular location.
1.7 Utility Services (IAW FAR 36.514)
The contractor will be required to participate in Air Force energy and water conservation programs. Utility services are normally furnished to the contractor at no cost; however, see contract clause titled FAR 52.236-14, “Availability and Use of Utility Services.” All connections are the responsibility of the contractor. At construction sites where utilities are not available, the contractor is responsible for furnishing temporary utilities (portable generators, etc.).
1.8 Designation Of Government Inspector
The Base Civil Engineer or his authorized representative is designated as the representative of the contracting officer for the purpose of performing construction contract quality assurance for the government, which includes performing technical surveillance, monitoring workmanship, verifying compliance with plans and specifications, and tracking progress. This provision in no way authorizes anyone other than the contracting officer to commit the government to changes in the terms of this contract.
1.9 Contractor Consent To Background Checks
The contractor and, as applicable, subcontractor shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well being or operational mission of the installation and its population, nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified by Law Enforcement Agency Data System (LEADS) through the National Crime Information Center. LEADS checks will verify if a person is wanted by local, state, and federal agencies. All contractor and subcontractor personnel must consent to LEADS background checks. Contractor and subcontractor personnel who do not consent to an LEADS check will be denied access to the installation.
Information required to conduct an LEADS check includes: full name, driver’s license number, and/or social security number, date of birth of the person entering the installation, and completion of a background check questionnaire. The contractor shall provide this information using the Scott AFB Form 21, Contractors Consent for Background Check, and shall submit it in conjunction with the contractor’s request for either base or vehicle passes.
Completion of a successful LEADS check does not invalidate the requirement for an escort when contractor or subcontractor personnel are working within controlled or restricted areas.
Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Persons later found to be undocumented or illegal aliens will be remanded to the proper authorities. The contractor shall not be entitled to any compensation for delays or expenses associated with complying with the provisions of this clause. Furthermore, nothing in this clause shall excuse the contractor from proceeding with the contract as required.
1.10 Contractor Registration of Vehicles on Scott AFB
All contractor or contractor employees’ vehicles used for the performance of this contract shall comply with all local, state and federal regulations. Additionally any pass shall be surrendered to Security Forces upon demand to positively identify a person’s need to be on Scott AFB.
1.11 Access to Installation During Force Protection Conditions (FPCONs) Contractors will be assigned a mission essential designation IAW requirements contained in SAFBI 31- 101/Installation Security Instruction. Only the installation commander or the unit commander requesting contract support will assign the mission essential designation.
1.12 Property Protection
Property protection for facility where the contractors’ primary work center is located will be the responsibility of the local facility manager and local Government Security Manager, or their duly authorized representative IAW AFI 31- 401, Security Program Management and command/local directives. The contractor shall safeguard all government-owned equipment and materials in his/her possession or use.
1.13 Safeguarding Classified or Unclassified Information
The contractor shall meet Air Force standards for storing, processing, and handling classified information and systems. Additionally, all resources (e.g. maps, publication/instructions, photos) provided by the government to assist the contractor in the performance of their contract will be surrendered upon termination of employment or the end of the contract performance period.
1.14 Non-Disclosure Agreements
To safeguard information, the contractor shall enter into non-disclosure agreements with the responsible local security manager.
1.15 Privacy Act
Work on this project requires that personnel may have access to Privacy Information. Personnel shall adhere to the Privacy Act, Title 5 of the U.S. Code, Section 552a and applicable agency rules and regulations.
1.16 Base Passes
In accordance with (IAW) FAR 52.232-5(e) and AFFARS 5352.242-9000, all issued base passes shall be returned upon contract completion to the Contracting Officer. Questions regarding payment and base pass collection may be directed to the Contract Specialist. Failure to comply with incorporated clauses, as well as local policy pass collection procedures, may result in withholding of final payment.
1.17 Contractors Working in Controlled or Restricted Areas
The unit requesting contract support will provide escort (s) for contractors’ at all times when within a controlled area. Contractors shall not escort other contractor employees within controlled or restricted areas. In addition, contractors shall fulfill, maintain, and comply with all security requirements IAW AFI 31-401, Security Program Management, and command/local directives.
1.18 Contractors Responsibilities while Working within Controlled or Restricted Areas Only contractor personnel with proper authority and qualifications shall enter a controlled or restricted area. Certain facilities require the issuance of an AF Form 1199. The government, at any time, may revoke the AF Form 1199.
Contractors shall not escort other contractor employees within controlled or restricted areas. In addition, contractors shall fulfill, maintain, and comply with all security requirements contained in AFI 31-401, Security Program Management.
1.19 Access To Government Facilities with Controlled or Restricted Areas The contractor shall comply with security regulations imposed by the installation commander and/or the agency responsible for the project location. Due to specific mission requirements inherent in the nature of controlled or restricted areas on Scott AFB, the government may direct the contractor to leave the controlled or restricted areas at any given time.
1.20 Access To Government Facilities with Controlled or Restricted Areas for Replacement Contractors The unit requesting contract support will continuously escort replacement contractors, not initially possessing the proper clearances and requiring entry to controlled or restricted areas. Replacement contractors shall submit paperwork within 30 days of being assigned to obtain an approved security clearance or favorable review.
Replacement contractor personnel shall obtain a security clearance prior to working with, or having direct access to, classified material. In addition, replacement contractor personnel shall obtain a “Favorable review” prior to having access to a Controlled Area. The above information shall be submitted to 375 SFS/SFA.
1.21 Green Procurement Program (GPP)
Green Procurement is a federal acquisition policy that promotes preferred purchasing of environmentally sound products and services that have a reduced effect on human health and the environment. In order to comply with the affirmative procurement requirements of Section 6007 of the Resource Conservation and Recovery Act (RCRA) and Executive Orders 13101 and 13148 (Green Procurement Program (GPP)), the Contractor shall use recycled and recovered materials and products identified in the USEPA's Comprehensive Procurement Guidelines (CPG).
1. The latest CPG product list, and the specific recycled-content requirements for each product, can be found on the USEPA’s website (www.epa.gov/cpg).
2. The Contractor shall provide EPA-designated products containing recovered material unless the item cannot be acquired:
a. Competitively within a reasonable time frame.
b. Meeting the appropriate performance standards.
c. At a reasonable price.
3. Items identified in the USEPA's CPG shall be viewed as the minimum that can be considered when evaluating recycled/reused materials. Other materials and products not listed, but commonly used in industry outside of the government, shall also be considered.
4. Material and product submittals for all recycled-content items shall list the recycled and recovered materials used and the percentage content listed.
5. Additional program elements include:
a. Energy Star products and energy-efficient standby power devices
b. Bio-based products as defined by USDA
c. Non-ozone-depleting substances
d. EPA priority chemicals
Section I - Contract Clauses
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
APR 2014
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
JUL 2013
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research APR 2011 52.211-13 Time Extensions SEP 2000 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications
AUG 2011
52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-21 Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data -- Modifications
OCT 2010
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns NOV 2016 52.219-14 Limitations On Subcontracting JAN 2017 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-11 Ozone-Depleting Substances and High Global Warming
Potential Hydrofluorocarbons.
JUN 2016
52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners.
JUN 2016
52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.223-19 Compliance with Environmental Management Systems MAY 2011 52.223-20 Aerosols JUN 2016 52.223-21 Foams JUN 2016 52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-21 Required Use of American Iron, Steel, and Manufactured
Goods--Buy American Statute--Construction Materials
MAY 2014
52.225-22 Notice of Required Use of American Iron, Steel, and Manufactured Goods--Buy American Statute--Construction Materials
MAY 2014
52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-1 Alt I Disputes (May 2014) - Alternate I DEC 1991 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items NOV 2017 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012
52.249-2 Alt I Termination for Convenience of the Government (Fixed- Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.203-7004 Display of Hotline Posters OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.216-7009 Allowability of Legal Costs Incurred in Connection With a Whistleblower Proceeding
SEP 2013
252.217-7028 Over And Above Work DEC 1991 252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements DEC 2010 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7048 Export-Controlled Items JUN 2013 252.227-7022 Government Rights (Unlimited) MAR 1979 252.227-7023 Drawings and Other Data to become Property of Government MAR 1979 252.227-7033 Rights in Shop Drawings APR 1966 252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7006 Cost Limitation JAN 1997 252.236-7008 Contract Prices-Bidding Schedules DEC 1991 252.242-7006 Accounting System Administration FEB 2012 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for
Military Operations
OCT 2010
252.247-7023 Transportation of Supplies by Sea APR 2014
52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $520.55 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
14.7% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Scott AFB, IL 62225.
(End of provision)
52.222-35…