FA440718R00040006 - Amendment 6
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VDYD 15-1246
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
A. Incorporate the revised version of Attachment 21 - RFI Log 27 July 2018.
B. Incorporate Attachment 27 - B861 CAD to Section J.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Jul-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA440718R0004
X 9B. DATED (SEE ITEM 11)
22-Jun-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Jul-2018
CODE
375 CONS/PK
201 E WINTERS STREET BLDG 50
SCOTT AFB IL 62225-5015
FA4407 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA440718R0004
SECTION
SF 30
BLOCK
CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
LIST OF ATTACHMENTS
LIST OF ATTACHMENTS
(End of Summary of Changes)
Attachment Title Date Pages 1 Statement of Work 18-Jul-18 12 2 B861 Phasing Plan 17-Jul-18 7 3 B861 100% Specification 25-Apr-17 540 4 B861 100% Drawings 25-Apr-17 45 5 B861 100% Design Analysis 25-Apr-17 292 6 B861 Fire System Drawings 21-Mar-18 4 7 Site Utility Plan 30-July-04 1 8 Termite Treatment Report 23-Feb-18 44 9 Schedule of Materials Submittals 17-May-18 23
10 B861 Glass Door 17-May-18 1 11 TEKLAB Sample Results-B861 29-May-18 7 12 AFCEC D Wing Renovation 17-May-18 1 13 AFAA Furniture 17-May-18 1 14 Wage Determination IL 17 180017 11-May-18 14 15 Required Electrical On Equipment Inventory Sheet 15-Mar-17 1 16 Required HVAC on Equipment Inventory Sheet Jun 18 1 17 Real ID Act Feb-18 3 18 Past Performance Information 29-May-18 2 19 Past Performance Questionnaire 29-May-18 4 20 RFP Checklist 29-May-18 1 21 RFI Log B861 26-Jul-18 16 22 Preproposal Conference Slides 12-Jul-18 14 23 Preproposal Conference Sign In Sheet 12-Jul-18 5 24 Post Investigation Report 23-Jan-18 16 25 Additional Site Visit Sign in Sheet 18-Jul-18 1 26 S-File Room Designation 25-Jul-18 1 27 B861 CAD 25-Apr-17 Multiple
File details come from the government source that posted it.