This Statement of Work (SOW) details Architect-Engineer (A/E) services for renovating Building 1056 at Maxwell Air Force Base. The project requires comprehensive design work including renovation of the facility, with specific tasks such as repairing/replacing roof ventilators, exterior doors, wall exhaust, roof insulation, interior painting, modifying floor space for 908 MSG functions, upgrading HVAC systems (AHUs, VAV, heating and domestic boilers), replacing flooring and lighting, and main panel lugs. The A/E contractor must complete the entire design within 220 days from Notice to Proceed, with mandatory design milestone submissions at 65%, 95%, and Ready-to-Advertise (RTA) stages.
Key technical requirements include delivering design documents in specific formats (AutoCAD 2024, half-scale drawings, electronic and printed specifications), using Master Format 2018 for specifications, providing Level 5 cost estimates, and adhering to multiple industry standards and codes including ASHRAE, International Building Code, and UFC requirements. Deliverables must be submitted to 42CES/CEN at Maxwell AFB, with multiple printed and electronic copies required at each design stage. The project emphasizes compliance with federal accessibility, safety, and design standards, and includes a separately biddable Comprehensive Interior Design package.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Appendix A revised Mar 2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A/E-SOW
STATEMENT OF WORK
ARCHITECT-ENGINEER SERVICES FOR
PNQS 20-1056 Renovate, Building 1056 Maxwell AFB
WO# 18148 & 21493
1.0 INTRODUCTION
Maxwell AFB 42CES/CEN has a requirement for a contractor to provide Architectural-Engineering services for requirement for a Subcontractor to provide Architectural-Engineering services for:
PNQS 20-1056 Renovate, Building 1056 Maxwell AFB
The Service provider (Architect/Engineer) will perform all design work necessary to accomplish the work indicated herein and in accordance with Appendix A, Performance Requirements for
Architect-Engineering Services, except as modified herein. Provide all plant, labor, equipment and materials required to complete the project and deliver to Maxwell AFB complete project documents, including but not limited to: construction drawings, specifications, design analyses, cost estimates, construction submittal register, drawing list, specification list, bid schedules, product and material technical data sheets, and working sketches. For 65% drawing and specification submittals, the A-E shall deliver two sets of bound half-size drawings and one set of bound specifications along with drawings and specifications in electronic format stored on CD. For 100% drawings and specifications submittals, the A-E shall deliver three sets of bound half-size drawings and three sets of bound specifications along with drawings and specifications in electronic format stored on CD.
All RTA final construction drawings shall be delivered as three sets of bound half-size copies and in electronic format stored on CD. All Mechanical Drawings shall be stamped by the Mechanical
Engineer. Drawings shall be delivered in a useable electronic format as an AutoCAD “.dwg” file, 2007 or greater. All RTA final specifications shall be delivered three sets bound and in electronic format in both MSWord 2010 (.docx) and Adobe PDF format stored on CD. Design analyses shall be delivered in two bound sets at all junctures of the project time frame. Cost estimate and submittal register shall be delivered in two bound sets and in electronic format stored on CD with the all submittals.
1.1 All work is to be performed in accordance with this SOW (Statement of Work).
1.3 Consultants. The A-E will be required to have as an integral part of the firm, or shall be able to obtain the services of, registered professional engineers and registered Architects established in various disciplines to support the subject project. The use of consultants will be determined by the
A-E with all coordination, control, payment and scheduling responsibilities belonging to the A-E.
The A-E shall make the consultants aware of the scope of the work and shall be responsible for the accomplishment of the work in accordance with all related standards, regulations, instructions, directions, and adopted codes that are pertinent to Maxwell AFB, AL and as described under 3.0 herein.
Cost Estimates:
All cost estimates will be a ‘LEVEL 5’ cost estimate as defined by the Whole Building Design
Guide. UFC 3-740-05 Construction Cost Estimating https://www.wbdg.org/dod/ufc/ufc-
3-740-05
The purpose of this level of estimate is to develop probable costs in the preparation and submittal of bids for contract. This will be provided with 65%, 95%, and RTA submittal.
Include a complete and thorough "Scope of Estimate" statement that would state clearly such https://www.wbdg.org/dod/ufc/ufc-3-740-05 https://www.wbdg.org/dod/ufc/ufc-3-740-05 items assumptions, allowances, documents used for the estimate, and contingency amounts included.
Specifications:
All specifications will be in the format of Master Format 2018.
Specifications will be in line with the specifications at the Whole Building Design Guide website. https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs
2.0 ACRONYMS/DEFINITIONS:
A-E = Architect/ Engineer
ASHRAE = American Society of Heating, Refrigerating and Air Conditioning Engineers
COE = Corps of Engineers
DDC = Direct Digital Control
NTP = Notice to Proceed
SMACNA = Sheet Metal and Air Conditioning Contractors National Association
SOW = Statement of Work
VFD = Variable Frequency Drive
3.0 APPLICABLE SPECIFICATIONS/STANDARDS/RELATED STUDIES:
3.1 Applicable Publications, Laws and Regulations, and Instructions, ETC.:
3.1.2 Latest Edition of the following Codes & References
a. ASHRAE Std 62
b. ASHRAE Std 90.1
c. SMACNA Duct Construction Standards
d. American with Disabilities Act and Architectural Barriers Accessibility Guidelines
e. National Fire Protection Association Codes and Standards.
f. National Fire Protection Association 101, Life Safety Code
g. International Building Code
h. International Mechanical Code
i. International Fuel Gas Code
j. International Plumbing Code
k. ASHRAE Handbook of Fundamentals; Handbook of HVAC Systems and Equipment;
Handbook of HVAC Applications; and Handbook of Refrigeration
l. National Electric Code
m. UFC, DOD Minimum Antiterrorism Standards for Buildings, UFC 4-010-01
4.0 TASK DESCRIPTION
4.1 Background Information & Location –
Building 1056 is located on Maxwell AFB and the address is 401 West Maxwell Blvd and part of the 908AW.
4.2 Description of Services: This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs applicable constraints on the project and the refinement of the intent as indicated in the
SOW are the responsibility of the A/E.
The A/E is to design for but not limited to:
Renovate the facility and include:
Repair/replace roof ventilator and wall exhaust. Repair/replace roof insulation.
Repair/replace exterior doors. Prep and paint interior doors, ceiling, and walls.
Modify first floor space for 908 MSG functions, correct age and wear related deficiencies.
This work should include, AHUs, VAV, heating and domestic boilers upgrade controls and repair devices or LON issues.
Prepare the HVAC portion so it will be able to separate from the overall renovation package if necessary.
Replace flooring. Replace main panel lugs. Replace lighting.
Comply with applicable UFCs and building codes.
This design will also include a design for furniture package that will include a separately biddable Comprehensive Interior Design package.
STANDARD PROJECT REQUIREMENTS
*ALL FORMS AND SOW MUST BE INCLUDED IN BID PACKAGE AND WILL BE
FURNISHED BY SANDRA BREDLOW IN CE
1. General Requirements
2. AF Form 66
3. Spec Section 1305 Submittal Procedures
4. AF Form IMT 3000
5. Contractor's HAZMAT Questionnaire Form.
6. Contractor's Environmental Reporting Entry Form
7. Recycling and Landfill Report
8. T-1 Title Sheet (revised)
9. Updated Signature Block Drawing
10. Cost Estimate Form
4.3 This description of services provides the A/E with a basis to develop the design intent as proposed. The SOW is not intended to be a complete and concise description of all the details required in the work effort. The determination of all applicable constraints on the project and the refinement of the intent as indicated in the SOW are the responsibility of the A/E.
4.4 Performance of Work
4.4.1 Performance Period. Complete design shall be completed within 220 days from NTP.
The definition of complete work shall mean that all design stages have been accomplished, all reviews required herein have been completed, all comments made by the user, 42CES/CEN are incorporated into the construction documents, and all documents are ready for advertisement and the bidding process.
4.4.2 Schedules: The A-E shall provide a schedule that indicates the start of the performance period, the review milestones, and the completion date. If the contract is modified to adjust the completion date the A-E shall submit a revised schedule to the contract administrator within one day of the signed modification to the original delivery order clearly indicating the original performance period and the new completion date.
4.4.3 Submittal Milestones. The A-E shall submit the following design documents and supporting elements for the subject project in the following sequence. Note that all time elements are in reference to the date the purchase order is received by the A-E, which hereafter shall be referred to as NTP (Notice to Proceed):
A. 15% Design Charrette---------------------------------------------------- N/A
B. 65% Design Documentation-------------------------------------------120 Days after NTP
C. 95% Design Documentation-------------------------------------------190 Days after NTP
D. RTA Design Documentation------------------------------------------220 Days after NTP
4.4.4 The design documents submitted by the A-E will be reviewed by various agencies located on Maxwell AFB to verify that Air Force requirements are reflected in the design.
The A-E shall be held responsible for ALL requirements particular to the project being designed. 42CES/CEN shall only act as a regulatory body specifically there to provide the
A-E with direction on relevant regulations, standards, codes, and public laws that impact the subject project. The A-E shall determine how all of these elements guide and control the resultant design.
4.5 Review Process.
4.5.2 Upon completion of the 65% milestone the A-E shall submit the design package in the quantities indicated to the agencies listed in paragraph 5.1. Drawings shall be half-scale.
The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period timeline indicated in paragraph 4.4.3.
4.5.3 Upon completion of the 95% milestone the A-E shall submit the design package in the quantities indicated to the agencies listed in paragraph 5.1. Drawings shall be half-scale.
The review process shall take 10 working days after receipt of the package and will generate written documents stating 42CES/CEN / user’s observations, questions and comments. The review time indicated is concurrent with the performance period time line indicated in paragraph 4.4.3.
4.5.4 Upon completion of the RTA milestone, the A-E shall submit the design package in the quantities indicated to the agencies listed in paragraph 5.1. Drawings shall be half-scale.
The original specifications, drawing list, specification list, and Submittal Register shall be printed on one side of each page. All drawings, including CAD files, specifications and cost estimate shall be provided to on compact disks. The CD shall be labeled with project name, no., submittal phase, date and A/E name. The Construction Cost Estimate and Annotated
Comments shall be submitted in separate bound copies with Title Cover Sheets.
4.5.5 Note: The A-E shall attach a letter to each RTA design level addressee above that indicates the project number and name, the using organization, the project location, and state that all comments be forwarded to 42CES at the address indicated in #1 on the list within 5 working days from the date on the A-E’s letter.
4.5.6 Specifications. A sample format will be given to the A-E. There shall be no reference to the “owner”, “Architect”, “Engineer” etc. in specifications. The only entity authorized to obligate government funds and negotiate with a contractor is the Contracting Officer shall be used in place of all references to an individual, except where the term “Contractor” is used.
4.5.7 Specification References. Provide in both MS-word (.docx) and PDF format (PDF at
RTA only). All references to industry standards such as ASTM, ANSI, Fed Spec, etc. shall be dated. Only references specifically applicable to the subject project shall be included in the specifications.
4.5.8 Warranty & Guaranties. All items that carry a warranty longer than the one-year warranty provided for in the Federal Acquisition Regulations shall be covered by a warranty paragraph in the specifications that reflects the extended warranty period.
4.5.9 Proprietary References. Federal projects are required to provide open competition for all products that serve the intended function and fulfill the performance requirements stated in the construction documents. The A-E shall provide performance specifications whenever possible and use reference specifications when necessary. If the work requires the use of proprietary specifications the A-E shall provide a Sole Source justification letter that explains why a particular product is the only one that can perform the intended function.
When reference specifications are used provide the name and address of the manufacturer used as a basis for the design. Qualify the use of a single manufacture name by stating, “any reference to a specific manufacture is intended to set minimum standards, configuration, and appearance, and not to restrict competition of equal or better manufacturers and products.
The A-E shall provide a cut sheet from the manufacture that describes all the salient features of the product being specified.
4.7 Asbestos. The A-E shall not specify asbestos containing materials in the work. In those instances that removal of asbestos containing materials is required a comprehensive specification meeting the requirements and conditions of the federal government will be required. A sample specification will be given to the A-E.
4.8 Drawing Notes. A sample title sheet will be given to the A-E. Ensure that the following is on the title sheet:
“ALL DRAWINGS ARE DIAGRAMMATIC AND ARE INTENDED TO QUANTIFY THE
MATERIALS SPECIFIED AND INDICATE THEIR INTENDED RELATIONSHIP TO EACH
OTHER. THE DRAWINGS ARE NOT TO BE SCALED. THE VARIOUS SCALES USED ON THE
DRAWINGS MAY NOT ALLOW FOR ALL FITTINGS, OFFSETS, AND ACCESSORIES THAT MAY
BE REQUIRED TO COMPLETE THE WORK. THE CONTRACTOR SHALL CAREFULLY
INVESTIGATE THE CONDITIONS THAT WOULD AFFECT THE WORK TO BE PERFORMED
AND SHALL ARRANGE SUCH WORK AS NECESSARY TO COMPLY WITH THE INTENT OF
THE CONSTRUCTION DOCUMENTS.”
4.9 Designs In Inch-Pound. This requires the use of inch-pound measurements in criteria, design, and specification documents for facility projects. When dual units are needed present International
System of Units (SI) designations first, followed by the inch-pound (IP) designation in parenthesis.
4.10 Provided Materials. 42CES will provide hard copies of the subject building listed above from archive drawing files and other drawings selected by the A-E. The archive files are located in the
Civil Engineering administrative building, 400 Cannon Street. The A/E will be required to retrieve all necessary drawings from the archives vault & reproduce them on site. 42CES will also provide blank electronic copies of a submittal register (AF Form 66), a cost estimate (AF Form 3053), Tri-
Services drawing format, title sheet, sample specification format, sample specifications for General
Requirements, Schedule of Proposal Items, Submittal Procedures, and Recycled / Recovered
Materials.
4.11 Drawing Data
a. Drawing sheet size to be 11”x 17” with (Tri-Services Standards border)
b. Drawings shall be AUTOCAD 2024 or higher
c. Pen settings shall be (Tri-Services Standards line weights/colors).
In addition to other title block information, the following data shall be on each drawing sheet: (As appropriate)
Project Number: PNQS 20-1056
Project Title: RENOVATE BLDG 1056, MAXWELL AFB, AL
5.0 DELIVERABLES:
5.1 Submittal Requirements. All submittals shall be hand delivered or express mailed to the following office:
Receiving Office Percentage of
Design
Quantity of Doc. Sets
42CES/CEN
400 Cannon Street
(Bldg 1060)
Maxwell AFB, AL 36112-6523
Attn: Frank Manning
65%
95%
RTA
2 printed spec originals &
2 set printed plans and 1 pdf file
2 printed spec originals &
2 set printed plans and 1 pdf file
1 CD includes spec originals & set plans, also
CAD files, et al.
2 printed copies of spec originals & 2 printed set plans