LAUGHLINAIRFORCEBASE
DIVISION01SPECIFICATIONS
FORCONSTRUCTIONPROJECTS
LAUGHLINAIRFORCEBASE

PROJECT: REPAIR AFFF POND

DATE: 02‐16‐18

Table of Contents

Section 01‐1 Summary of Work & General Requirments

Section 01‐2 Deliverables

Section 01‐3 Project Schedules

Section 01‐4 Work In Controlled Areas

Section 01‐5 Project Safety Requirements

Section 01‐6 Contractor Quality Control

Section 01‐7 Temporary Construction Facilities and Controls

Section 01‐8 Environmental Protection

Section 01‐9 Closeout Procedures

Section 01‐1 SUMMARY OF WORK

1‐1 PROJECTDESCRIPTION
Providealldocuments,labor,materials,equipment,andoversighttorepairtheRetentionPondfor
building508atLaughlinAFB(LAFB),Texas.
ThescopeoftheprojectshallincludetheinstallationofanewlinertocatchAFFFfromthe
dischargepointinthepond.Thisprojectwillrequirebutisnotlimitedtodemolitionofexisting
concretefootings,chainlinkfencing,andremovalofplantgrowth.
1‐2 REGULATORYREQUIREMENTS
a. TheprojectshallconformtoallapplicableFederal,Stateandlocallaws,regulationsand
base‐specificstandardsandapplicableUnifiedFacilitiesCriteria(UFC).Wherethereisa
conflictbetweenthereferencedstandards,themoststringentshalltakeprecedence.All
workaccomplishedbytheContractorshallcomplywiththesecriteriaunlessawaiveris
obtainedfromtheLaughlinAFBwhenconditionswarrantsuchconsideration.
b. TheContractorshallensurethatonlyqualified,competentpersonnelcarryoutthetasks
outlinedinthisSOW.Competentisdefinedasaregisteredprofessionalor,where
registrationisnotapplicable,trainedand/orcertifiedintherespectivefield.
1‐3 WARRANTYREQUIREMENTS
a. TheGeneralContractorprovidesallwarrantiesrequiredinthespecificationsforthis

project.

1‐4 PRE‐CONSTRUCTIONCONFERENCES
Priortocommencingdesignorconstructionwork,theContractorshallmeetwiththeContracting
Officerandotherdesignatedtechnicalpersonnelatamutuallyagreeabletimetodiscussand
developmutualunderstandingsconcerningthedesignandconstructionprogressscheduleandthe
administrationofwork.
1‐5 WORKINGHOURS
a. TheContractor'sworkinghoursshallbebetween0730and1630,withnoworkexpectedon
weekendsandFederalholidays.Permissiontoworkattimesotherthanthosestatedabove
mustbeobtainedfromtheContractingOfficeratleastthreeworkingdaysinadvance.As
permissionmaynotalwaysbegranted,theContractor’sscheduleshouldneverrelyon
accomplishingworkattimesotherthanthosestatedabove.
b. Noworkwillbeallowedduringquiettimesforspecialevents.Graduationceremonies
typicallyoccuronceeverythreeweeksandrequirequiettimesfrom1600to2000on
ThursdayandFridayeveningsaswellas0900to1000onFridaymorning.Timesmayvary.
Unplannedeventsmayoccurduringthelifeoftheproject.CoordinatewiththeContracting
Officerforspecificdatesandtimesastheprojectprogresses.
c. Forthoseactivitieswhenworkisprohibited,theContractorshallhaveallequipmentand
materialsremovedand/orshallorganizematerialsandequipmentonthesiteasdirectedby
theContractingOfficer.TheContractorshallhavetheareascleaned.
d. Thesecurityfenceinstallationcontractorpersonnelshallpresentaneatappearanceandbe
easilyrecognized.Thismaybeaccomplishedbywearingdistinctiveclothingbearingthe
nameofthecompanyorbywearingappropriatebadges,whichcontainthecompanyand
employee’sname.Contractor’spersonnelshallberesponsibleforwearingappropriate
personalprotectionequipment(PPE)inandaroundtheairfield.TheContractorassumes
responsibilityfortheactionsofalltheiremployees,subcontractors,andsupplierswhenon
LaughlinAFB.
e. NormalworkhoursareMondaythroughFridayfrom7:30A.M.to4:30P.M.exceptdays
observedasfederalholidaysaslistedbelow:
NewYear’sDay1January
MartinLutherKing’sBirthdayThirdMondayinJanuary
President’sDayThirdMondayinFebruary
MemorialDayLastMondayinMay
IndependenceDay4July
LaborDayFirstMondayinSeptember
ColumbusDaySecondMondayinOctober
VeteransDay11November
ThanksgivingDayFourthThursdayinNovember
ChristmasDay25December
HolidaysfallingonSaturdayareobservedontheprecedingFriday.Holidaysfallingon
SundayareobservedonthesucceedingMonday.TheContractormayrequesttoworkona
weekend,afterhours,oronaholiday.Allsuchrequestsmustbesubmittedinwritingto
LaughlinAFBwithadescriptionofthetypeofworktobeaccomplishedonthatdate.Any
requesttoworkaweekendshallbesubmittedbycloseofbusinessonthepriorWednesday.
Requeststoworkotherthanweekendsshallbesubmittedaminimumof36hourspriorto
therequesteddate.LaughlinAFBreservestherighttoapproveordenytherequest.
1‐6 INSPECTIONOFWORK
a. 47CES/CENMPisdesignatedastheofficeresponsibleforinspectingthework,whilethe

Contracting Officer is responsible for final acceptance of the work.

b. The47CES/CENMPshallbegiventheopportunity,duringregularbusinesshours,to
inspectanyconstructionaspectthatwillbeburiedorhidden(e.g.,utilities,mechanical
systems,electricalwiring).TheContractorshallcontacttheContractingOfficeratleast1
dayinadvanceofenclosing,encasing,burying,etc.,toarrangeforinspection.Ifthe
ContractorisunabletocontacttheContractingOfficertheyshouldcontactthe47
CES/CENMPforassistance.

1‐7 SUPERVISION OF WORK

a. ThesitesuperintendentorapprovedalternateandQualityControlManager(QC)or
approvedalternateshallbeonthejobsiteanytimeworkisbeingaccomplished.THEQC
ANDSUPERINTENDENTMUSTBOTHBEONSITEDURINGWORK.
b. Thequalificationsofthesuperintendent,QC,andalternatesshallbeapprovedbythe
ContractingOfficerpriortoassumingtheirresponsibilitiesandshallincludeaminimumof
fiveyears’experienceonsimilarprojects.Qualificationsshallbesubmittedtothe
ContractingOfficerinresumeformatpriortothestartofconstruction.
c. Theon‐sitesuperintendentshallbereachablebytelephoneatalltimeswhenworkisbeing
accomplished.TheContractor’ssuperintendentorcontractmanagershallbereachableby
telephone24hoursaday,sevendaysaweek,forthedurationofthecontract.
1‐8 SURVEYANDVERIFICATIONOFEXISTINGCONDITIONS
TheContractorshallperformallsurveyingnecessarytocompletetheworkandshallbesolely
responsibleforverificationandvalidationofexistingconditions,coordinationofexistingconditions
inparallelwithproposedrequirements,andabove‐andbelow‐gradeconditionassessment.Useof
existingconditiondataprovidedbytheAirForcedoesnotrelievetheContractorofliability.
1‐9 PROTECTIONOFEXISTINGWORK
a. Atthecompletionoftheproject,existingworkshallbeinaconditionequaltoorbetterthan

the condition that existed before new work started.

b. TheContractorshallremoveoralterexistingworkinsuchamannerastopreventdamage
toanyportionsoftheexistingworkwhichremain.Repairorreplaceportionsofexisting
workwhichhavebeenalteredduringconstructionoperationstomatchexistingor
adjoiningwork,asapprovedbytheContractingOfficer.
c. TheContractorshallinvestigatetheadequacyofexistingroadsandtheirallowableload
limitandshallrepairanydamagetoexistingroadscausedbyconstructionoperationsatno
additionalcosttotheGovernment.
d. Vehiculartrafficonconcretewalkwaypavementshallberestrictedtoequipmentwith
pneumatictires.
e. Allworkthatmustcrossexistingroadsshallbeaccomplishedbyboring,ratherthan
trenching.Trenchingmaybeapprovedinspecialcircumstances,buttheContractorshall
notexpectthisorrelyonitunlessspecifiedinthecontractdocuments.

1‐10 BASE ACCESS AND SECURITY

1‐10.1 CRIMINALBACKGROUNDINVESTIGATIONCHECK
a. Allcontractors/subcontractorsseekingtoenterLaughlinAFB(LAFB)foremploymentmust
submittoacriminalhistorybackgroundcheckpriorenteringLAFB.Areleaseformand
spreadsheettemplatewillbeprovidedandmustbecompletelyfilledout.Individualswill
filloutonereleaseformperpersonandtheContractorshallcompileallcopiesandprovide
themwithacompletedspreadsheetto47SFS/S5throughtheContractingOfficer.
Contractorpersonnelconvictedofthefollowingcrimes(butnotlimitedto)willnotbe
allowedtoworkonLAFB:espionage,sabotage,treasonorterrorism;felonyconvictions;
violentcrimesagainstpersons;sexcrimes;drugcrimesrelatedtodistributionorintentto
distribute;orfirearms/explosivesviolations.Othergroundsforexclusionforworkingon
LAFBinclude,butarenotlimitedto:unabletoprovideproofofU.S.citizenship,outstanding
warrants,individualsidentifiedonFederalterroristwatchlists,andincarcerationfor12
monthsorlongerwithinthepastthreeyears.Deviationsfromthisguidelinearepermitted
onacasebycasebasisasdeterminedby47SFS/CCand/orthe47FTW/CC.Anyrelease
form/spreadsheetnotcorrectlyfilledoutwillbeconsideredincompleteandthatcontractor
employeewillnotbegrantedaccessontoLAFB.
b. Backgroundchecksmaytakeupto4weekstoprocessandwillbeconsideredvalidfora
periodof12monthsforcontractorswithoutabreakinserviceworkingonLAFBduringthat
time.However,ifthereisabreakinservice(workonbase)forlongerthan6months,the
Contractorwillhavetoresubmittoacriminalbackgroundcheck.
c. Allcontractor/subcontractorpersonnelobtainingasatisfactorycriminalhistory
backgroundcheckmustobtainalong(24hrs‐2yrs)orshortterm(lessthan24hrs)AF
Form75orcontractorbadgetoentertheinstallation.TheContractormustprovideavalid
USGovernmentissuedidentification.Identificationmusthaveperson’spictureattimeof
obtainingAFForm75and/orcontractorbadge.Ifthecontractor/subcontractoris
requestingavehiclepasshe/shemustprovideavaliddriverslicense,vehicleregistration
andinsurancemeetingtheminimumTexasliabilitycoverage.Contractor/subcontractor
willreportalllost,stolenormissingAFForm75sand/orcontractorbadgesto47SFS
immediatelyupondiscovery.AllAFForm75and/orcontractorbadgeswillbeturnedinat
thecompletionofstatedcontract,terminationofemployee,debarmentfrombase,released
fromcontract,and/orGovernmentterminatescontract.Failuretofollowstatedprocedures
maypreventcontractor/subcontractorfromfurtherqualifyingforbaseaccess.
d. Short‐noticepassesmaybeconsideredonacase‐by‐casebasisandaresubjecttoapproval
bytheContractingOfficerwithcoordinationof47SFS/S5and47FTW/ATOpersonnel.
Contractorsareexpectedtodoadvanceplanningtothemaximumextentpracticableto
minimizeshortnoticepassrequests.
e. TheretentionpondrepairareaiswithinadesignatedLaughlinAFBcontrolledarea.
Therefore,thecontractor’sworkareawillbedesignateda“FreeZone”.Freezonesare
establishedwithincontrolledareaswhenprojectsand/orsimilaractivitiesmakeit
inappropriateorimpracticaltoapplynormalcirculationcontrols.TheAirForceestablishes
suchfreezonecorridorstopermitaccessofcontractorpersonnelandequipmenttoproject
siteslocatedwithincontrolledareas.Uponawardofthecontract,appropriateactionswill
beinitiatedtoobtaintherequiredapprovalsforthisdesignation.Contractorsupervisory
representativeswillberequiredtoattendapre‐constructionmeetingpriortomobilization,
whereapplicableFreeZonerequirementsandlocalbaseaccessprocedureswillbe

discussed.

f. Atthecloseofeachworkperiod,facilities,equipmentandmaterialsshallbesecured.Ifany
governmentpropertyisprovidedthecontractorshallberesponsibleforsafeguardingsaid

property.

1‐10.2 BASEPOLICIES
a. Allpersonsenteringthebasemustpresentvalididentificationatbaseentrances.
b. Whileoperatinganyvehicleonbase,alldriversmusthaveintheirpossessionavalid
driver'slicense,validvehicleregistration,andproofofvehicleinsurance.Ifavehicleis
registeredtosomeoneotherthantheoperator,theoperatormustprovideanotarizedletter
fromtheregisteredowner,authorizingtheoperatorpermissiontooperatethevehicle.
c. Accesstothebasemaysometimesbedelayedby60minutesormoreduetosecurity
precautions,includingthecheckingofvehicleoccupants'IDs,vehiclemanifests,andthe
searchingofallvehicles.Longerwaittimesmayoccurintheeventofanemergency.
d. Contractors,subcontractors,andallpersonnelwhoreportforworkanddonotknowthe
locationofthejobsitewillbeheldatthemaingatetoawaitescortservicefromthe
constructionsuperintendentorotherdesignatedrepresentative.
e. Basespeedlimitsarestrictlyenforcedwiththeuseofradarequipment.Thebasespeed
limitis5mphinservicedrivesandparkinglots,15mphinhousingareas,20mphon
BarnesStreet,and30mpheverywhereelse,unlessotherwiseposted.
f. Motorcycleoperators/ridersmustwearprotectiveheadgear(helmets),gloves,goggles,
closetoedshoes,longpants,andareflectivebeltorvestatalltimeswhileridingonbase.
g. Mandatoryseatbeltlawsareineffectonbaseandpersonnelarenotpermittedtorideinthe
bedsoftrucks.Seatbeltsmustbefastenedpriortoenteringthebase.
h. Noprivatelyownedweaponsorcontraband(drugs,etc.)arepermittedonanymilitary
installation,atanytime.ViolatorswillbeprosecutedthroughtheFederalMagistrates
Court.Camerasaretobeusedforconstructiondocumentationonly.Anyphotographsthat
needtobetakenrelativetotheconstructionsitemustbecoordinatedwiththeContracting

Officer.

i. LaughlinAirForceBaseisconsideredtobeaclosedfacility.Nounauthorizedtoursor
visitorswillbeallowedontheinstallation.
j. Cellphoneusagewhiledrivingonbaseisnotpermitted,unlesscommunicationtodeviceis
“handsfree”.
k. ContractorsandpersonnelshallobeyallposteddirectivesandadheretoSecurityForces
directionandinstructions.

l. Failure to comply with base policies may result in loss of driving privileges or debarment.

1‐11 OUTAGESANDCLOSURES
a. Anyutilityandcommunicationsoutagesnecessitatedbytheworkshallberequestedin
writingatleast14calendardayspriortotheproposedoutage.Therequestshallbe
directedtotheContractingOfficerandshallstipulatethespecificutilitysystem(s)tobe
affectedandtheproposeddurationfortheoutage.Primaryelectricaloutagesincluding
thosethatrequirepowertobeshutoffatthetransformermustberequested,inwriting,21
calendardaysinadvance,noexceptions.
b. Ifutilitiesareconsideredmainutilities(watermains,overheadelectrical,etc.),thenthe
ContractingOfficermustprovidethisshutdown,butallotherutilitiesshouldbede‐
energizedordisconnectedbytheContractor.TheContractorwillprovidethenecessary
lock‐outtagdevicestoensureutilitieswillnotbeenergizedorturnedon.TheContractor
shallcoordinatelockout/tagoutwiththeContractingOfficer.
c. Allstreetandparkinglotclosuresnecessitatedbytheworkshallberequestedinwritingat
least14calendardayspriortotheproposedclosure.TheContractorshallcomplywiththe
recommendationscontainedinPart6oftheU.S.DepartmentofTransportation,Federal
HighwayAdministration'sManualonUniformTrafficControlDevicesandTxDOT’s
StandardSpecificationsforConstructionandMaintenanceofHighways,Streets,andBridges
toensureproperwarningtomotorists.Adequatetrafficcontroldevicesshallbeprovided
bytheContractor.TheContractorshallsubmitacompletetrafficcontrolplanforapproval
bythebase.Workcannotbeginuntilthetrafficcontrolplanisapproved.
d. Allbaseaccessgateclosuresnecessitatedbytheworkshallberequestedinwritingatleast
45calendardayspriortotheproposedclosure.
1‐12 PRIVATIZEDELECTRICALINFRASTRUCTURE
a. OnLaughlinAFB,allprimaryelectricalinfrastructureincludinglines,poles,and
transformersareownedbyRioGrandeElectricCooperative,Inc.(RGEC).Secondary
electricalinfrastructuresuchaselectricallinesandpanelsinsideofbuildingsareownedby
LaughlinAFB.
b. AnyworkdoneonexistingprimaryelectricalinfrastructureshallbecompletedbyRGEC.
Thisincludesconnectionstothetransformerontheprimaryside,butnotconnectionsto
thetransformeronthesecondaryside.Theprimecontractorshallsubcontractallworkon
existingprimaryelectricalinfrastructuretoRGEC.
c. AnyworkdonetoconstructnewprimaryelectricalinfrastructuremustconformtheRGEC
specificationsandwiththeexceptionofmakingtheconnectiontothedistributionsystem,
canbecompletedbytheprimecontractor,subcontractedtoRGEC,orsubcontractedtoa
differentcontractor.IfRGECdoesnotcompletetheworkthemselves,theyhavetherightto
inspecttheworkcompletedpriortotakingownership.Theprimecontractorshall
coordinatethisinspectionwithRGECandpayallinspectionfeesrequired.Thecontractor
willberequiredtore‐doanyworkthatdoesnotmeetRGEC’sspecificationsatnoadditional
costtotheGovernment.Theprimecontractorshallsubcontractanyworktoconnecttothe
distributionsystemtoRGEC.
1‐13 SALVAGEMATERIALANDEQUIPMENT
Equipmentandmaterials(i.e.,signs)removedduringconstructionshallbesalvaged(asapplicable)
andinstalledattheiroriginallocationoratthenewlocationasneededoridentifiedbythe
ContractingOfficerpriortoacceptanceofthework.
ItemsdesignatedtobesalvagedtotheGovernmentshallbemovedtoandstoredatlocationsonthe
basedesignatedbytheContractingOfficer.
1‐14BID
Thiscontractwillbeawardedasalumpsum.
1‐14.1LUMPSUMBASEDPAYMENTITEMS
a. LumpSumPaymentItemsconsistofmobilizationanddemobilization.Theseitemsshall
constitutefullcompensationforperformingallworkrequiredforwhichaseparatepayment
isnototherwiseprovided.
b. TheMobilizationitemshallinclude,butnotbelimitedto,mobilizationofpersonnel,
equipment,andmaterialstotheworksite,andothercontractexpensespriortothe
beginningofconstructionwork.
c. TheDemobilizationitemshallconsistofallworknecessarytocleartheworksiteandreturn
equipmentofalltypestotheContractor’soffsitefacility.Requiredsiteclean‐upand
restorationshallbeincludedinthisitem.

d. This project will require 2 written Notices to Proceed (NTP) from the Contracting Officer:

(1) NTP#1willbeissuedformaterialsubmittals.ThePeriodofPerformanceforthis
workshallbe60calendardays.
(2) NTP#2willbeissuedforConstruction.ThePeriodofPerformanceforthiswork
shallbe60calendardays.
e. TheGovernmentreservestherighttonotissuetheNoticetoProceedforconstructionuntil
thefullperiodofperformanceforsubmittalsandorderandreceiptofmaterialshas
completelyexpired.TheNoticetoProceedforanyphaseofconstructionwillnotbeissued
untilthepreviousphaseiscompleteandaFinalInspectionhasoccurred.
f. AScheduleofMaterialSubmittalsisprovided.Allsubmittalsshallbesubmittedaccordingto
thesubmittalscheduleandallpreconstructionsubmittalsshallbeapprovedwithinthe
periodofperformanceforsubmittalsandorderandreceiptofmaterials.Ifallsubmittals
arenotapprovedwithinthespecifiedtimeframe,liquidateddamagesmaybeassessed.

1‐15 REQUIRED USE OF HIGH EFFICIENCY EXTERIOR LIGHTING

InresponsetoPresidentialMemorandum,theAirForcehasmandated,whereeconomicallyviable,
theuseofHighEfficiencyLighting(HEL)forallmajorrenovationsandnewconstructionofparking
lots,roadways,andotherfacilitiesrequiringexteriorlighting.HELincludesinductionandlight‐
emittingdiodes(LED).
1‐16 AETCSMOKINGPOLICY
ContractorsareadvisedthattheCommanderhasplacedrestrictionsonthesmokingoftobacco
productsinAETCfacilities.AFI40‐102,TobaccoUseintheAirForce,anditsAETCSupplement1,
outlinestheproceduresusedbytheCommandertocontrolsmokinginourfacilities.Contractor
employeesaresubjecttothesamerestrictionsasgovernmentpersonnel.Smokingispermitted
onlyindesignatedsmokingareas.
1‐17 WORKBYTHEGOVERNMENT
ThegovernmentreservestherighttoundertakeperformancebyGovernmentforcesorother
contractors,thesametypeorsimilarworkascontractedforherein,asGovernmentdeems
necessaryordesirable,andtodosowillnotbreachorotherwiseviolatethiscontract.
1‐18 TEXASSALESTAXEXEMPTIONNOTIFICATION
ToallowallcontractorsthemaximumadvantageoftheexemptionprovisionsofTexasSalesand
UseTaxLaws,contractorsmayclaimexemptionfromtaxwhenpurchasingtangiblepersonal
propertythatwillbeincorporatedintorealtyfortheU.S.Government.Questionsregardingthe
properapplicationoftheStateTaxLawsshouldbeaddressedtotheStateComptroller’soffice.
1‐19 SUBCONTRACTORRESPONSIBILITIES
TheContractorwillberesponsibleforthemanagementandperformanceofallsubcontractors.The
Contractorshallensurecontractsarecompletedwithinthestatedrequirements.Theprime
Contractorisresponsibleforsubcontractorcompliancewithallrulesandregulations.
1‐20 SPECIALUTILITYPROVISION
TheContractorwillberesponsibleforanyandalldamagestoaccuratelymarkedutilitiesresulting
fromitsoperationsandsubcontractors.Further,thecontractorshallbeheldliableforallcosts
associatedwithsuchdamage.Suchcostsincludenotonlythecosttoproperlyrepairthedamaged
utility,butanydirectcostsincurredbythegovernmenttoprovideemergencyresponsetothesite,
aswellasforanymonetarylosses.Suchlossmayalsoincludethevalueoflossofproductivity
experiencedbythegovernmentduetolossofpowerand/orfacilityevacuationarisingfromthe
utilitydamage.
1‐21 NOTIFICATIONREQUIREMENTSWHENCHANGINGKEYPERSONNEL
Personnelinkeypositionsareconsideredessentialtotheperformanceofanyworkunderthis
contract.Examplesofkeypositionsincludeprojectmanager,superintendents,andqualitycontrol
inspectors.Thecontractoragreesthatapartialbasisofawardofthiscontractwillbethekey
personnelproposed.Accordingly,thecontractoragreestoassignunderthecontractthosekey
personnelwhosecredentials,experienceandexpertisewereprovidedwiththeproposalandwhich
meetthequalificationsnecessarytofulfilltherequirementsofthecontract.
Contractorshallprovidealistingofkeypersonnel.Thislistingofkeypersonnelmaybeamended
fromtimetotimeduringthecourseofthecontracttoeitheraddordeletepersonnel,as
appropriate.Priortodivertinganykeypersonneltootherprograms/projects,thecontractorshall
notifytheCOatleastfourteen(14)calendardaysinadvanceoftheproposeddiversion.The
governmentreservestherighttorejectproposedchangesinkeypersonnel.Suchnotificationsshall
include:(1)anexplanationofthecircumstancesnecessitatingthesubstitution,(2)acomplete
résuméoftheproposedsubstituteand(3)anyotherinformationneededbytheCOtoenable
him/hertodeterminethatthecontractorismaintainingthesamequalityofpersonnelasthose
includedatthetimeofaward.

1‐22 DRAWINGS

Alldrawings,ifapplicable,accompanyingtheRequestforProposalwillbeconsideredtobeapartof
theStatementofWork(SOW)orStatementofObjectives(SOO).AllAs‐builtsubmissionswillbe
addressedontheScheduleofMaterialSubmittals.
1‐23 PROPOSALPREPARATIONCOSTS
ThecostsforpreparationofcontractproposalsshallbetheresponsibilityoftheContractorandnot
directlyreimbursable.TheContractorshallfurnishallprojectmanagement,planning,estimating,
labor,transportation,materials,equipment,tools,supervision,designifapplicable,andallother
associatedcostsnecessarytofulfilltherequirementsofthecontract..
1‐24 SAFETYASSURANCE
a.PostawardSafetyMeeting:RepresentativesofthecontractorshallmeetwiththeContracting
Officerandhis/herrepresentative(s)priortothestartofrepair,alterationorconstructionactivities
forthepurposeofreviewingthecontractor'ssafetyandhealthprogramsanddiscussing
implementationofallsafetyandhealthprovisionspertinenttotheworktobeperformedunderthe
contract.Thecontractorshallbepreparedtodiscuss,indetail,themeasureshe/sheintendstotake
inordertocontrolanyunsafeorunhealthyconditionsassociatedwiththeworktobeperformed
underthecontract.Thismeetingmaybeheldinconjunctionwiththepre‐constructionconference,
ifsodirectedbytheContractingOfficer.Theconductofthismeetingisnotcontingentupona
generalpre‐constructionmeeting.Thelevelofdetailforthesafetymeetingisdependentuponthe
natureoftheworkandthepotentialinherenthazards.Thecontractor'sprincipalonsite
representative(s),thegeneralsuperintendent,andhis/hersafetyrepresentative(s)shallattendthis

meeting.

b.ContractorResponsibility:Thecontractorshallassumefullresponsibilityandliabilityfor
compliancewiththeapplicableregulationspertainingtothehealthandsafetyofpersonnelduring
theexecutionofworkandshallholdtheGovernmentharmlessforanyactiononhispartorthatof
hisemployeesorsubcontractorswhichresultsinillness,injuryordeath.
c.Inspections,Tests,andReports:Theinspections,testsandreportsmadebythecontractor,
subcontractors,speciallytrainedtechnicians,equipmentmanufacturers,andothersasrequiredby
aCLIN,shallbefurnishedinaccordancewiththetermsofthecontract.Areportshallconsistofthe
resultsoflabtests.
d.MaterialsandEquipment:Specialfacilities,devices,equipment,clothing,andsimilaritemsused
bythecontractorintheexecutionofworkshallcomplywiththeapplicableregulations.
e.HazardousMaterials:ThecontractorshallbringtotheattentionoftheContractingOfficerany
previouslyunknownmaterialsuspectedofbeinghazardouswhichheencountersduringexecution
ofthework.AdeterminationwillbemadebytheContractingOfficerastowhetherthecontractor
shallperformteststodetermineifthematerialishazardous.IftheContractingOfficerdirectsthe
contractortoperformtests,and/orifthematerialisfoundhazardousandadditionalprotective
measuresareneeded,acontractchangemayberequired,subjecttoequitableadjustmentunderthe
termsofthecontract.
1‐25 REMOVALANDREPLACEMENTRESPONSIBILITY
TheContractorshallberesponsibleforthereplacementorrepairofallexistingfinishedsurfaces,
utilities,equipment,landscapes,grounds,andstructuresorpartsthereofthathe/shehasdamaged,
removed,orcutintoinordertoperformworkspecified.
1‐26 GOVERNMENNTLIABILITY
TheGovernmentwillnotbeliableforanylossordamagetothecontractor’sproperty,including
stock,orforexpensesincidentaltosuchlossordamage.
1‐27 POWEROUTAGES
AllutilityoutageswillbecoordinatedwiththeusingagencythroughtheContractingOfficerorhis
representative.ThecontractorwillprovidenoticetotheContractingofficer,inwriting,notless
than12calendardayspriortotherequiredoutage.Allworkshallbecoordinatedandarrangedto
insuretheoutagewillbeofminimumduration.Intheeventascheduledpoweroutageiscancelled
bytheGovernment,notificationshallbegiventothecontractoratleast48hoursinadvanceofthe
timefortheoutagetostartandthecontractorwaiveshisrighttoanyclaimforequitable
adjustmentorincreasedcostofperformanceunderthiscontractasaresultofthiscancellation.
Onceautilityoutageisarrangedandworkhasbegun,workmustgoonuntiltheaffectedutilities
arerestoredtotheaffectedfacility.
1‐28 CONTRACTORPARKING
Contractorvehiclesandequipmentwillbeparkedinadesignatedarea.Thecontractorshallbe
responsibleformaintainingsecurityforcontractorandGovernment‐ownedequipment/vehiclesas
wellasformaterialsstoredbythecontractor.Thecontractorwillnotbepermittedtoparkorrun
vehiclesongrassareas.Onlyequipmentrequiredindirectperformanceoftheworkwillbe
permittedtoentergrassareas.Anydamagedonetolawnsorshrubswillberepairedorreplaced
bythecontractoratnoadditionalcosttotheGovernment.Atcertainfacilities/locationson
LaughlinAFB,thecontractormayberequiredtoloadoroff‐loadmaterialandequipmentandpark

elsewhere.

1‐29 TRANSPORTATION OF CONSTRUCTION EQUIPMENT

Thecontractorshallnotdriveanyconstructionequipmentwithmetalwheelsortracks(i.e.roller,
excavatoretc.)onthestreetsofLaughlinAFB.Allsuchequipmentshallbeloadedonatrailerand
hauledtothelocation.
1‐30 UNAUTHORIZEDRECONNAISSANCE
TheContractorshallinformallpersonnelworkingunderhis/herjurisdiction(including
subcontractorandvisitingsupplierpersonnel)thataccesstoareasoutsideoftheimmediatework
area(excludingauthorizedeatingestablishmentsandrestroomsneartheworksite,directhauland
accessroutes,Contracting,CivilEngineering,andSecurityForcesbuildings,andpointsofsupply
andstorage)areprohibited.Circulationofsaidpersonnelwillbelimitedtoofficialbusinessonly.
Personsengagedinunauthorizedreconnaissanceofothercontractor'sorGovernmentactivitywill
bereferredtotheContractingOfficerfordisposition.

Section 01‐2 DELIVERABLES

2‐1 SUBMITTALS

2‐1.1 GENERAL

a. Contracting Officer’s approval is required for all submittals.

b. The Contractor shall make submittals as required by the specifications and submittal register.

c. IncludedinthissolicitationisaScheduleofMaterialSubmittals.Theregisterisnotall
inclusiveandsubmittalsonadditionalitemsmayberequestedbytheContractingOfficer.
d. TheContractorshallprovidesubmittalsaccordingtothetimelinespecifiedontheSchedule
ofMaterialSubmittals.
e. TheContractorshallensurethatnoworkbeginsormaterial/equipmentisacquireduntil
submittalsforthatworkoritemhavebeenapproved,excepttotheextentthataportionof
workmustbeaccomplishedasbasisofasubmittal.
f. TheContractorshallcompleteworkwhichmustbeaccomplishedasbasisofasubmittalin
timetoallowsubmittalstooccurasscheduled.
g. TheContractor’sQualityControl(QC)Managershallberesponsibleforreviewingand
certifyingallsubmittalsareincompliancewithcontractrequirements.TheContractorshall
transmitsubmittalstotheQCManagertopreventdelaysinthework.
h. Eachsubmittalshallbecompleteandinsufficientdetailtoallowreadydeterminationof
compliancewithcontractrequirementsforeachdefinablefeatureofwork.Componentsof
definablefeaturesinterrelatedasasystemshallbesubmittedatsametime.Allofthe
varioustypesofsubmittalsrequiredtoevaluateaparticularsystem,item,ormaterialshall
besubmittedatthesametime,includingguarantees(whenapplicable).Whenacceptability
ofasubmittalisdependentonconditions,items,ormaterialsincludedinseparate
subsequentsubmittals,submittalwillbereturnedwithoutreview.

i. The Contractor shall be prepared to discuss submittal status during Partnering Meetings.

j. Submittals not requested may not be recognized or processed.

k. Unitsofweightsandmeasuresusedonallsubmittalsshallbethesameasthoseusedinthe
contractdrawings.
2‐1.2 SUBMITTALPROCESS
a. TheContractorshalltransmitdigitalcopiesrequiredforeachtypeofsubmittalasdescribed
inSubmittalDescription(SD)FormatandQuantityandfurnishadditionalcopiesof
submittalswhenrequestedbyContractingOfficer.
b. AsignedAFIMT3000shallbeincludedwitheachpaperanddigitalcopysubmitted.The
digitalcopymustincludeasignedAFIMT3000withinthesamePDFDocumentasthe
submittalitself.

c. Paper and digital copies of the same submittal shall be exactly identical.

d. Unlessotherwisespecified,allpapercopiesshallbeprovidedon81/2by11inchpaper.
TheContractorshallbindtogetherindividualpagesandindicatebyprominentnotationthe
contractnumber,projectnumber(MXDP‐‐‐‐‐‐),submittalnumber,specificationnumber,
andparagraphnumbertowhichitpertains.
e. TheContractorshallsubmitpaperanddigitalcopiessuchthatinformationmaterialis
clearlyidentifiableandlegible.Whenrequiredforfullunderstandingofthesubmittal,color
PDFsandpapercopieswillberequired.Submittalsthatarenotclear,identifiable,and
legiblewillbedisapproved.
f. Digitalcopiescanbee‐mailedtotheContractingOfficer,butthesubmittalwillnotbe
consideredreceiveduntiltherequiredcopiesaredeliveredtoeachparty.
g. TheContractorshallassigneachAFIMT3000asequentialSubmissionNumber.When
required,revisedsubmittalsshallbemarkedwiththeoriginalnumberandsequential
alphabeticsuffix(e.g.,13A).
h. TheContractorshallcompleteallheaderinformation,specificationsectionnumberand
paragraph,andacompletedescriptionofinformationprovidedontheregister.Eachitem
listedontheformwillfollowthenumberingsequenceanddescriptionprovidedperthe
materialregister.Forexample,thematerialregisterstates“ConcreteMix”withalineitem
as#20.TheContractorwillplace“#20”intheitemnumbercolumnwith“ConcreteMix”
underdescriptioncolumnoftheAFIMT3000.Contractoristoensurethatthe
manufacturer’spartnumber/modelnumberneededtobeincludedinthe"Descriptionof
Material".TheContractorwilldeterminethesubmissionnumberonthisform,butshould
followinsequence.
i. TheQCManagershallsigntheAFIMT3000certifyingthesubmissionhasbeenreviewed
andisinaccordancewithcontractrequirements.

j. The Contractor shall identify any and all variations from contract requirements.

k. TheContractorshallbringanylimitationsofproductsorsystemswhichmaybedetrimental
tosuccessfulperformanceofthecompletedworktotheattentionoftheContractingOfficer.

l. The Contracting Officer shall be allowed 14 days for review of submittals.

m. Paper copies of submittals will not be returned to the Contractor.

n. TheContractorshallcorrectandresubmitdisapprovedsubmittalswithin7daysofthe
disapprovaldate.Whenrevisedforresubmission,changesmadesinceprevious
submissionsshallbeidentified.
o. TheContractorshallupdatetheScheduleofMaterialSubmittals,completingthesubmittal
number,datesubmittedtocontracting,datedisapprovedandresubmitted(ifapplicable),
anddateoffinalapprovalasactionsoccur.
p. TheContractorshallretainacopyofapprovedsubmittals(includingContractor’scopyof
approvedsamples)attheprojectsitethroughoutthelifeoftheproject.
2‐1.3 CONSTRUCTIONSUBMITTALS
Constructionsubmittalsshallincludeitemssuchas:Contractor's,manufacturer's,orfabricator's
drawings;descriptiveliteratureincluding(butnotlimitedto)catalogcuts,diagrams,operating
chartsorcurves;testreports;testcylinders;samples;O&Mmanuals(includingpartslists);
certifications;warranties;andothersuchrequiredsubmittals.

2‐1.3.1 Variations

a. Variations from contract requirements require Contracting Officer and will be considered where advantageous to Government.

b. DiscussionwiththeContractingOfficerpriortosubmissionwillhelpensurefunctionaland
qualityrequirementsaremetandminimizerejectionsandresubmittals.When
contemplatingavariationwhichresultsinlowercost,considersubmissionofthevariation
asaValueEngineeringChangeProposal(VECP).
c. Foranyproposedvariations,theContractorshallprovidealetteroncompanyletterhead
statingthefollowinginformation:
(1) Howboththefunctionalandqualityrequirementsmeetorexceedtheminimum
requirementsofthecontractand/orspecificdeliveryorder.
(2) Describethenatureandfeaturesofthevariationandwhythevariationisdesirable
andbeneficialtoGovernment.Includeanestimateofthecostsavings,ifapplicable.
Includethesubmittalsrequiredfortheitem.Clearlyindicatethevariationon
submittalpages.
(3) AssurancefromtheContractorand/ormanufacturer,asapplicable,thatthe
variationwillbecompatiblewithotherelementsofthework.

(4) Any additional information requested by the Contracting Officer.

d. Anadditional14calendardayswillbeadded,foratotalof21calendardaysforGovernment
reviewofsubmittalswithvariations.
2‐1.3.2 ApprovalandDisapproval
a. ApprovedsubmittalsauthorizetheContractortoproceedwiththeworkcovered.The
Contractorshallreviewthesubmittalfor,andcomplywith,anyconditionsorother
informationindicatedon,orattachedto,theapprovedsubmittal.Approvalofaseparate
material,product,orcomponentdoesnotimplyapprovalofanassemblyinwhichitem

functions.

b. TheContractingOfficer'sapprovalofsubmittalsshallnotbeconstruedasacompletecheck,
butwillindicateonlythatthegeneralmethodofconstruction,materials,detailingandother
informationappeartomeettheSolicitationandAcceptedProposal.Approvalwillnot
relievetheContractoroftheresponsibilityforanyerrorwhichmayexist,astheContractor
isresponsibleforthesatisfactoryconstructionofallwork.Aftersubmittalshavebeen
approvedbytheContractingOfficer,noresubmittalforthepurposeofsubstituting
materialsorequipmentwillbeconsideredunlessaccompaniedbyanexplanationofwhya
substitutionisnecessary.
c. Disapprovedsubmittalsindicatesubmittalisincompleteordoesnotcomplywithdesign
conceptorrequirementsofthecontractdocumentsandshallberesubmittedwith
appropriatechanges.Noworkshallproceedforthisitemuntilresubmittalisapproved.If
theContractorconsidersanycorrectionindicatedonthesubmittalstoconstituteachange
tothecontract,anoticeinaccordancewiththeclause52.243‐4shallbegivenpromptlyto
theContractingOfficer.
2‐1.3.3 SubmittalDescription(SD)FormatandQuantity
SubmittalsareidentifiedbySDnumbersandtitlesasfollows.
2‐1.3.3.1 SD‐01PreconstructionSubmittals
a. PreconstructionSubmittalsarethosewhicharerequiredpriortoaNoticetoProceedfor
Construction.PreconstructionSubmittalsincludeallthosesubmittalsdesignatedas
PreconstructionSubmittalsinthespecificationsectionsandontheScheduleofMaterial

Submittals.

b. Submit 1 digital copy (in PDF Format) of each submittal.

2‐1.3.3.2 SD‐02 Shop Drawings

a. SD‐02 Shop Drawings include:

(1) Drawings,diagramsandschedulesspecificallypreparedtoillustratesomeportion
ofthework.
(2) Diagramsandinstructionsfromamanufacturerorfabricatorforuseinproducing
theproductandasaidstotheContractorforintegratingtheproductorsysteminto
theproject.
(3) DrawingspreparedbyorfortheContractortoshowhowmultiplesystemsand
interdisciplinaryworkwillbecoordinated.

b. Submit 1 digital copy (in PDF Format) of each submittal.

c. The Contractor shall comply with the following standards for SD‐02 Shop Drawings:

(1) Include on each drawing the drawing title, number, date, and revision numbers.

(2) Dimensiondrawings,exceptdiagramsandschematicdrawings;preparedrawings
demonstratinginterfacewithothertradestoscale.Identifymaterialsandproducts
forworkshown.
(3) Drawingsshallincludethenameplatedata,sizeandcapacity.Alsoinclude
applicableFederal,military,industryandtechnicalsocietypublicationreferences.
(4) Papercopiesshallnotbelessthan8‐1/2by11inchesormorethan30by42inches
andshallbesubmittedinboundsets.
2‐1.3.3.3 SD‐03ProductData
a. SD‐03ProductDataincludes:
(1) Catalogcuts,illustrations,schedules,diagrams,performancecharts,instructions
andbrochuresillustratingsize,physicalappearanceandothercharacteristicsof
materials,systemsorequipmentforsomeportionofthework.

(2) Samples of warranty language when the contract requires extended product warranties.

b. Submit 1 digital copy (in PDF Format) of each submittal.

c. The Contractor shall comply with the following standards for SD‐03 Product Data:

(1) Presentproductdatasubmittalsforeachsectionasacomplete,boundvolume.
Includetableofcontents,listingpageandcatalogitemnumbersforproductdata.
(2) Indicate,byprominentnotation,eachproductwhichisbeingsubmitted;indicate
specificationsectionnumberandparagraphnumbertowhichitpertains.
(3) Supplementproductdatawithmaterialpreparedforprojecttosatisfysubmittal
requirementsforwhichproductdatadoesnotexist.Identifythismaterialas
developedspecificallyforproject,withinformationandformatasrequiredfor
submissionofSD‐07Certificates.
(4) Productdatashallincludethemanufacturer'sname,tradename,placeof
manufacture,andcatalogmodelornumber.Submittalsshallalsoincludeapplicable
Federal,military,industryandtechnicalsocietypublicationreferences.Should
manufacturer'sdatarequiresupplementalinformationforclarification,the
supplementalinformationshallbesubmittedasspecifiedforSD‐07Certificates.
(5) Whereequipmentormaterialsarespecifiedtoconformtoindustryandtechnical
societyreferencestandardsoftheorganizationssuchasAmericanNational
StandardsInstitute(ANSI),ASTMInternational(ASTM),NationalElectrical
Manufacturer'sAssociation(NEMA),UnderwritersLaboratories(UL),and
AssociationofEdisonIlluminatingCompanies(AEIC),submitproofofsuch
compliance.Thelabelorlistingbythespecifiedorganizationwillbeacceptable
evidenceofcompliance.Inlieuofthelabelorlisting,submitacertificatefroman
independenttestingorganization,competenttoperformtesting,andapprovedby
theContractingOfficer.Thecertificateshallstatethattheitemhasbeentestedin
accordancewiththespecifiedorganization'stestmethodsandthattheitem
complieswiththespecifiedorganization'sreferencestandard.
2‐1.3.3.4 SD‐04Samples
a. SD‐04Samplesincludes:
(1) Fabricatedorun‐fabricatedphysicalexamplesofmaterials,equipmentor
workmanshipthatillustratefunctionalandaestheticcharacteristicsofamaterialor
productandestablishstandardsbywhichtheworkcanbejudged.
(2) Colorsamplesfromthemanufacturer'sstandardline(orcustomcolorsamplesif
specified)tobeusedinselectingorapprovingcolorsfortheproject.
(3) Fieldsamplesandmockupsconstructedontheprojectsitetoestablishstandardsby
whichtheensuingworkcanbejudged.Includesassembliesorportionsof
assemblieswhicharetobeincorporatedintotheprojectandthosewhichwillbe
removedatconclusionofthework.
b. TheContractorshallfurnishsamplesinsizesbelow,unlessotherwisespecifiedorunless
themanufacturerhasprepackagedsamplesofapproximatelysamesizeasspecified:

(1) Sample of Equipment or Device: Full size.

(2) Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.

(3) SampleofMaterialsExceeding81/2by11inches:Cutdownto81/2by11inches
andadequatetoindicatecolor,texture,andmaterialvariations.
(4) SampleofLinearDevicesorMaterials:10‐inchlengthorlengthtobesupplied,ifless
than10inches.Examplesoflineardevicesormaterialsareconduitandhandrails.

(5) Sample of Non‐Solid Materials: Pint. Examples of non‐solid materials are sand and paint.

(6) Color Selection Samples: 2 by 4 inches.

(7) Sample Panel: 4 by 4 feet.

(8) Sample Installation: As required.

c. The Contractor shall furnish the quantity of samples as stated below:

(1) Whencolor,textureorpatternisspecifiedbynamingaparticularmanufacturerand
style,includeonesampleofthatmanufacturerandstyle,forcomparison.
(2) Submitonesampleofeachrequireditem.Forsamplesrequiringaselectionfor
varioustypes,characteristics,etc,theContractorshallsubmittwosamplesforthree
separatepreferencesoftheGovernment,fromwhichonewillbechosen.One
approvedsampleorsetofsampleswillberetainedbyapprovingauthorityandone
willbereturnedtoContractor.

(3) Submit one sample panel. Include components listed in technical section or as directed.

(4) Submit one sample installation, where directed.

(5) Wherevariationsareunavoidableduetonatureofthematerials,submitsetsof
samplesofnotlessthanthreeunitsshowingextremesandmiddleofrange.
d. Incorporatereturnedsamplesintoworkonlyifsospecifiedorindicated.Incorporated
samplesshallbeinundamagedconditionattimeofuse.Noteandpreservethenotationof
areaconstitutingsampleinstallationbutremovenotationatfinalcleanupofproject.
e. Samplesremaininguponcompletionoftheworkshallbepickedupanddisposedofin
accordancewithmanufacturer'sSafetyDataSheets(SDS)andincompliancewithexisting
lawsandregulations.
2‐1.3.3.5 SD‐05DesignData
a. SD‐05DesignDataincludesdesigncalculations,mixdesigns,analysesorotherdata

pertaining to a part of work.

b. Submit 1 digital copy (in PDF Format) of each submittal.

2‐1.3.3.6 SD‐06TestReports
a. SD‐06TestReportsincludes:
(1) Reportsignedbyauthorizedofficialoftestinglaboratorythatamaterial,productor
systemidenticaltothematerial,productorsystemtobeprovidedhasbeentested
inaccordwithspecifiedrequirements.(Testingmusthavebeenwithinthreeyears
ofdateofcontractawardfortheproject.)
(2) Reportwhichincludesfindingofatestmadeatthejobsiteoronsampletakenfrom
thejobsite,onportionofworkduringorafterinstallation.

(3) Investigation reports

(4) Daily reports

(5) Final acceptance test and operational test procedure

b. Submit 1 digital copy (in PDF Format) of each submittal.

2‐1.3.3.7 SD‐08Manufacturer'sInstructions
a. SD‐08Manufacturer’sInstructionsincludespreprintedmaterialdescribinginstallationofa
product,systemormaterial,includingspecialnoticesandSafetyDataSheetsconcerning
impedances,hazardsandsafetyprecautions.

b. The Contractor shall comply with the following standards for SD‐08 Manufacturer’s Instructions:

(1) Submit manufacturer instructions in compliance with standards for SD‐03 Product Data.

(2) Submit SDS sheets prior to bringing hazardous materials onto base.

(3) Submit manufacturer's instruction prior to installation.

c. Submit 1 digital copy (in PDF Format) of each submittal.

2‐1.3.3.8 SD‐09Manufacturer’sfieldReports
a. SD‐09Manufacturer’sFieldReportsincludesdocumentationofthetestingandverification
actionstakenbymanufacturer'srepresentativeatthejobsite,inthevicinityofthejobsite,
oronasampletakenfromthejobsite,onaportionofthework,duringorafterinstallation,
toconfirmcompliancewithmanufacturer'sstandardsorinstructions.

b. Submit 1 digital copy (in PDF Format) of each submittal.

c. The Contractor shall comply with the following standards for SD‐09 Manufacturer’s Field Reports:

(1) Submitalltestresults;andindicatewhetherthematerial,product,orsystemhas
passedorfailedthetest.

(2) Reports shall be signed by an authorized official of a testing laboratory or agency.

2‐1.3.3.9 SD‐10OperationandMaintenanceData
a. SD‐10OperationandMaintenanceDataincludesinformationfurnishedbythe

manufacturer, or the system provider, to the equipment operating and maintenance personnel.

b. Submit 1 digital copy (in PDF Format) of each submittal.

c. The Contractor shall comply with the following standards for SD‐09 Manufacturer’s Field Reports:

(1) OperationandMaintenanceDatashallnotbesubmittedseparatelyforeachsystem
orcomponentforwhichitisrequired.Rather,alldatashallbeincorporatedintoa
singleboundreport.
(2) Thereportshallbeboundinathreeringbinderandincludeacoversheet,labelfor
thebinderspine,andatableofcontents.Informationforeachcomponentand/or
systemshallbeseparatedbydividersthatareclearlylabeled.