01-RFI_FA302224R0012.pdf
PDF 53 KB Posted
- Attached to
- B267 Expand Hazardous Waste Facility
- Solicitation number
- FA302224R0012
About this file
This document is a Request for Information (RFI) related to Solicitation Number FA302224R0012, titled "B267 Expand Hazardous Waste Facility." The RFI provides responses to three questions regarding the construction project, including clarification that the existing fire sprinkler system is a dry pipe system and that a 1-inch drain pipe issue needs to be addressed.
The related federal contract opportunity is for the expansion of the hazardous waste storage facility, which includes site work, foundation, block walls, roofing, a new rolling door, explosion-proof electrical equipment, and fire protection piping and sprinklers. The government is offering a site visit on September 10, 2024, which is highly encouraged but not mandatory. All RFIs must be submitted by 12:00 PM CST on September 12, 2024. The magnitude of the procurement is between $250,000 and $500,000. Contractors must complete CUI training and sign the acknowledgment form to gain access to the drawings and other associated documents on SAM.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MFR Contractor CUI Training Acknowledgment for Solicitations.pdf | ||
| SOW EEPZ216100 Expand Hazardous Waste Facility B267 17July2024.pdf | ||
| Wage Determination DBA MS20240045.pdf | ||
| FM66 Expand Hazardous Waste Facility.xlsx | XLSX spreadsheet | |
| Solicitation - FA302224R0012.pdf | ||
| Appendix A - Cost Breakdown.xlsx | XLSX spreadsheet | |
| Contractors CUI Training Slides.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Requests for Information: FA302224R0012, B267 Expand Hazardous Waste Storage:
Q1: Do the new blocks for the walls need to be insulated?
A1: No insulation requirement beyond what is inherent to the block.
Q2: The SOW states the Fire Sprinkler System is a wet system. At the site visit it appears that this system is a Dry System. Can this be clarified?
A2: Confirmed it is a dry pipe system.
Q3: It was noted there is a 1" drain pipe coming from the riser to the outside of building dripping water. Does this need to be address when adding new piping to the system?
A3: Yes.