Amendment 1 12 September 2022
502d Contracting Squadron
Request for Quote (RFQ) FA301622Q0113 Equine Saddles, Tack and Repair - US ARMY NORTH Caisson
Joint Base San Antonio (JBSA) – Lackland, TX
The purpose of this amendment is to provide the Government response to contractor questions. Contractor questions are in black. Government responses are in blue.
1. Are contractors required to receive the Covid-19 vaccine? Or at any time during this contract period?
GOVERNMENT RESPONSE: No -- contractors are not required to receive the Covid-19 vaccine.
2. Will negative Covid tests be required for every entry on base every time Contractor is on base?
GOVERNMENT RESPONSE: No -- contractors are not required to be tested to enter the installation.
3. How does the payout structure work? How will we get paid? Is it upon completion of the contract? Or is it as pieces are delivered? Or do we determine the payout?
GOVERNMENT RESPONSE: Please see DFARS clause 252.232-7006 for payment instructions.
The Contractor will get paid as pieces are delivered and accepted/inspected by the Government.
4. Is there a time frame for delivery of the tack for the first team? Or do we determine this?
GOVERNMENT RESPONSE: All items are required to be delivered within 240 days after issuance of contract. If unable to meet this date, please provide proposed delivery date with valid justification.
5. Request for Quote due date is as follows:
Document Due
• Written acknowledgement of Amendment 1 to the
RFQ will be required with your quote submission.
16 September
10:00 am CT
Note: Due to time limitations, no further questions can be accepted by the Government for this acquisition.
File details come from the government source that posted it. Updated .