1) Can we request pictures of the current 1M and 3M Diving Board, including the concrete structure that the contractor will demo?

Answer: See additional document

2) Will the owner release a drawing of the diving board metal stand? Or is it up to the contractor to design the metal stand?

Answer: As far stands the contractor should design the metal stand to match what he is replacing , repairing. If there anything else you need let me know