Question and Answer with responses.pdf
PDF 80 KB Posted
- Attached to
- Furniture Move
- Solicitation number
- FA301026Q0012
About this file
This is a Questions and Answers (Q&A) document for a Furniture Move solicitation, issued on 1 June 2026. The document addresses five inquiries received between 18 May and 27 May 2026 regarding a furniture relocation project with a proposal ceiling of $350,000.00.
Key clarifications provided include: (1) Limitations on Subcontracting (LOS) requirements do not apply to this procurement since it is below the SAT threshold; (2) information regarding electrical components in cubicles has been addressed in an Updated Statement of Work (SOW); (3) photographs of private offices will not be provided by the government, and the manufacturer information is not disclosed; (4) a site visit is not mandatory for award eligibility, and quotes will be accepted based on the provided SOW documentation alone; and (5) photographs of truck staging areas for loading and unloading operations are unavailable, though additional details have been included in the Updated SOW. Offerors are directed to the Updated SOW for further clarification on scope-related questions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Furniture Move Q&A Version 1
1 June 2026
Question # Date Received Question Response 1 18 May 2026 Since the proposal amount will not exceed the SAT threshold of $350,000.00, does the Limitations on Subcontracting (LOS) still apply as it is not specifically stated in the solicitation?
No, it does not apply.
2 19 May 2026 Could you please confirm if there are any electrical components in the cubicles that will need to be moved as part of this project?
See Updated SOW
3 20 May 2026 Can photos of the private offices be provided? Is the manufacturer known?
No photos will be provided for the offices.
4 26 May 2026 Is the site visit mandatory for award eligibility, or will the command accept technical proposals based on the provided administrative Statement of Work?
No, the site visit is not mandatory. Yes, quotes will be accepted based on SOW.
5 27 May 2026 Can you please send pictures of where the trucks will be staged for loading and unloading?
See updated SOW – photos unavailable