Attachment 10 - Addendum 01.pdf
PDF 130 KB Posted
- Attached to
- Repair 3 Chillers Federal contract opportunity
- Solicitation number
- FA301023R0016
About this file
This addendum modifies the statement of work for solicitation number FA301023R0016 to repair three chillers. The contractor shall provide labor, materials, and equipment to complete all work stipulated in the statement of work except providing a temporary chiller. The contractor's labor must be supervised by the chiller manufacturer's inspection and overhaul team, and the existing chiller must be inspected and tested according to the manufacturer's specifications. The contractor will procure and replace recommended parts for two chillers, remove and clean condenser and evaporator heads, and perform eddy current tube testing and plugging. The addendum includes alternate options for the contractor to replace any damaged parts found during inspection and to upgrade control panels and purge units on two chillers if non-operational.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 01
PROJECT NAME: Repair NPS Dorm Chillers 3 & 4, and Inspect Chiller 2
LOCATION: Building 7405 – Keesler AFB, Mississippi
PROJECT NUMBER: MAHG231013
Changes to the SOW:
3.2.4.1 BID ITEMS:
A. BASE BID: Provide labor, materials and equipment to complete all work as stipulated within this SOW other than to provide a temporary Chiller.
B. Contractor labor must be supervised by manufacturer inspection and overhaul team from TRANE TECHNOLOGIES. Existing chiller 2 is a TRANE CVHE770 machine. The chiller must be inspected and tested in accordance with TRANE CVHE specifications. See SOW Section 3.2.4.5.A, and SOW Appendix A for Trane CVHE Chiller Compressor Overhaul Service Procedure List.
C. Contractor is to procure and replace recommended parts for chillers 3 & 4. See SOW Section
3.2.4.4 A and B for replacement parts.
D. Contractor is to remove condenser and evaporator heads and mechanically brush and clean the heat exchanger tubes. Perform a nondestructive eddy current tube analysis of condenser and evaporator tube bundles on chillers 3, 4, and 2 as well as provide results report. Isolate and plug tubes per Trane recommendations.
E. ADD ALTERNATE Option 1: Contractor shall replace any damaged parts found during inspection.
F. ADD ALTERNATE Option 2: If the control panels and purge units are not operational the Contractor is to upgrade control panels and purge units on chillers 3 and 4.
E. ADD ALTERNATE Option 1: Contractor is to upgrade control panels and purge units on chillers
3 and 4 (2 ea) (CLIN 0002 in Solicitation FA3010R0016).
END OF ADDENDUM 01