Attachment 14 Questions and Answers - Turf Field.pdf
PDF 411 KB Posted
- Attached to
- Design and Install Synthetic Turf Field Federal contract opportunity
- Solicitation number
- FA301022R0021
About this file
This document contains questions and answers regarding a federal solicitation for the design and installation of a synthetic turf field. Key details include that the solicitation number is FA301022R0021, the work involves furnishing all design, labor, materials and equipment to design and install a synthetic turf field at Keesler Air Force Base in Mississippi. The acquisition will be set aside for HUBZone small businesses using a best value tradeoff process. Interested HUBZone sources may submit a proposal with a size standard of $16.5 million. The estimated value is between $500,000 and $1 million. The solicitation is anticipated to be posted on SAM.gov on June 24th 2022 with a closing date of July 25th 2022 and a 150 day performance period after award.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A for FA301022R0021
Design and Install Synthetic Turf Field
1. Can you please provide the elevation of the invert of the storm water manhole we are to tie into?
A: 17.9 Invert
2. The “Synthetic Turf Edge Detail” in Attachment #13 references a Geotechnical Report in reference to the compaction of the “Compacted & Moisture Conditioned Subgrade”. Can you please provide the referenced Geotechnical Report?
A: Contractor is to provide this to the Government.
3. Is the demolished scoreboard to be turned over to the government, or is the contractor to properly dispose of it?
A: Demo and dispose of it.
4. Are there existing drawings showing the scoreboard footing sizes?
A: No
5. Please provide electrical specifications.
A: SOW page 3 of 16, item C
6. What is the size of the existing storm drain piping that runs parallel to G Street?
A: 24”
7. Are the existing water mains shown on the Utility Plan to be relocated or left in place?
A: The lines are to be cap next to the main, and the pipe to be removed from the ground as close to the electrical duct bank. Dig permit will show where these lines are located at for removal.
8. Can one person perform the roles of the Superintendent, QCM, & SSHO?
A: Yes
9. In the SOW 3.5.2, it states “Jobsite and lay down / staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening unless noted otherwise.” Please advise which is needed, as item C.3 under “Provide and Install New” states to provide and install a 4’ orange contractor fencing around the entire site.
A: 6’ chain link fence with brown fabric is for Materials and laydown yard.
4’ Orange construction fence is for the perimeter of the job site.