Attachment 3 - Material Submittal Schedule.xls
XLS spreadsheet 56 KB Posted
- Attached to
- Design and Install Synthetic Turf Field Federal contract opportunity
- Solicitation number
- FA301022R0021
About this file
This solicitation package outlines requirements for the design and installation of a synthetic turf field at Keesler Air Force Base in Mississippi. The work includes furnishing all labor, materials, and equipment to design and install the turf field south of Building 1101 according to the statement of work, specifications, and drawings. This will be conducted as a HUBZone small business set-aside utilizing performance price trade-off procedures. Interested HUBZone sources may submit a proposal under NAICS code 238990 for specialty trade contractors with a size standard of $16.5 million. The product service code is C1PA. The proposed construction value is between $500,000 and $1 million. The solicitation package will be posted on SAM.gov on or around June 24th, 2022 with a closing date of July 25th, 2022. The contract performance period will be 150 days after award. Registration in SAM is required for all contractors wishing to do business with the Department of Defense or Department of the Air Force.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG211141 | Project Title: | ||
| Install Turf Field | Solicitation / Contract Number: |
[ enter here ]
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | HazMat Questionnaire | 1 | 5 Days Prior to Start Date | |||||||||||||||||||
| 2 | HazMat MSDS | 1 | 5 Days Prior to Start Date | |||||||||||||||||||
| 3 | Hazmat Reporting Entry Form | 1 | 5 Days Prior to Start Date | |||||||||||||||||||
| 4 | Hazmat Reporting Entry Form | 1 | End of Contract | |||||||||||||||||||
| 5 | Recycling and Landfill Report | 1 | End of Contract | |||||||||||||||||||
| 6 | Warranty (Manufacturer's) | 1 | End of Contract | |||||||||||||||||||
| 7 | 1-Year Warranty (Contractor) | 1 | End of Contract | |||||||||||||||||||
| 8 | Geotechnical Report | 3 | 10 Days prior to construction | |||||||||||||||||||
| 9 | Site Survey and Proposed elevations | 3 | 10 Days prior to construction | |||||||||||||||||||
| 10 | Turf Field Installation Drawings | 3 | 20 Days after award | |||||||||||||||||||
| 11 | Turf Field Maintenance Instructions | 3 | Prior to Close Out | |||||||||||||||||||
| 12 | Storm Water Prevention Plan | 3 | 10 Days prior to construction | |||||||||||||||||||
| 13 | Fill Material | 3 | 10 Days prior to construction | |||||||||||||||||||
| 14 | Turf Field Specifications | 3 | 10 Days prior to construction | |||||||||||||||||||
| 15 | Electrical Submittals | 3 | 10 Days prior to construction | |||||||||||||||||||
| 16 | Color and Logo Submittal | 1 | 3 | 10 Days prior to construction | ||||||||||||||||||
| 17 | ||||||||||||||||||||||
| 18 | ||||||||||||||||||||||
| 19 | ||||||||||||||||||||||
| 20 | ||||||||||||||||||||||
| 21 | ||||||||||||||||||||||
| 22 | ||||||||||||||||||||||
| 23 | ||||||||||||||||||||||
| 24 | ||||||||||||||||||||||
| 25 |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)
File details come from the government source that posted it. Updated .