Attachment 10 Addendum 1 Questions and Answers.pdf
PDF 325 KB Posted
- Attached to
- Washer Lint Traps & Stacks Replacement Federal contract opportunity
- Solicitation number
- FA301021R0003
About this file
This document contains answers to questions from respondents on a federal solicitation for replacing washer lint traps and stacks at a Department of the Air Force installation. The questions and answers provide clarification on project details such as counter top dimensions to be field verified, the availability of an appliance laydown area, and expectations around locating other utilities when excavating. Discrepancies between statement of work and drawing details regarding drain line sizes and cleanout installations are addressed, with the statement of work taking precedence. Dimensions and locations provided in the document are for bid purposes only.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 2.pdf | ||
| Amendment 1.pdf | ||
| Attachment 11 Addendum 1 Drawings.pdf | ||
| Sign In Sheet.pdf | ||
| Attachment 5 - MAHG201024 Wage Det MS20200050.pdf | ||
| Attachment 6 - MAHG201024 Past Performance Questionnaire.pdf | ||
| Attachment 9 - MAHG201024 SF 1444.pdf | ||
| Solicitation - FA301021R0003.pdf | ||
| Attachment 1 - MAHG201024 SOW 20201215.pdf | ||
| Attachment 2 - MAHG201024 Specs 20201215.pdf | ||
| Attachment 3 - MAHG201024 Drawings.pdf | ||
| Attachment 4 - MAHG201024 AF66.xlsx | XLSX spreadsheet | |
| Attachment 7 - MAHG201024 Past Performance Reference List.pdf | ||
| Attachment 8 - MAHG201024 Notice of Compliance.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: Respondent:
January 27, 2021 Onree Wilson
Addendum 1 Questions and Answers
MAHG20-1024
Replace Washer Lint Traps and Stacks Phase 1
Q1. No architechtural details exist regarding countertops and their approximate dimensions/locations.
Can you please provide?
A1. See {1} below as well as included drawings. [Pg. A507 Enlarged Laundry Room Plan/Interior Elevations, Pg. A702 Millwork Details (Detail 1).] Note: These documents and drawings are given as approximate dimensions/locations for bid purposes only. Actual dimensions and locations may vary per laundry room (Depth measurements of the counter tops for these facilities average 12.5”). Contractor shall field verify dimensions prior to purchasing materials and/or fabrication of countertops.
Q2. Will a lay down area be provided for appliance storage containers?
A2. Yes. Location of laydown area to be coordinated with Vectrus and Government Personnel prior to work start.
Q3. Are there any other utilities located in the concrete slabs to be cut/removed?
A3. Per AS-BUILT drawings, we do not expect to encounter any other utilities under concrete slab within the area of work denoted/depicted on the contract documents. As with any project requiring outdoor excavation and dig permits, contractor shall request a locate prior to beginning any excavation activity.
Correction to Attachment 3 - MAHG201024 Drawings:
NOTE: There is a discrepancy between the Statement of Work and page M2 of the Drawings.
The statement of work is the correct course of action.
Statement of Work, Pg. 3, Section Provide and Install New (B) states:
All horizontal and vertical drain piping, clean-outs, and connections for each branch for a complete replacement of existing system. Six-inch schedule 40 PVC piping to replace existing vertical and underground drain piping. Four-inch schedule 40 PVC to replace existing horizontal branch lines. This is correct
Statement of Work, Pg. 4, Section Provide and Install New (L):
References Drawings and states:
two 6” cleanouts are to be installed per facility exterior, one on inlet and one on outlet of lint interceptor near the building. This is correct
Drawings:
A portion of Sheet M2 Drawing #3 New Interceptor Layout is incorrect and should appear as shown below {2}.
Date: Questions and Answers Respondent:
January 27, 2021 Onree Wilson
In the interest of new work drain line sizes and installation of clean-outs, the Statement of work takes precedence over the Drawing Set.
{1}
{2}
6”
End of Addendum