MAHG151099_Q&A__1.pdf
PDF 125 KB Posted
- Attached to
- Repair Street & Parking Lot Striping
- Solicitation number
- FA301017R0017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_3.pdf | ||
| Amendment_2.pdf | ||
| Site_Visit_Sign_In_Redacted.pdf | ||
| Attachment_4_-_Reference_List.docx | DOCX document | |
| Attachment_7_-_Wage_Det_MS170237.pdf | ||
| Attachment_2_-_Drawing.pdf | ||
| Attachment_6_-_Notice_of_Compliance.pdf | ||
| 17-R-0017_Sol.pdf | ||
| Attachment_5_-_SF_1444.pdf | ||
| Attachment_3_-_PPQ.doc | DOC document | |
| Attachment_8_-_SOW.pdf | ||
| SF_30.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
AIR EDUCATION AND TRAINING COMMAND
19 July, 2017
MAHG151099 REPAIR STREET & PARKING LOT STRIPING
QUESTIONS & ANSWERS 1
1. Please specify the type of markings required. The specs list multiple types of application, but nothing states which spec is applicable to this project.
Answer: Paint markings with reflector beads as called for and specified
2. If thermoplastic is required, please be sure to state if hot or cold application is required.
There's is substantial price difference between the two.
Answer: Thermoplastic markings are not required.
3. Are pavement reflectors part of this project?
Answer: Pavement reflectors are part of this project at existing roadways with reflectors.
4. Will multiple mobilizations be required to complete the work or can all work be completed with one mobilization and one demobilization priced into the proposal?
Answer: Multiple mobilization are the contractor’s option and will depend on their Scheduling and Coordination with Keesler AFB. Parking lot striping is to be done on the weekends which may include 'Down Fridays' and Holidays at Contractor’s option. Contractor shall provide and post 18”x24” warning signage at each parking lot entrance 1 week in advance of striping each parking lot.
5. If thermoplastic is to be applied will the existing thermoplastic need to be removed prior to application?
Answer: NA
6. If thermoplastic is required, please be sure to state if hot or cold application is required.
There’s is substantial price difference between the two Answer: NA
7. We are requesting the pay items per sheet 3 of 3 of the project drawings under general note 2:
Edge stripe shall be same material as lane-line stripe (paint or plastic as indicated in pay items). We believe having these pay items will provide quantities for paint and plastic (thermo) to be installed per the scope of work.
Answer: See approximate quantities in the Scope of Work.
8. Please let us know if all parking parallel to streets are included in new striping. Currently, some adjacent parking areas are greyed out and some are not. -Will parking areas that are adjacent to the streets that are to me striped be striped also?
Answer: Yes
9. After the Contractor provides 3 days notice prior to striping parking lots, will the Air Force close the lot or will the Contractor be responsible for coning it off?
Answer: See Question #4. Contractor shall cone off at 1800 the evening before striping.
NOTE: Thermoplastic was mentioned a lot times in the Specifications attachment. Please disregard these references.