RFIs (Answered).docx

DOCX document 36 KB Posted

Attached to
Repair HVAC/Boiler Bldg 3500 Federal contract opportunity
Solicitation number
FA286020R0048
Issued by
Department of the Air Force Headquarters District Washington

About this file

This document contains questions and answers regarding a federal solicitation to repair HVAC and boilers at Building 3500. The solicitation seeks replacement of boilers, chillers, RTUs, and expansion of the existing energy management system. Key details include replacing two boilers with high-efficiency models, installing a new 320-ton chiller adjacent to existing, replacing an RTU serving an amphitheater, and ensuring new components are compatible with the Automated Logic controls system. The period of performance is from September 2020 to May 2021. The rough order of magnitude cost is between $1-5 million. The solicitation is issued by the Department of the Air Force for work at Joint Base Andrews.

View the file

Other files for this federal contract opportunity

Other files attached to Repair HVAC/Boiler Bldg 3500, newest first.
File Type Posted
Solicitation - FA286020R0048 (Revised).pdf PDF
A70I_33-04-039.PDF PDF
M2.4.pdf PDF
P2.2.pdf PDF
M01.pdf PDF
M1.5.pdf PDF
M4.6.pdf PDF
M6.2.pdf PDF
RLC-PRC006Q-EN_07102018.pdf PDF
M2.3.pdf PDF
M4.6 (1).pdf PDF
ANGRC HVAC BOILER DIAGRAM.pdf PDF
M1.12.pdf PDF
P0.1.pdf PDF
M6.1.pdf PDF
M4.1.pdf PDF
ANG B3500 Chiller As Builts Drawings.pdf PDF
AJXF 20-1547 Repair HVAC Boiler-Bldg 3500 SOW (Revised 2).docx DOCX document
AJXF 20-1547 Repair HVAC Boiler-Bldg 3500 SOW (Revised).docx DOCX document
Base Access Info Requirements.xlsx XLSX spreadsheet
Solicitation - FA286020R0048.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Reference: “Design Build” OR “Replace in Kind” Project / Statement of Work - 8/17/2020 (SOW), Title Page (Page 1), and Part 2.1.1 (Page 2); and Solicitation No. FA286020R0048 – Page 1 of 51, Block 10.

Question: Statement of Work (SOW) Title Page (Page 1) states “Design Build Project”. Document named ‘Solicitation+-+FA286020R0048’ (SF1442), Page 1, Block 10 and SOW Part 2.1.1 both state “This is a “Replace in Kind” project.”. Which is correct? This has a bearing on the type and number of engineering tasks required, their associated costs and the deliverable documents to be generated.

Replace in kind

2. Reference: Period of Performance / Solicitation No. FA286020R0048 – Section F, Page 8 of 51.

Question: Please confirm the designated Period of Performance is from 07 Sept 2020 to 12 May 2021. (This is 247 calendar days.) RTUs and chillers may have long lead/order times which could impact the designated Period of Performance.

247 days POP from NTP

3. Reference: High Efficiency Boilers / Statement of Work - 8/17/2020 (SOW), Part 2.1.1 – HVAC (Page 2) Question: Please define and further describe ‘High Efficiency Boilers’.

The existing Lochinvar gas-fired, hot water boiler is approximately 75% to 85% efficient and over sixteen years old. The government is interested in new boilers, with high output high efficiency, and hot water boiler capacity.

4. Reference: Statement of Work - 8/17/2020 (SOW), Part 2.1.1 – HVAC (Page 5) Question: 20 Ton AHU indoor unit and associated roof mounted condensing unit serving Crisis Action Team (CAT). “New indoor/outdoor unit shall be compatible with R-143a.” This refrigerant is unfamiliar to TRC. Typically, split systems of this type use R-410A. Is this a typo? Please clarify.

This was not a typo, since this refrigerant is limited to one company and most companies use R410a then R410a is the refrigerant to be used.

5. Reference: Statement of Work - 8/17/2020 (SOW), Part 2.1.1 – HVAC (Page 5) Question: “30 Ton RTU servicing the large amphitheater room”: Is this unit operated continuously or is it cycled on for occupancy only? This room presents special problems if an RTU of that size is operated with the room being vacant a majority of the time. Premature failure and/or very poor performance can be expected if this unit is not designed and then operated in accordance with the design.

This unit is operated continuously. Pre-COVID this room is heavily used. Post COVID this room is slowly increasing in usage. The government is expecting a unit to be designed that can heat/cool this unique multi-purpose area.

6. Reference: Statement of Work - 8/17/2020 (SOW), Part 2.1.1 - HVAC (Page 5) Question: ‘The Contactor shall submit design calculations to substantiate proposed layout and sizing of utilities and structural elements (i.e., HVAC loads, electrical loads, Platform supports, etc.). What types of design calculations are required? Is the Carrier HAP program acceptable for HVAC calculations?

Yes, HAP is acceptable. This is a replace in kind project, CE is asking for design calculations for verification purposes for the outdoor units and sizing of new pipes and new pumps if applicable.

7. Reference: Efficiency Rating for RTU and Split System / Statement of Work 17/2020 (SOW) Question: For RTU and Split System, what efficiency rating is required. Is there interest in energy efficiency system changes, such as CO2 control of outdoor ventilation?

The required efficiency (SEER) is per the latest Unified Facilities Criteria. The government is interested in outdoor ventilation and programmed into the controls system. B3500 already has CO2 sensors.

8. Reference: EMC System Background / Statement of Work - 8/17/2020 (SOW) Question: “Install new energy management control system to all new components and connect to JBA EMC System.” Please provide EMC System background (I.E., existing sequences of operation, Bacnet or Lonworks backbone, graphics standards, etc.) for our price proposal.

Ensure all new components are compatible with Automated Logic, the existing building control system. Our buildings are not integrated with Joint Base Andrews control systems.

9. Reference: Commissioning Requirement / Statement of Work - 8/17/2020 (SOW) Question: There are effectively four projects here; boilers replacement, N-1 chiller new installation, RTU replacement, and energy management system addition/expansion. What level of commissioning effort is expected? Please elaborate.

Contractor to commission only new equipment per the Statement of Work.

10. Reference: Air and Water Flow Readings and Balancing / Statement of Work - 8/17/2020 (SOW) Question: Is it the intention of this RFP to limit air and water flow readings and balancing to the replaced equipment; or to do ‘whole-system’ balancing?

Limit air and water flow readings and balancing to the replaced equipment

11. Reference: Power for New Chiller / Statement of Work - 8/17/2020 (SOW), Part 2.1.1 – HVAC (Page 5) Question: Has any accommodation been made electrically for the new chiller? Or is it the intent of the Scope of Work for the chillers to be operated from the same power source; Either/Or?

It is the government intent for the contractor to place the chiller adjacent to the existing chiller system outside and run power back underground to the electrical room in B3500 that was visited on Monday/17 August.

12. Reference: Permits / Statement of Work - 8/17/2020 (SOW), Part 6.3.1 Question: Permits are described in Part 6.3.1. Please provide a list of the specific permits and their associated fees as required for this project. If a (Construction) Permits and Fees Schedule exists for Joint Base Andrews, please also provide that document.

JBA is Federal land to include B3500. Contractor shall follow all Federal regulations and laws, to include all Air Force guidance and regulations.

13. Reference: Statement of Work - 8/17/2020 (SOW), Part 2.1.1 – HVAC (Page 5) Question: There is reference to a drawing to be attached to the RFP related to the chiller layout piping. “Install new 320 Ton Trane air-cooled chiller with new concrete pad adjacent to existing chiller to remain, and connect new chilled water pipes to existing chiller piping system refrigerant relief piping, and valves as referred in attached drawing, reinsulate all existing and new chilled water piping and fittings in mechanical room.” We have received the mechanical drawings, but to be clear, there is NOT an additional drawing showing the new piping, valves, etc., as referred to. Missing Mechanical Drawings - to date – are as follows: M1.1 through M1.4, M1.6 through M1.11, M1.13 through M1.15, M2.5, M2.6 and M3.3. We request all Mechanical Drawings as part of verifying chiller, boiler and pumps sizing as required in the RFP. We also request Electrical Drawings for the same reason.

Will be provided if available

14. Reference: Sequence of Operation for Chiller / Statement of Work - 8/17/2020 (SOW) Question: “The contractor shall coordinate phasing sequence for chiller with the building staff/facility manager to minimize chiller downtime, refer to attached drawing for sequence of operation.” Please advise which of the drawings issued to date includes a “Sequence of Operations”. If not shown or included on the drawings provided to date, please provide a copy of the referenced drawing Will be provided if available

15. Reference: Chilled Glycol Thermal Storage Plant / Drawings Question: Limited drawings provided indicate a partial load low temperature chilled glycol thermal storage plant. Is this still functional and is the new N-1 chiller required to run at the lower temperatures?

The old ice enhanced chiller system has been removed. The new chiller is not required to operate at lower temperatures. Refer to New drawings.

16. Reference: CAD and Word Files for Contractor’s Use Question: Please advise if the Owner will provide CAD files (drawings) and Word files (specifications) for the Contractor’s use in generating the required Design Documents.

Will be provided if available Additional CAD drawings and Word doc specifications will be provided to assist with the design effort that will aid in the As-Built requirement.

17. Reference: Site Superintendent – Quality Control and Site Safety Question: Will the Contractor’s Site Superintendent be allowed to also perform the roles of Quality Control Manager (QCM) and Site Safety and Health Officer (SSHO)? If not, please specify the On-Site Personnel requirements.

I do not have issue with the following request. The government would expect a cost savings for only having one representative for the three tasks.

18. Reference: Building Automation System / Controls Contractor Question: Please provide the company name, contact person, and phone number for the Building Automation Systems (BAS)/Controls Contractor currently providing service and/or maintenance for the existing building and temperature controls systems in Building 3500.

The Automated POC will be provided the Contractor after award of project

19. Can this project be completed in phases so to least effect the buildings tenants? Most of the work would start end of March beginning of April.

• Boilers be replaced summer of 2021 after heating season.

• CU-1.6 serving Crisis Action Team AHU-1.1 spring 2021.

• RTU-1 serving the large amphitheater room spring 2021.

• Will the large amphitheater room be in use during construction?

The government expects long lead-times for the following parts/equipment and is very interested in minimally interfering with the building tenants. Any scheduling opportunity that minimizes tenant discomfort, competitively priced, and provides the best value has a great chance of award.

20. Will this project require off hours and if so when and for what project?

This project does not require off hours. If the Contractor desires a case-by-case basis to deliver/install etc. during off hours, then the government may consider making arrangements if the following benefits the Contractor and the government. However, this project is expected to be scheduled during normal business hours Monday thru Friday.

21. At the site visit it was said the Automated Logic was the controls contractor for building 3500. Please confirm and provide contact information.

B3500 is controlled by Automated Logic, and the POC information will be provided to the Contractor after award.

22. SOW for Chiller: Reinsulate all existing and new chilled water piping and fittings in mechanical room.

• Are we to reinsulate the existing and new chilled water piping at the chillers only, not the mechanical room? No, Contractor not required to reinsulate existing piping/fittings, only the new piping and fittings per this statement of work.

• Are we to heat trace the existing and new chilled water piping at the chillers? No, existing piping/fittings already have heat trace and not required to be repaired or replaced by the contractor. All new heat trace and insulation for new chilled water piping are to be installed as per manufactures recommendations.

• Please provide voltage requirements and heat trace specification?

Heat trace shall be in accordance with local, State, Federal regulations. Contractor can match existing heat trace product. However, contractor must provide submittal/approval prior to purchase/installation for government approval.

• Can you provide chilled water piping insulation specification? Contractor to match existing pipe insulation (Replace in kind). Contractor to provide submittal prior to purchase/installation for government approval

23. Existing drawings show Glycol system:

• Is the chilled water piping system still glycol? Yes

• Will new glycol system need to be filled by the mechanical contractor? Yes

• If so, what type glycol is required and at what percentage?

The existing system does have glycol. Pipe system to be sectioned off with relief valve. Contractor to replace any glycol loss with new. Glycol must be food based. Provide submittal prior to purchase/installation for government approval.

24. Roofing work will need to be done for the boiler flues:

• Is the roof under warranty?

• Please provide contractor name and contact information if so?

A new roof was recently installed (2018). The government would like to consider other options vs. going through the roof. The roof warranty company/number is the following; TREMCO, warranty number 176872, phone 1-800-422-1195

25. Contractor shall verify if existing pumps to remain are compatible with new selected boilers:

• Are you talking about boiler inline pumps or the building loop system pumps P-R.1 & P-R.2?

Contractor to verify the boiler inline pumps

26. Boiler room:

• Will the expansion tank need to be replaced? No, not in contract

• Will the air separator need to be replaced? No, not in contract

• Will new water treatment service be required? No, not in contract

27. During the two-walk through’s the SOW only reflected replacing the CU-1.6 New scope calls to remove and replace existing 20 Ton Trane compressor on roof and indoor AHU serving the Crisis Action Team. Since this wasn’t part of first scope. There was discussion at the second visit to change out DX coil only.

• Please confirm that the AHU-1.1 is to be demoed and replaced in its entirety. The government request the removal of the compressor and the DX coils only.

• Drawing M1.5 boxes in the area of AHU1.1 referring to M2.1. Drawing M2.1 is needed for the AHU1.1 serving Crisis Action Team. Please provide.

28. Building electrical drawing are needed for the northeast addition. Please provide.

The drawings and as-builts are posted on BETA SAM in the attachments section.

29. Can bid be extended?

• Equipment vendors need time to put this together for the equipment.

• Subs will need some time once we figure our basis of design.

The proposal due date will be extended (exactly one week from the time of RFI answers being posted on BETA SAM).

30. Please provide record drawings or as-builts for the mechanical & electrical systems associated with the equipment replacement.

The drawings and as-builts are posted on BETA SAM in the attachments section.

31. The SOW references “drawings” in several locations, such as the sequence of operation, the new chiller enclosure and the mechanical room layout.

The drawings and as-builts are posted on BETA SAM in the attachments section.

32. Is there a POC for the controls contractor for the building if it’s not Siemens?

This building (3500) is controlled by Automated Logic – The POC will be provided after award

33. Please provide the Rough order of Magnitude for this project IAW FAR 36.204(f), the rough order of magnitude for this project is between $1,000,000 and $5,000,000