FA2860-15-R-0011-0002.pdf
PDF 35 KB Posted
- Attached to
- Solicitation and Documents Federal contract opportunity
- Solicitation number
- FA2860-15-R-0011
About this file
FA2860-15-R-0011-0002
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F1D3265078A001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
1. The purpose of this amendment is to make changes to SOW, Section 01010, Paragraph, and extend proposal date to 11 September 2015.
2. SOW Amendment #2 is hereby incorporated as an attachment.
3. Offer due date and time is extended to 12:00PM (EST) on 11 September 2015.
4. All other terms and conditions remain unchanged.
POC: TSgt Christopher Castro, christopher.r.castro8.mil@mail.mil, 240-612-5661
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Aug-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA2860-15-R-0011
X 9B. DATED (SEE ITEM 11)
11-Aug-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Aug-2015
CODE
11TH CONTRACTING SQUADRON
1349 LUTMAN DRIVE
JOINT BASE ANDREWS MD 20762-6501
FA2860 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA2860-15-R-0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
ISUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS & ANSWERS
FA2860-15-R-0011 Questions & Answers
Q. Should bid include cleaning of the downspouts?
A. Contractor shall clean all vertical drain lines. See SOW Section 01010 Para 4.2.7 for inclusion of work.
Q. Should bid include upgrading/replacing of hatch for access to the roof?
A. Contractor shall install new roof hatch. See SOW Section 01010 Para 4.2.6 for inclusion of work.
Q. How many non-functioning vents or ducts are on the roof and do they need to be removed?
A. Only one are has been identified as an inoperable vent. Contractor shall be required to re-roof, re-flash, or remove and re-deck this vent. See SOW Section 01010 Para 4.2.8 for inclusion of work.
Q. How will selection for award be made?
A. Selection shall be based on lowest-price offeror.
Q. Since core samples were not available during the site visit, should we include moisture testing as part of bid?
A. The SOW has been modified requiring the contractor to replace all section of the roof. See
Amendment #1 as posted on FBO.
Q. Will electronic proposals be accepted and if so, can the bid bond be scanned?
A. Electronic proposal shall be accpeted, as well as the scanned bid bond. The selected awardee shall be required to provide the original copy of the bid bond with the raised seal after award.
Q. The contractor estimate form does not have line items for inclusion of certain items, will this document be modified or can an offeror insert additional lines items?
A. The estimate form may include additional line items as needed.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 08-Sep-2015 12:00 PM to 11-Sep-2015 12:00 PM.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 10 Drawing #2
Attachment 11 Drawing #14
Attachment 12 Drawing #13
Attachment 13 Drawing #12
Attachment 14 Drawing #11
Attachment 15 Drawing #10
Attachment 16 Drawing #1
Attachment 18 Contractor Estimate
Form: Choice #1
Attachment 19 Bldg 1444 Roof Report
Attachment 2 Site Plan
Attachment 20 SOW Amendment #1
Attachment 3 Drawing #9
Attachment 4 Drawing #8
Attachment 5 Drawing #7
Attachment 6 Drawing #6
Attachment 7 Drawing #5
Attachment 8 Drawing #4
Attachment 9 Drawing #3 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 10 Drawing #2
Attachment 11 Drawing #14
Attachment 12 Drawing #13
Attachment 13 Drawing #12
Attachment 14 Drawing #11
Attachment 15 Drawing #10
Attachment 16 Drawing #1
Attachment 18 Contractor Estimate
Form: Choice #1
Attachment 19 Bldg 1444 Roof Report
Attachment 2 Site Plan
Attachment 21 SOW Amendment #2
Attachment 3 Drawing #9
Attachment 4 Drawing #8
Attachment 5 Drawing #7
Attachment 6 Drawing #6
Attachment 7 Drawing #5
Attachment 8 Drawing #4
Attachment 9 Drawing #3
(End of Summary of Changes)