This file is a Consolidated Requests for Information (RFI) and Responses document for a federal contract opportunity FA2823-26-Q-0062 for drone targets, issued by the Air Force as of August 7, 2026.

The procurement seeks counter-UAS testing aircraft with the following key specifications: a delta wing airframe (preferred for visual representation, though conventional airframes are acceptable), an Orange Cube autopilot or NDAA-compliant equivalent compatible with Mission Planner, and an RFD-900 telemetry radio or similarly capable Mission Planner-compatible alternative. Gasoline propulsion is preferred for thermal and acoustic signatures, with electric configurations potentially acceptable depending on use case; electric aircraft must achieve two hours of all-inclusive flight time, while gasoline aircraft require two hours of avionics power. The solicitation includes requirements for 10 flight batteries (1/tail) and a complete launch solution if the aircraft requires a physical launch mechanism; however, a launcher is not required for conventional or vertical takeoff and landing aircraft, and a runway is available for operations. Aircraft are non-recoverable and single-use expendable. Contractor acceptance testing with documented results satisfies flight testing requirements prior to delivery. Delivery is required 45 days after receipt of order, though alternative timelines may be acceptable based on mission requirements. Offerors may submit multiple solutions (e.g., separate gasoline and electric options), with evaluation based on lowest priced technically acceptable criteria. TAA compliance does not apply as the requirement is anticipated to fall below the TAA threshold. Towed aerial target systems are not acceptable; an independently launched, self-flown target aircraft is required.

View the file

Other files

File Type Posted
RFIs 10 Aug 26.pdf PDF
FA282326Q0062 Amend 0001.pdf PDF
RFIs 4 Aug 26.pdf PDF
RFIs 28 Jul 26.pdf PDF
Combo.pdf PDF
FA282326Q0062.pdf PDF
Att 2 Brand Name Justification R.pdf PDF
Att 3 Reps and Certs.docx DOCX document
Att 1 TRD 6 Jul 26.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA2823-26-Q-0062 – Drone Targets Consolidated Requests for Information As of 07 Aug 2026

Question 1): Are the end users planning to utilize these drones for pilot training or Counter-UAS training?

Response 1): We are planning on using the targets for counter-UAS testing.

Question 2): Aircraft Configuration (Section 2.b.ii): The Technical Requirements Document states that a Shahed-type flying wing airframe is preferred, although a conventional airframe may be suitable. Could the Government clarify how this preference will be evaluated? Specifically, is the preference based primarily on aerodynamic performance, visual representation, or another operational consideration?

Response 2): A delta wing is preferred for its visual representation.

Question 3): Orange Cube Autopilot (Section 2.b.iii): Will the Government consider an equivalent commercial autopilot that provides the required functionality and is fully compatible with Mission Planner, or is the Orange Cube autopilot a mandatory requirement?

Response 3): The Orange Cube is preferred due to its ease of use and Mission Planner compatibility. A similar, NDAA compliant autopilot may be acceptable.

Question 4): RFD-900 Radio (Sections 2.b.iv and 2.c.ii): Will the Government consider an equivalent telemetry radio that provides the required range and is fully compatible with Mission Planner in lieu of the specified

RFD-900?

Response 4): A similarly capable radio that is compatible with Mission Planner may be acceptable.

Question 5): Flight Testing (Section 2.b.vii): The Technical Requirements Document requires contractor flight testing prior to delivery. Could the Government clarify the expected scope of this testing? Specifically, is Contractor acceptance testing with documented results sufficient, or does the Government expect a formal flight acceptance demonstration or witness testing prior to delivery?

Response 5): Contractor acceptance with documented results are sufficient.

Question 6): Launch Interface (CLIN 0004): Please clarify the "Launch Interface" requirement. Is the Government seeking compatibility with an existing launch system, or is the Contractor expected to provide a complete launch solution as part of this procurement?

Response 6): If the aircraft requires a physical launch mechanism, the Contractor is expected to provide a complete launch solution.

Question 7): Regarding CLIN 0004 (LAUNCH INTERFACE): Is a launcher required even if the aircraft has landing gear? The manufacturer is not sure if the end user has access to a runway or a large open field for takeoff with conventional landing gear?

Response 7): If the aircraft is Conventional or Vertical Takeoff and Landing, a launcher is not required.

Question 8): Is gasoline propulsion a requirement for award? If an all-electric configuration would be considered under the stated option for electrical, what is the minimum required aircraft endurance per sortie? The TRD specifies two hours of flight time in the context of flight batteries, which on a gasoline aircraft would describe avionics power rather than propulsion endurance.

Response 8): Gasoline is preferred for its thermal and acoustic signals. Electric configurations may be acceptable depending on use case. The two hours of flight time would be all inclusive for electric propulsion, and would be just avionics power for gasoline.

Question 8): Regarding CLIN 0004, Launch Interface: Does the Government require a specific launch method, or is the launch interface expected to be whatever the offered aircraft's launch system requires?

Response 8): Please see responses # 6 and 7.

Question 9): Are the aircraft expected to be recoverable and reusable across multiple test events, or single-use expendable?

Response 9): The aircraft are not expected to be recoverable.

Question 10): Gasoline Propulsion, with option for electrical is required in this requirement, but it is also mentioned with an option for electric. Are Electric VTOL options also acceptable?

Response 10): See response #8

Question 11): Regarding the aircraft propulsion requirement, the solicitation states "Gasoline Propulsion, with option for electrical" and also requires "Flight batteries supporting 2 hours of flight time, 10x batteries (1/tail)." If offering a gasoline-powered aircraft, are the 10 flight batteries still required, or is this requirement only applicable to an electrical propulsion configuration?

Response 11): See response #8

Question 12): Is the requirement open to other than launcher aircraft? Would a runway be available to take off from?

Response 12): Launcher is not required. A runway is available.

Question 13): Shahed is preferred, but are non-Shahed aircraft options also acceptable?

Response 13): See response #2

Question 14): Delivery is required to be made 45 Days After Receipt of Order (ARO). If the lead time exceeds the required timeline, would it still be acceptable?

Response 14): Alternative timelines may be acceptable depending on mission requirements.

Question 15): Is TAA compliance required for this requirement only, or are non-TAA-compliant products acceptable?

Response 15): This is anticipated to be under the TAA threshold, therefore it does not apply.

Question 16): Given the stated end use of counter-UAS testing, would a towed aerial target system be considered responsive to this requirement, or is an independently launched, self-flown target aircraft (as described in the TRD) a firm requirement for this acquisition?

Response 16): A towed aerial target would not be acceptable.

Question 17): Can we submit more than one solution in our quotation, for example, Option 1 (Gasoline) and Option 2 (Electric), when submitting our proposal?

Response 17): Offering separate solutions is acceptable. The evaluation criteria is lowest priced technically acceptable so it would be up to the Offeror if they want to split their efforts on separate solutions to meet the Government’s minimum requirements.