STATEMENT OF WORK

FOR

33 FW Wheel and Tire Shop Aircraft Parts Washer, Bldg. 1417 5 August 2019

1. SCOPE:

The project is located at Eglin AFB, Florida, 33rd Fighter Wing, building 1417. The Clean Products Inc. parts washer model HD-4848-HP-SS that is currently installed in building 1417 requires removal/transport/disposal. The contractor is responsible for all labor and equipment associated with removing and transporting the old Clean Products Inc. parts washer model HD- 4848-HP-SS. The replacement washer requires purchase and installation. The new aircraft wheel washer equipment should be sized to operate on the existing electrical circuit to the current parts washer. The current circuit is 480 volts, 3-phase, fed from panel P4 in room 211 and is protected by a 100 amp circuit breaker. The circuit consists of 3 #1 power conductors plus a #8 ground in 1.5” conduit terminating in a 100 amp non-fused disconnect. The current aircraft parts washer is then fed from this disconnect. If the new aircraft parts washer equipment can’t use the existing circuit, then it is the contractor’s responsibility to properly size and install the required circuit components to power the new equipment from panel P4 in room 211. The new washer will be installed in the same location as the existing The Clean Products Inc. parts washer model HD-4848-HP-SS, therefore, the old aircraft wheel washer must be removed first. The contractor is responsible for all labor and equipment associated with the transport and installation of the new washer. Tooling required for removal of the old parts washer and install of the new parts washer will not be provided by the 33rd MXS. All previously mentioned expenses must be included and itemized in the contractor bid.

2. TECHNICAL REQUIREMENTS:

o Cabinet style washer o Standard turn table o Washer must be able to fit 2 (two) wheels & 2 (two) rings during the cycle, see wheel & ring dimensions below:

Wheel Dimensions & Weight 22 x 12 inches, 90 lbs.

Ring Dimensions & Weight 22 x 5 inches, 20 lbs.

o The current washer’s dimensions is 96 x 84 x 72. The new washer’s dimensions may not exceed more than 18 inches over current dimension.

o Complete wash & rinse cycle must be completed in less than 25 minutes.

o Must be compatible with CALLA 296 wheel cleaner.

o Water temperature used for the wash cycle must reach 180 degrees.

o Turn-key installation o OEM manual o Safety & operation training, must be scheduled within 7 calendar days after installation o Automatic Fresh Water Rinse System o Automatic Steam Exhaust

4. ELECTRICAL

Provide all labor and materials to disconnect and remove the existing parts washer. Reuse the existing circuit to power the new equipment, if possible, or install the required electrical circuit from panel P4 (room 211) to a properly sized non-fused disconnect mounted adjacent to the equipment. Existing circuit breakers, conductors, conduit, and non-fused disconnect can be re-used by the contractor as long as they are the required size/rating IAW the manufacturer’s specifications/latest edition of the National Electrical Code (NEC). This circuit shall be installed in electric metallic conduit (EMT), and the conductors, conduit, and circuit breaker shall be sized IAW manufacturer’s specifications/latest edition of the National Electrical Code (NEC).

Install the circuit from the non-fused disconnect switch to the parts washer. This circuit shall be installed in EMT conduit with a final transition of no more than 6’ liquidtight, flexible metal conduit using compression fittings appropriate to the installation, to make the final connection to the new equipment. Both the conductors and conduit shall be sized IAW manufacturer’s specifications/latest edition of the NEC.

OTHER ELECTRICAL SPECIFICATIONS:

Contractor shall perform all investigative and design services to verify where they will get power to feed the new equipment, which include all material required and method of installation Final installation shall comply with the manufacturer’s recommended instructions and standards.

Install all necessary components to make this a complete and operational system and by all appropriate codes and standards.

All insulated type wire shall be THHN/THWN copper Only use compression fittings for EMT conduit. Connectors using set screws are not allowed.

Contractor must field verify the voltage, amperage, wire size, transformer size, measurements, etc.

Ensure electrical work is completed per the latest edition of the National Electrical Code.

Ensure new electrical work is grounded and bonded per the latest edition of the National Electrical Code Ensure Design and Installation meet all requirements of UFC 3-600-01 and all applicable NFPA standards Ensure compliance with the Eglin AFB specific base electrical requirements.

All branch circuits shall have their own neutral conductor, no sharing of the neutral conductor.

The Contractor shall repair any openings in electrical boxes, panels, cabinets, etc. when the opening is created by the Contractor removing something or not using an opening they created

Any holes created by the Contractor through the wall, floor, ceiling, etc. for installation or removal of conduit, pipe, duct, etc. needs to be repaired to seal the opening with appropriate material to meet any appropriate code requirements.

5. POINT OF CONTACT:

SrA Madison Cotton , madison.cotton@us.af.mil

6. CHANGES TO THE SOW:

No changes to this SOW will be allowed without the Contracting Officer consent.