Attach_A_-_SOW.pdf

PDF 574 KB Posted

Attached to
Repair Water Main and Fire Suppression at Santa Rosa Island Tower
Solicitation number
FA282318R4011
Issued by

About this file

Attach A - SOW

View the file

Other files

File Type Posted
Attach_A_-_SOW.pdf PDF
FA282318R4011_Amendment_4.pdf PDF
Attach_J_-_Access_Affidavit.pdf PDF
Attach_E_-Wage_10.5.2018.pdf PDF
Bid_Schedule_with_CLIN_options.pdf PDF
Attach_D_-_Eglin_Language.pdf PDF
Attach_I_-_50_Divisions.xls XLS spreadsheet
Attach_G_-_Past_Performance_Q's.docx DOCX document
Attach_B_-_Drawings_9.20.18.pdf PDF
Attach_H_-_Financial_Resp_Q's.docx DOCX document
Attach_F_-_Past_Performance_Info.docx DOCX document
FTFA_17-1109_Bidder_Inquiries.pdf PDF
Attach_C_-_Specifications_9.20.18.pdf PDF
FA282318R4011_Amendment_3.pdf PDF
FA282318R4011_Amendment_2.pdf PDF
FTFA_17-1109_Solicitation_Amendment.pdf PDF
Attach_G_-_Past_Performance_Q's.docx DOCX document
Attach_F_-_Past_Performance_Info.docx DOCX document
Attach_H_-_Financial_Resp_Q's.docx DOCX document
Attach_E_-Wage_Determination.pdf PDF
Attach_J_-_Access_Affidavit.pdf PDF
Attach_H_-_Financial_Resp_Q's.docx DOCX document
Attach_D_-_Eglin_Language.pdf PDF
Attach_C_-_Specifications.pdf PDF
Attach_B_-_Drawings.pdf PDF
Attach_G_-_Past_Performance_Q's.docx DOCX document
Attach_I_-_50_Divisions.xls XLS spreadsheet
FA282318R4011.pdf PDF
Attach_F_-_Past_Performance_Info.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION

STATEMENT OF WORK

FTFA 17-1109

Repair Water Main Rupture, Bldg 9284

Eglin AFB, FL

96th Civil Engineering Group

Repair Water Main Rupture, Bldg 9284

FTFA 17-1109

Eglin CEG Drawing/Specification: 18AB

Eglin AFB, FL

TABLE OF CONTENTS

1. GENERAL DESCRIPTION OF WORK

2. PERIOD OF PERFORMANCE

3. LIQUIDATED DAMAGES

4. CONTRACTOR QUALITY

5. SAFETY

6. SUBMITTALS

7. SCHEDULE

8. REQUEST FOR INFORMATION

9. MEETINGS

10. TEMPORARY FACILITIES AND WORK AREA

11. CRANES

12. UTILITY OUTAGES AND ROAD CLOSURES

13. AVAILABILITY AND USE OF UTILITY SERVICES

14. HOURS OF WORK

15. WARRANTY

16. CLOSEOUT

17. ADDITIONAL ENCLOSURES

Repair Water Main Rupture, Bldg 9284 FTFA 17-1109

Eglin AFB, FL Revision 0

1. GENERAL DESCRIPTION OF WORK

Bldg 9284 is a 300 foot range tower located on Eglin AFB’s Santa Rosa Island test range at Site A-13B. Building 9284 consists of two structures; the tower with an elevated POD with three floors and an adjacent utility building on a raised platform near the base of the tower.

Bldg 9284 existing fire suppression components are deteriorated to the point that they are no longer considered functional and there is currently no fire protection for the facility.

Work includes the demolition of the existing fire suppression components and the installation of new fire suppression components in accordance with contract plans and specifications. Project was designed by Peterson Engineering Inc. on 11 April 2018.

2. PERIOD OF PERFORMANCE

The Contractor shall be required to (1) commence work under this contract(s) within 8 calendar days after the date the Contractor receives the notice to proceed, (2) prosecute the work diligently, and (3) complete the entire work ready for use not later than 120 calendar days after receipt of notice to proceed. This time stated for completion shall include completion of all punchlist items and final cleanup of the premises.

3. LIQUIDATED DAMAGES

If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to the Government as liquidated damages, the sum of $230.02 for each day of delay.

If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

If the Government does not terminate the Contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted

4. CONTRACTOR QUALITY

The Contractor is responsible for the quality of construction for all phases of work.

Establish and maintain an effective quality control (QC) system. QC consists of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the

Contracting Officer.

5. SAFETY

Refer to Specification 01 35 26 Governmental Safety Requirements.

6. SUBMITTALS

Refer to Specification 01 33 00 Submittal Procedures.

7. SCHEDULE

Refer to Specification 01 32 01.00 10 Project Schedule.

8. REQUEST FOR INFORMATION

Submit a Request for Information (RFI) when questions arise concerning interpretation, conflicts, omissions, errors, or regulatory violations within the Contract Documents.

Review all RFIs prior to submission to the Contracting Officer or Government’s

Designated QA Representative. The General Contractor is responsible to have a thorough and working knowledge of the entire Contract Documents and to review their subcontractor’s and in-house RFIs for legitimacy and reasonableness. Do not forward questions to the Contracting Officer or Government’s Designated Representative that are easily answerable from a cursory review of the Contract Documents.

Allow 14 calendar days for government review of the RFI. The Government will respond to all RFI's on the RFI form with the Contracting Officer’s signature. If the response to the RFI does not involve a change to the contract, after receipt of the government response, proceed as if the answer to the RFI existed within the Contract Documents. For

RFIs where the government determines a change to the Contract price or time is appropriate, officially close the RFI and refer thereafter as a pending modification.

Comply with the modification requirements.

Use the attached RFI form to submit RFI’s to the Contracting Officer. For tracking purposes, submit an updated RFI tracking log with each new RFI.

9. MEETINGS

Progress Meetings

Contractor shall conduct progress meetings with the Government representative(s).

Contractor shall have all participants at these conferences familiar with the project and authorized to conclude matters relating to the work. Contractor representatives shall include the required the on-site staff. Agenda of progress meetings will include but not limited to:

1) Interface requirements.

2) Time.

3) Sequences.

4) Status of submittals.

5) Status of LEED documentation.

6) Deliveries.

7) Off-site fabrication problems.

8) Access.

9) Site utilization.

10) Temporary facilities and services.

11) Hours of work.

12) Hazards and risks.

13) Housekeeping.

14) Quality and work standards.

15) Changes to the contract.

16) Documentation of information for payment requests.

17) Short Interval Schedule (SIS).

18) Status of RFI’s.

19) Safety.

20) Other topics as required.

Provide minutes for the prior week’s progress meeting prior to each new weekly meeting.

No later than 3 days after each meeting, distribute minutes of the meeting to each party present and to parties who should have been present. Include a brief summary, in narrative form, of progress since the previous meeting and report.

Red Zone Meeting

A pre-initial Red Zone meeting will be held to build a schedule of events necessary to achieve project and fiscal completion within 120 days of the Project Beneficial

Occupancy Date (BOD). The initial meeting identifies key project milestones, responsibilities, and target task completion dates. Particular attention must be given to the

BOD date. The initial Red Zone meeting is held approximately 60 days prior to BOD.

There are three objectives to the initial meeting:

1) Representatives responsible for specific remaining tasks must be identified and be in attendance at the meeting.

2) Representatives in attendance must be able to fully identify remaining work necessary to complete their portion of the scope.

3) Representatives must commit to finishing the task they are responsible for by the agreed date.

The objective of each follow on weekly meeting is to discuss and record actual progress of each task. If a specific task appears to be slipping or occurs earlier than the completion date; means methods and resources will be discussed, identified, and committed to maintain the Red Zone Schedule. The impact to related activities is determined and discussed. The entire team is notified of the potential impact to the remaining work.

Contractor representatives shall include the required the on-site staff.

10. TEMPORARY FACILITIES AND WORK AREA

Temporary Facilities: Refer to Specification 01 57 19.

Designated work area: Refer to Specification 01 57 19.

Additionally, regarding temporary facilities, provide and maintain within the construction area minimum field type sanitary facilities approved by the Contracting Officer and periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into any municipal, district, or commercial sanitary sewer system. Any penalties and / or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times without nuisance. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.

Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.

11. CRANES

All cranes used by the Contractor for construction purposes will require written acceptance for their use by the Contracting Officer's Representative. All requests shall be made seven (7) days in advance of the crane's arrival on the job site and shall include such information as latitude and longitude of the crane location, total operating height, mode of transportation and delivery to the project site, period of use and methods of conforming to all safety and airfield operations procedures.

For additional information regarding the use of cranes during construction, refer to

Specification 01 35 26 and EM 385-1-1 (2014) Safety and Health Requirements Manual.

12. UTILITY OUTAGES AND ROAD CLOSURES

Utility Outages: Refer to Specification 01 11 00.

Road Closures: Refer to Specification 01 14 00.

13. AVAILABILITY AND USE OF UTILITY SERVICES

Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.

Existing utilities are available in the project area. The Contractor is responsible for providing all temporary utilities until permanent utility connections are made. The

Contractor is responsible for providing all connections to existing utilities and metering.

Contractor will provide temporary water supply for construction purposes.

Contractor shall complete Utility Service Agreement with Eglin AFB if temporary utilities are needed. Once utility connections are made, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government, as indicated herein or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia. The current utility rates are as follows:

Electric: $0.12272 per KWh

Natural Gas: $6.57413 MCF

Sewer: $8.30352 per kilo gallons

Water: $3.24276 per kilo gallons

The contractor is to pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor is also to make connections, including meters; and providing transformers; and make disconnections. The water and sewer privatized utility agency, ASUS, will be responsible for making connections to existing domestic water lines for a fee. All domestic water and sewer lines installed, whether temporary or permanent, will have to be inspected or installed by ASUS. ASUS demarcation point is 5 feet outside elevated utility building 9284.

At the Contractors expense and in a manner satisfactory to the Contracting Officer, provide and maintain necessary temporary connections, distribution lines, and meters and meter bases required to measure the amount of each utility used for the purpose of determining charges. Notify the Contracting Officer, in writing, 5 working days before final electrical connection is desired so that a utilities contract can be established. The contractor is to obtain Government approval of their temporary wiring installation prior to the final hot connection.

Before completion of the work and final acceptance of the work by the Government, notify the Contracting Officer, in writing, 5 working days before termination is desired.

The Government will take a final meter reading. The Contractor will be responsible to disconnect service, and remove the meters. Then remove all the temporary distribution lines, meter bases, and associated paraphernalia. Pay all outstanding utility bills before final acceptance of the work by the

Government.

Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.

14. HOURS OF WORK

Refer to Specification 01 14 00.

15. WARRANTY

Refer to Specification 01 78 00.

16. CLOSEOUT

Refer to Specification 01 78 00.

17. ADDITIONAL ENCLOSURES

- Request for Information Form

- ASUS Hydrant Access Permit

- ASUS Temporary Tap Permit

- ASUS Credit Card Payment Form

- ASUS Specifications

- CHELCO Specifications

- Eglin Fire Dept. Specifications

- Eglin Fire Alarm Specifications

- Eglin As-Built Requirements