6_GLEN_15-2203_Form_66.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
GLEN 15-2203 Repair Sanitary Sewer Manholes
Solicitation number
FA255017R1013
Issued by

About this file

AF 66

View the file

Other files

File Type Posted
RFI_1_Questions_and_Responses.pdf PDF
Schriever_2013_I-I_Study.pdf PDF
2_GLEN_15-2203_SOW_25_Apr_17.pdf PDF
5_Design_Guide_Version_March_2016.pdf PDF
8_WD_CO20160012.pdf PDF
7_23-DD_1354_August_2013.pdf PDF
1_FA255017R1013_1442.pdf PDF
4_SAFB_Overarching_Environmental.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALS (Paving IDIQ)PROJECT NO.PROJECT NAMESOLICITATION /CONTRACT NUMBER
GLEN 15-2203Repair Sanitary Sewer Manholes Basewide
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.CERTIFICATE OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALREMARKS
GENERAL
1Approved Form 103, BCE Work Clearance RequestXPrior to commencement of workWith Map Accurately Showing Work Area
2Project Specific MSDS SheetsXNTP + 5 daysPrior to Mobilization
3Form-3064 Contract Progress ScheduleXBid Submittal
4Form-3065 Contract Progress ReportXEach Draw
5Health, Safety, and Environment Plan(s)1NTP + 5 days
6Traffic Control Plans - For Each Phase of Construction Including Temporary Fencing Plan11NTP + 10 days
7Contractor's QA/QC Plan1NTP + 5 days
8Business Telephone and Directory1NTP + 5 days
9Site Visit Meeting Minutes1NTP + 5 days
10Construction Schedule1NTP + 5 days and weekly updates
11Salvageable Material1NTP + 5 days
12Monthly Solid Waste Reporting1Monthly Reports
13Hydrant Connection request110 days prior to any work
14Utility Outage Request110 days prior to the proposed outage
15Traffic Change Request110 days prior to commencing with construction activities
CIVIL
16Current Backflow Preventer Inspection Cert.1110 days prior to any work
17Joint layout Plan110 days prior to any work
18Select Fill / Class 6 Sieve Analysis11NTP+5 days
19Select Fill Chem. Analysis (Where Applicable)11NTP+5 days
20Soil Compaction Test Results11Within 3 days after test results are made available
21Concrete Mix Design per ACI11NTP+5 daysIncluding Break History
22Concrete Batch Tickets, Each Truck11Following day
23Concrete 7 and 28 Day ACI Compressive Strength Test Results11Within 3 days after test results are made available
24Product Data - Expansion Joint Sealant11NTP+5 days
25Concrete Aggregate Sieve Analysis11NTP+5 days
26Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints, and Asphalt Crack Sealant Materials11NTP+5 days
27Sampling and Testing, Aggregate Base - Sieve Results, Field Density Tests11Within 3 days after test results are made available
28Asphalt Mix Design1NTP+5 days
29Asphalt Test Reports - Aggregates11Within 3 days after test results are made available
30Pipe and Headwwall/Flared End SectionsXXXNTP+5 days
31Street Signs and PostsXXXNTP+5 days
32Guardrail Materials and Method of InstallationXXXNTP+5 days
33Asphalt Cement Binder Certificates11NTP+5 days
34Product Data - Paint for Pavement Markings and Glass Beads11NTP+5 days
CLOSEOUT
35O&M Maintenance data, manuals and Manufacturer's Warranties1Install + 4 days
36Factory and Field Test Certificates, Logs and Test Results11Before Acceptance
37DD1354 Transfer and Acceptance of DoD Real Property Form11Before Acceptance
38As Built Submittal per AEC Standards on CD3Final + 7 days

Sheet2

Sheet3

File details come from the government source that posted it. Updated .