QUESTION AND ANSWER TEMPLATE
Solicitation: FA2521-22-B-0006 Project Number: DBEH 21-1507
Project Description: Repair Tower 81559, Cape Canaveral SFS, FL
Contractor Name: Ram Telecom
POC: Steve Hertel
1. IFB Section Paragraph
SOW/Technical Specification/Drawings paragraph/page
Other (Specify) X
Can we obtain the latest structural analysis or structural design information (including member sizes, etc.) of the tower? Or any other as‐builts from past repairs?
Response: Use information as provided in spec and drawing.
2. IFB Section Paragraph
Can the bid be extended to allow for review of any new documentation the Space Force can provide from past repairs?
Response: use information as provided in spec and drawing.
3. IFB Section Paragraph
Are you looking for a bid strictly based upon the items/fixes provided? OR can we value engineer a better solution for these areas?
Response: Drawing does not dictate means and methods for repairs, value engineering is welcomed.
4. _IFB Section Paragraph
Other (Specify) X
Question: Do you have foundation/geotechnical information for the tower? TIA‐222‐H requires that for any modification a full analysis of the foundation is incorporated.
Response: Geotechnical information is not available.
Project Number: DBEH 21-1507
5. IFB Section Paragraph
SOW/Technical Specification/Drawings paragraph/page S501
Question: Can you provide at a minimum the thickness of the corroded pipe members? We need to know the thickness of structural pipes at a minimum as depicted in the drawings. A 1/8” weld is being specified, which is smaller than the typical minimum structural weld of 3/16”. I am not sure if the pipes we are proposing to weld to are thick enough to even accept a weld or if we risk more damage to them by welding.
Response: Use information as provided in spec and drawing.
6. IFB Section Paragraph
Other (Specify) X
Question: Will encasing the footing be allowed as previously performed? Special inspections?
Response: Per drawing, the footings do not require encasing. However, if requirement is identified, it will be allowed.
7. IFB Section Paragraph
SOW/Technical Specification/Drawings paragraph/page S902 photo 4
Question: Will all pipes that are installed incorrectly be required to be corrected? I.e. weep holes facing up?
Response: Yes, all new materials will need to be installed in corrected performance manner.
8. IFB Section Paragraph
Question: Special requirements for cranes. Height requirements or restrictions, FAA notification? If so who will prepare documentation and what is the timeline?
Response: FAA notification is not required for this project. Crane may not exceed 150' horizontal surface, and will be restricted during equipment operations. Shortest equipment needed should be used.
Project Number: DBEH 21-1507
9. IFB Section Paragraph
Other (Specify) X
Question: Any special preparation or cautions needed on site. i.e. keeping special clearances in any locations, designated staging areas, restrooms, will power be provided or do we provide our own?
Response: Restrooms will not be provided. Power may be provided, if an accessible point is located.
Staging on-site will be allowed. No particular clearance but all government assets must be protected. The instruments have safety and property clearance restrictions.
10. 1
11. 1
12. 1
Any restrictions on open flame i.e. welding/cutting torch or will this all need to be cut out with a plasma cutter or saw then grind.
Response: All burning requirements must submit and gain a burn permit from CCSFS Fire Chief. A three notice is required.
IFB Section Paragraph
Question:
Estimated Timeline for SF remove tech equipment from tower. (Down time) Estimated Timeline for tower to be in non‐commission status (CX timeline) EstimatedTimeline to reinstall all equipment Response: All removals are subject to constraints at time of operation. Recommend planning on one day to accomplish any particular move, or resinstallation. Tower down time will be dependent on operations.
IFB Section Paragraph
Other (Specify) Solicitation
Question: 000101 FUNDING for CLIN 0001 Page 4 of 55 Is this requirement funded for this fiscal year? If not will it be for early 2023?
Response: See solicitation guidance.
IFB Section Paragraph
Other (Specify) X
Question: Can the Contracting Office provide projected launch schedules through December 2022? Can they provide link to published rain schedule mentioned at the site walk?
Response: Link to published launches is found at spaceflightnow.com.